Atelis at d3 by Meraas in Dubai Design District construction updates cover image featuring a project rendering of the waterfront residential tower and surrounding high-rise buildings in Dubai - Presented by Tohid Fetrat

Dubai Design District · Meraas

Atelis at d3 Construction Updates

The Verified Build Record on the d3 Creekside Shoreline

Atelis at d3 recorded 0.96% at its 06 July 2026 RERA inspection, an early record where enabling works on the Creekside plot are the only certified activity.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0.96%Construction Progress
06 July 2026Latest RERA Inspection
280 residential unitsTotal Units
Project 3750DLD Registration

Construction Snapshot

Atelis at d3 at a Glance

Atelis at d3 is Meraas's 280-residence tower on the Creekside shoreline of Dubai Design District, carried on the Dubai Land Department register as project 3750. Construction was registered as started on 14 August 2025, and the inspection of 06 July 2026 certified 0.96%, which puts the whole of the record so far inside enabling works. Because d3 was a working district of offices, studios and galleries years before this plot was registered, the figures below track the delivery of one building rather than the build-out of a community around it.

DLD Project Number

3750

Project Status

Active

Construction Start

14 August 2025

Total Units

280 residential units

Total Built-Up Area

38,127.02 sq m

Registered Completion Date

14 August 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Atelis at d3 Construction Update Timeline

Two readings sit in this record and only one of them carries a date: 0.06% at a previous inspection the register leaves undated, and 0.96% on 06 July 2026. The 0.90 point difference between them is therefore a gain that can be stated but not a rate that can be calculated, which is why the track below labels a single dot. The row underneath links the full July 2026 inspection report.

Inspection MonthConstruction ProgressInspection DateFull Update
July 20260.96%06 July 2026View the July 2026 update

Pace Analysis

How Fast Atelis at d3 Has Been Built

With one dated reading on file, Atelis at d3 does not yet have an inspection-to-inspection pace. What the record does support is the arithmetic below: one movement the register leaves undated, and two divisions over spans it does date.

  • Previous undated reading to 06 Jul 2026: 0.06% to 0.96%, enabling worksPlus 0.90 points, no rate
  • 14 Aug 2025 registered start to 06 Jul 2026 inspection: 0.96% across about 10.7 monthsAbout 0.1 points per month
  • 06 Jul 2026 to the 14 Aug 2029 registered completion: 99.04 points across about 37 monthsAbout 2.7 points per month

Read those three lines in order and the shape of this record is honest about its own limits. The first is a movement without a clock, because the register publishes no date against the 0.06% reading. The second divides a certified figure by a registered span and produces roughly 0.1 points per month, which is what a deep-basement plot in enabling works looks like when surveys, hoarding and excavation move a percentage barely at all. The third is not a prediction: it is the same division run over the remaining window, and it says only that 99.04 points and about 37 months currently sit between 06 July 2026 and 14 August 2029. Neither computed figure is a forecast of what the next inspection will record, and this page will not carry one until the readings themselves establish a cadence. For an investor that means the entry case here rests on registered dates, escrow protection and the payment calendar rather than on a delivery curve, and for an end user it means the useful discipline is following each reading as it publishes.

Get the Next Inspection Figure First

Tell me you are tracking Atelis at d3 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Atelis at d3 at Dubai Design District

A 0.96% reading only means something once you know what the remaining 99.04 points are meant to deliver. The full project guide covers exactly that:

Waterfront exterior view of Atelis at d3 featuring a sculpted residential tower with curved balconies, landscaped promenade, palm-lined walkways, and contemporary architecture in Dubai Design District. Presented by Tohid Fetrat.

Atelis at d3: Meraas's 45-Floor Tower in Dubai Design District

Atelis at d3 is a Meraas waterfront tower of 280 residences, designed by Skidmore, Owings & Merrill in Dubai Design District.

View the Atelis at d3 Project Guide

Considering an Early-Stage Entry?

Buying while the record still reads 0.96% buys the longest payment runway this project will ever offer, and availability shifts between inspection cycles. If the record on this page is what brought you here, ask me what is still open before the next dated installment period.

Ask About Remaining Availability on WhatsApp

Stage Record

Atelis at d3 Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is placed against what project 3750 has actually recorded. Two stages carry dates; the rest are named as what the 3B+G+45+R tower still has ahead of it, because no inspection has certified them yet.

Jun 2025 to Aug 2025

Registration, Escrow, and Registered Start

Project 3750 was registered with the DLD on 18 June 2025, its escrow account was opened with National Bank of Ras Al-Khaimah (P.S.C), and construction was registered as started on 14 August 2025.

Current PhaseAug 2025 onward, 0.96% at last reading

Enabling Works on Plot 452

The 06 July 2026 inspection found enabling works progressing at the site on plot 452 in Zaabeel Second, and logged the progress status as Enabling Works - Progressing at 0.96%.

Next in the 3B+G+45+R sequence

Three Basement Levels

The three basement levels for services and parking are the first structure the record is waiting on. Nothing in the 06 July 2026 report certifies substructure work as started.

Not yet recorded

Ground Amenity Floor and 42 Residential Floors

Above the basements sit the ground floor amenity spaces connected to the main lobby and the 42 residential floors holding the 280 residences. No inspection has recorded activity at this stage.

