DAMAC Properties · DAMAC Islands 2
Antigua at DAMAC Islands 2 Construction Updates
Every Dated Register Reading for 468 Island Cluster Homes in Dubailand
Antigua at DAMAC Islands 2 read 0.32% in the DLD project register on 16 September 2026, the first move off zero for its 468 low-rise homes.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Antigua at DAMAC Islands 2 at a Glance
Antigua at DAMAC Islands 2 is DAMAC Properties' 468-unit cluster of G+1 and G+2 townhouses and villas, registered with the Dubai Land Department as project 4369 on plot 21569 in Al Yelayiss 1. Its record is young: construction started on 15 July 2026 by the register's date, and the two readings filed so far, 0% on 28 January 2026 and 0.32% on 16 September 2026, are the baseline every later figure will be measured against. Because Antigua is one of eight island clusters sharing the DAMAC Islands 2 masterplan, this register entry is the one place its own progress can be read apart from the wider community, on the way to a handover the developer anticipates in June 2030.
4369
Active
15 July 2026
468 residential units
83,137.75 sq m
31 December 2030 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Antigua at DAMAC Islands 2 Construction Update Timeline
The Antigua record holds two dated readings in the Dubai Land Department project register: 0% on 28 January 2026, when the inspection report found no construction activity on site, and 0.32% on 16 September 2026, with mobilization on going and enabling works at an early stage. That 0.32-point spread across 231 days is narrow, but it is the first change the register has logged for project 4369. The track below plots both readings, and each table row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 0.32% | 16 September 2026 | View the September 2026 update |
| January 2026 | 0% | 28 January 2026 | View the January 2026 update |
Both monthly updates open with a project rendering rather than a site photograph; the inspection detail for each date sits inside the update itself.
Pace Analysis
How Fast Antigua at DAMAC Islands 2 Has Been Built
With two register readings on file, Antigua's pace is arithmetic over a short window rather than a curve, and the result depends on whether it is counted from the January 2026 inspection or from the registered construction start:
- Jan 2026 to Sep 2026: pre-start baseline to enabling works, 0% to 0.32% over 231 daysAbout 0.04 points per month
- 15 Jul 2026 start to 16 Sep 2026: mobilization and enabling works, 0.32 points over 63 daysAbout 0.15 points per 30 days
The shape of the Antigua record is a long flat line followed by a first small step. The 28 January 2026 reading was taken about five and a half months before the register's 15 July 2026 construction start, so most of the 231-day window between the two inspections passed before works began; measured from the start date instead, the same 0.32 points spread over 63 days, about 0.15 points per 30 days. Neither rate says anything about how quickly the concrete frames of 468 low-rise homes will rise, because enabling works move the percentage slowly by nature. What the dates do fix is the size of the task: 99.68 points remained after the 16 September 2026 reading, and closing them by the June 2030 anticipated handover, about 45 months later, implies an average of roughly 2.2 points per month. That figure is arithmetic on the stated dates, not a forecast. For an end user it means the record will say little about delivery timing until foundations appear; for an investor it sets a benchmark that each of the next readings can be measured against.
Get the Next Inspection Figure First
Tell me you are tracking Antigua at DAMAC Islands 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Antigua at DAMAC Islands 2 at DAMAC Island 2
A 0.32% reading on 16 September 2026 only makes sense next to what it measures: 468 townhouses and villas from 4 to 6 bedrooms. The project guide covers what this record is tracking toward:

Antigua at DAMAC Islands 2: Freehold Townhouses and Villas
Antigua at DAMAC Islands 2 is a freehold cluster of 468 homes, from four bedroom townhouses to six bedroom luxury villas.
View the Antigua at DAMAC Islands 2 Project GuideConsidering an Early-Stage Entry?
Availability at Antigua shifts as DAMAC releases and sells homes across the cluster, and an enabling-stage entry leaves the full instalment schedule ahead of you. If this record is what brought you here, ask me which home types are still open before you choose one.
Ask About Remaining Availability on WhatsAppStage Record
Antigua at DAMAC Islands 2 Build Stages, Mapped to the Inspections
Only two of the five stages below carry real dates so far, which is itself the clearest reading of where Antigua stands: a 0% baseline on 28 January 2026 and enabling works from the 15 July 2026 start to the 0.32% of 16 September 2026. The three later stages follow the scope written into the inspection reports and will take dates as readings arrive.
Pre-Start Baseline
The 28 January 2026 inspection found no construction activity on plot 21569, and the DLD register logged 0% as Antigua's opening entry.
Mobilization and Enabling Works
From the register's 15 July 2026 construction start, mobilization and early enabling works carried the reading to 0.32% by the 16 September 2026 inspection.
Foundations Across the Cluster
Neither report to date lists foundation works; their first appearance will mark the close of enabling works for Antigua's 468 homes.
Concrete Frames and Blockwork
The inspection reports scope a concrete structure with block walls for every G+1 and G+2 townhouse and villa; no reading has reached this stage.
Finishes and Handover
Internal and external finishes close the build ahead of the developer's anticipated June 2030 handover; the register's registered completion date is 31 December 2030.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Antigua at DAMAC Islands 2's own record.
Buyer Position
Tracking Your Position at Antigua at DAMAC Islands 2
This page is one of four project resources that together cover a Antigua at DAMAC Islands 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Antigua at DAMAC Islands 2 Construction Updates
This page: every dated DLD register reading for Antigua, from the 0% January 2026 baseline onward.

