Emaar Properties · Dubai Creek Harbour
Altan at Dubai Creek Harbour Construction Updates
The Dated RERA Record Beneath Green Gate's 53-Floor Tower
Altan at Dubai Creek Harbour recorded 11.06% at its 02 July 2026 RERA inspection, an early record documenting piling, foundations and first structure in Green Gate.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Altan at Dubai Creek Harbour at a Glance
Altan at Dubai Creek Harbour is Emaar's 479-residence project in Green Gate, entered in the DLD register on 24 March 2025 as project 3608 and started on 10 June 2025. Twelve and a half months after that start, the 02 July 2026 inspection put the build at 11.06%. One feature shapes how every figure on this page reads: the tower of B + G + 3 podiums + 53 floors and the park-facing 3 bedroom townhouses share a single DLD progress reading, so each percentage describes both parts at once rather than either one alone.
3608
Active
10 June 2025
479 residential units
53,111.17 sq m
31 July 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Altan at Dubai Creek Harbour Construction Update Timeline
Two dated inspections make up the Altan record so far: 9.28% on 17 March 2026, when the notes still listed mobilization as ongoing beside advanced piling and foundations, and 11.06% on 02 July 2026, when structure works joined them. The March entry also shows a previous reading of 6.73% with no date attached, so it sits on the track as an unlabelled dot and has no table row. The two readings sit close together near the start of the bar, so only the latest carries a visible label; each row below links the full monthly update for its cycle.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 11.06% | 02 July 2026 | View the July 2026 update |
| March 2026 | 9.28% | 17 March 2026 | View the March 2026 update |
Pace Analysis
How Fast Altan at Dubai Creek Harbour Has Been Built
With two dated readings, Altan's record so far yields one measured interval, set here against two labelled arithmetic yardsticks in the text below:
- Mar 2026 to Jul 2026: piling, foundation and early structure, 9.28% to 11.06%About 0.5 points per month
A single interval is a starting slope, not yet a curve. Between 17 March and 02 July 2026 the Altan reading rose 1.78 points in 107 days, about 0.5 points per month, across a cycle in which the inspection notes moved from mobilization and piling toward foundation and structure works progressing together. Two benchmarks give that slope scale, and neither is a forecast: 11.06% spread over the 387 days since the 10 June 2025 start, assuming 0% on that date, averages about 0.9 points per month, while closing the remaining 88.94 points by the DLD completion date of 31 July 2029 would average about 2.4 points per month from the July reading. The 6.73% previous reading shown beside the March figure has no date, so it adds a dot to the track but no slope to this analysis. For an end user, the register still lists 31 July 2029 as of 02 July 2026, with handover scheduled for Q3 2029. For an investor, the practical point is that the construction-linked instalments on Emaar's launch plan, starting at 20%, wait on recorded milestones rather than calendar dates, so each new dated reading shows how far the next of those payments still sits from the site.
Get the Next Inspection Figure First
Tell me you are tracking Altan at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Altan at Dubai Creek Harbour
An 11.06% reading means more once you see the finished project it is counting toward. The full project guide covers what Altan buyers are tracking on this page:

Altan at Dubai Creek Harbour: A 53-Floor Green Gate Tower
Altan at Dubai Creek Harbour pairs a 53-floor Emaar apartment tower with park-facing three bedroom townhouses, 479 residences in total.
View the Altan at Dubai Creek Harbour Project GuideConsidering an Early-Stage Entry?
Emaar is still releasing units at Altan while the record shows foundations and first structure, and availability changes from one inspection cycle to the next. If the record on this page is what brought you here, ask me for current availability before settling on a layout.
Ask About Remaining Availability on WhatsAppStage Record
Altan at Dubai Creek Harbour Build Stages, Mapped to the Inspections
Each stage below is tied to the dated window it occupies in Altan's own record, so the first two carry the March and July 2026 readings while the three still ahead are named from the B+G+3P+53F+2MECH+R description filed with project 3608.
Mobilization, Enabling Works and Piling
From the 10 June 2025 start to the 17 March 2026 inspection at 9.28%: enabling works completed, mobilization still ongoing, piling and foundations at advanced stages, substructure just begun.
Foundations Into First Structure
The 02 July 2026 inspection recorded 11.06%, with piling, foundation and structure works progressing together and the mobilization entry no longer listed.