Registered for 14 Aug 2029

Rooftop, Finishing, and Handover

The rooftop level, finishing and commissioning close the sequence against the 14 August 2029 registered completion date, with 99.04 percentage points still to be certified from the July 2026 reading.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Atelis at d3's own record.

Buyer Position

Tracking Your Position at Atelis at d3

This page is one of four project resources that together cover a Atelis at d3 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Atelis at d3 by Meraas in Dubai Design District construction updates cover image featuring a project rendering of the waterfront residential tower and surrounding high-rise buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Atelis at d3 Construction Updates

This page: every recorded RERA reading for Atelis at d3, starting from 0.96% in July 2026.

Atelis at d3 by Meraas in Dubai Design District Golden Visa concept with a UAE Golden Visa card beside the waterfront residential tower and creek view in Dubai - Presented by Tohid Fetrat

Atelis at d3 Golden Visa From the Entry One Bedroom

Meraas's Atelis at d3, a 280-residence Dubai Design District tower, qualifies at all six tiers, sky villa and penthouse included.

Read the Atelis at d3 Golden Visa Guide
Atelis at d3 by Meraas in Dubai Design District escrow account protection concept with shield and padlock icons beside the waterfront residential tower in Dubai - Presented by Tohid Fetrat

Atelis at d3 Escrow: Meraas in Dubai Design District

Meraas lists Atelis at d3 as project 3750, 280 units escrowed with National Bank of Ras Al-Khaimah, 0.96% certified July 2026.

Verify the Atelis at d3 Escrow Account

Approaching Handover

Between 0.96% and Handover: What Atelis at d3 Buyers Should Do Now

At enabling works there is no building to inspect and no milestone to celebrate, so the work that protects an Atelis at d3 buyer is documentary. It is also time-bound in a way that catches people out: this payment plan is calendar dated rather than milestone linked, so the December 2026, May 2027 and September 2027 installments fall due on their dates whether or not a new inspection figure has published in between.

First, confirm where your money lands before each dated transfer; the Atelis at d3 escrow account page shows the registered account for project 3750 and how to check it against the DLD record yourself.

Second, if residency is part of why you are buying, settle eligibility now rather than near handover, because every tier here starts above the threshold set out in the Atelis at d3 Golden Visa guide.

Third, follow the record reading by reading instead of by rendering; the July 2026 inspection record for Atelis at d3 is the baseline every later figure will be measured against.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Design District Structure

A build record is only half the picture; the other half is what is already standing around it. These three pages put the 0.96% reading in its district, market, and developer context:

Dubai Design District d3 properties for sale with aerial views of modern towers, waterfront surroundings, landscaped spaces and connected road networks in Dubai. Presented by Tohid Fetrat

Dubai Design District: d3 Apartments and Penthouses by Meraas and Select Group

Dubai Design District has 3 projects of apartments and penthouses for sale along Dubai Creek, minutes from Downtown Dubai and DIFC.

See Dubai Design District Properties for Sale
Aerial skyline view of Dubai Design District (d3) with illuminated residential towers, waterfront lagoon, and Downtown Dubai skyline featuring Burj Khalifa in the background. Presented by Tohid Fetrat.

Dubai Design District Community Overview

Read the Dubai Design District (d3) guide: Meraas' design-led waterfront district with freehold residences and creative spaces.

Explore the Dubai Design District Community
Meraas developer Dubai – luxury residential towers including Atélis, Jumeirah Residences, The Edit, Verve City Walk, and Bluewaters Bay

Meraas: Lifestyle Destinations From City Walk to Port de La Mer

Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.

View the Meraas Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Atelis at d3 Construction Updates Frequently Asked Questions

Atelis at d3 is an active DLD-registered project (number 3750) at the enabling works stage, recorded at 0.96% at the RERA inspection of 06 July 2026, with the progress status logged as Enabling Works - Progressing. The full record is in the inspection timeline above.

The 06 July 2026 inspection recorded 0.96% construction progress, a gain of 0.90 percentage points on the previous reading of 0.06%. That previous reading carries no published date in the register, so the gain can be stated as a gain but not converted into a monthly rate. The full report is in the July 2026 construction update.

Only one dated reading exists, so no inspection-to-inspection pace can be calculated for Atelis at d3. Measured instead against the registered construction start of 14 August 2025, the 0.96% certified on 06 July 2026 averages about 0.1 percentage points per month across roughly 10.7 months. That figure is arithmetic over a named span, not a forecast of what later stages will record. The working is in the pace analysis above.

The registered completion date for project 3750 is 14 August 2029, and the developer's payment plan places handover in August 2029 with the final 25% installment due then. The 06 July 2026 inspection recorded 0.96%, leaving 99.04 percentage points to be certified inside that window, and this page's record is updated as each inspection publishes.

Atelis at d3 holds 280 residences in a single tower configured as 3B+G+45+R: three basement levels for services and parking, a ground floor of amenity space connected to the main lobby, 42 residential floors, and a rooftop level. No total built-up area is published on this page, because the area figure recorded against project 3750 is not labelled in the source record as either plot area or built-up area.

Construction was registered as started on 14 August 2025, eight weeks after the project itself was registered with the Dubai Land Department on 18 June 2025. The first dated inspection reading, 0.96% on 06 July 2026, is documented in the Atelis at d3 July 2026 inspection report.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Atelis at d3 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.