Antigua at DAMAC Islands 2 Golden Visa: Four Home Types
Antigua at DAMAC Islands 2, DAMAC's 468-unit cluster, qualifies at every type from the 4 bedroom townhouse to 6 bedroom villa.
Read the Antigua at DAMAC Islands 2 Golden Visa Guide
Antigua at DAMAC Islands 2 Escrow, Checked Against Dubai REST
Mashreq holds Antigua at DAMAC Islands 2 escrow, DLD project 4369: 468 units, 0.32% certified in September 2026.
Verify the Antigua at DAMAC Islands 2 Escrow AccountApproaching Handover
Between 0.32% and Handover: What Antigua at DAMAC Islands 2 Buyers Should Do Now
At 0.32% on 16 September 2026, Antigua will pass from enabling works to a visible structure while most of its payment plan is still running: the 55% share falls due across 47 monthly instalments from month 3 to month 49 after the sale, whatever the register reads. The heavier 3% instalments land at the 6th, 12th, 18th and 24th payments, years before any handover notice, so the three steps below belong in the first months after purchase, not at completion.
First, check the regulated account before every transfer; the Antigua at DAMAC Islands 2 escrow verification steps show how to match project 4369 to its Mashreq Bank PSC account.
Second, set the dates in your sale and purchase agreement beside each new reading in the Antigua inspection timeline, so the 25% due on completion is judged against recorded progress rather than brochure timing.
Third, if residency is part of your plan, read the Antigua at DAMAC Islands 2 Golden Visa eligibility notes early, since every home type is priced above the AED 2M ≈ USD 545K threshold.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Island 2 Structure
Antigua is one of eight island clusters in a 20 million sq ft Dubailand masterplan, so its register record reads best beside the listings, the community plan, and the developer behind them:

DAMAC Island 2 Properties for Sale
Explore DAMAC Islands 2 properties for sale: lagoon-front villas and townhouses with flexible payment plans and resort-style island living.
See DAMAC Island 2 Properties for Sale
DAMAC Island 2 Community Overview
Read the DAMAC Islands 2 guide: eight island-themed clusters of lagoon-front villas and townhouses, with masterplan and payment plans.
Explore the DAMAC Island 2 Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Antigua at DAMAC Islands 2 Construction Updates Frequently Asked Questions
Antigua at DAMAC Islands 2 is an active DLD-registered project (number 4369) in its enabling works stage, with the Dubai Land Department project register reading 0.32% at the inspection dated 16 September 2026. That report records mobilization on going and enabling works at an early stage, about two months after the register's 15 July 2026 construction start. Both dated readings are listed in the dated inspection timeline above.
The DLD project register moved from 0% at the inspection dated 28 January 2026 to 0.32% at the inspection dated 16 September 2026, a rise of 0.32 points across 231 days, or about 0.04 points per month. It is the only change on record so far, and the detail behind it is set out in the Antigua September 2026 inspection record.
Construction at Antigua at DAMAC Islands 2 is scheduled to take just under four years, from the register's 15 July 2026 start to the developer's anticipated completion in June 2030, which is the handover date buyers are given. The DLD project register carries a registered completion date of 31 December 2030, about four and a half years after the start and later than the developer's date; neither date had passed as of September 2026, when the register read 0.32%.
The Dubai Land Department register listed 468 units for Antigua at DAMAC Islands 2 (project 4369) as of September 2026, the same total DAMAC Properties quotes for the cluster. The inspection reports describe them as G+1 and G+2 townhouses and villas, and the price list spreads them across 4 and 5 bedroom townhouses, 5 bedroom twin villas and 6 bedroom luxury villas; no per-type unit count is published.
Construction at Antigua at DAMAC Islands 2 started on 15 July 2026, according to the DLD project register. The earliest reading on file, 0% at the inspection dated 28 January 2026, was taken before that date with no construction activity found on site, so the first reading after the start is the 0.32% of 16 September 2026; the opening entry is kept in the Antigua January 2026 inspection record.
Not as of the latest record: the inspection dated 16 September 2026 notes mobilization on going and enabling works at an early stage, lists no foundation or structural works, and sits beside a register reading of 0.32%. Foundations for the 468 G+1 and G+2 homes are the next stage to look for in the Antigua stage record above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Antigua at DAMAC Islands 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.