Podium and Tower Frame
Not yet reached in any dated reading: the basement, ground and three podium levels, then 53 residential floors, two mechanical levels and the roof.
Enclosure, Fit-Out and Townhouses
Glazing and aluminium cladding on the tower, apartment fit-out, and the park-facing 3 bedroom townhouses that share the tower's single DLD reading.
Completion and Handover
The register lists 31 July 2029 for project 3608 and handover is scheduled for Q3 2029; the launch plan ties its final 20% instalment to 100% construction completion.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Altan at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Altan at Dubai Creek Harbour
This page is one of four project resources that together cover a Altan at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Altan at Dubai Creek Harbour Construction Updates
This page: Altan's dated RERA readings, 9.28% in March 2026 and 11.06% in July 2026.

Altan at Dubai Creek Harbour Golden Visa in the Green Gate District
Altan at Dubai Creek Harbour, Emaar Properties' 479-residence project, qualifies at three of four layouts; its 1 bedroom apartment sits below.
Read the Altan at Dubai Creek Harbour Golden Visa Guide
Altan at Dubai Creek Harbour: The Emirates NBD Escrow for 479 Homes
Altan at Dubai Creek Harbour escrows 479 units at Emirates NBD under DLD project 3608, with 11.06% certified in July 2026.
Verify the Altan at Dubai Creek Harbour Escrow AccountApproaching Handover
Between 11.06% and Handover: What Altan at Dubai Creek Harbour Buyers Should Do Now
At 11.06% on 02 July 2026, the Altan record covers piling, foundations and first structure, so the decisions open to a buyer now concern payments and paperwork rather than handover. The 4th instalment on Emaar's launch plan falls due at 20% construction completion, 8.94 points above the July reading, and the three checks below are easier to settle before that reading is recorded than after a payment request arrives.
First, confirm that every payment you make goes to the DLD-registered escrow account for project 3608 with Emirates NBD Bank (P.J.S.C); the escrow account page for Altan at Dubai Creek Harbour shows how to check it against the official record.
Second, read how your SPA defines the 20% trigger, as a recorded construction reading or as the Feb 2027 date Emaar estimated at launch, and follow each new dated figure in the inspection timeline on this page.
Third, if residency is part of your plan, check your layout against the property threshold in the Golden Visa guide for Altan at Dubai Creek Harbour while the purchase is still off-plan.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
Altan is building in Green Gate while other parts of the masterplan are already finished and lived in. These three pages set its 11.06% reading of 02 July 2026 against the market, the community and the developer:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Altan at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Altan at Dubai Creek Harbour is an active DLD-registered project, number 3608, recorded at 11.06% construction progress at the RERA inspection of 02 July 2026, with piling, foundation and structure works progressing. Both dated readings are set out in the inspection timeline above.
The 02 July 2026 inspection recorded 11.06% for Altan at Dubai Creek Harbour, up 1.78 points from the 9.28% reading of 17 March 2026, and listed enabling works as completed. The cycle's full record is in the July 2026 construction update for Altan.
Altan at Dubai Creek Harbour moved from 9.28% on 17 March 2026 to 11.06% on 02 July 2026, a gain of 1.78 points in 107 days, or about 0.5 points per month as measured. As labelled benchmarks rather than forecasts, the average since the 10 June 2025 start is about 0.9 points per month assuming 0% on that date, and reaching 100% by 31 July 2029 would take about 2.4 points per month from the July reading. The full breakdown is in the pace analysis above.
The DLD register lists 31 July 2029 as the completion date for Altan at Dubai Creek Harbour, project 3608, as of the 02 July 2026 inspection, and handover is scheduled for Q3 2029. At that inspection the project stood at 11.06%, and this page's record is updated as each later dated reading is recorded.
The DLD register lists 479 units for Altan at Dubai Creek Harbour, divided between 1 to 3 bedroom tower apartments and a limited number of park-facing 3 bedroom townhouses, with a total built area of 53,111.17 sq m. Both parts are tracked under one progress figure, 11.06% as of 02 July 2026.
Construction at Altan at Dubai Creek Harbour started on 10 June 2025, according to the DLD register, which shows the project registered on 24 March 2025. The first dated reading followed on 17 March 2026 at 9.28%, documented in the March 2026 construction update for Altan; the 6.73% previous reading shown beside it carries no date.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Altan at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.