Emaar · Rashid Yachts & Marina · Construction Update
Baystar by Vida Construction Update - June 2026
June 2026 Inspection Records Baystar by Vida at 6.3% Construction Progress in Rashid Yachts & Marina
Enabling works and piling were progressing on site at Baystar by Vida when the independent RERA inspection of 16 June 2026 recorded 6.3 percent construction progress.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Baystar by Vida Construction Snapshot
A 5.88 point rise over the previous DLD reading of 0.42% places Baystar by Vida at the opening of the enabling and foundations band, where the record measures ground preparation and piling long before either tower rises.
Baystar by Vida by Emaar Properties
4002
Active
6.3%
16 June 2026
24 December 2025
319 residential units
35,571.79 sq m
31 December 2029
Data source: RERA inspection conducted on 16 June 2026 (Independent Progress Monitoring Report), tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is a developer rendering of the completed project, not a photograph of the site. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Baystar by Vida Construction Progress Summary
Just under six months after construction formally started on 24 December 2025, the 16 June 2026 inspection moved Baystar by Vida from a previous reading of 0.42% to 6.3%, a 5.88 point gain. The DLD record gives no date for the earlier reading, and the inspection notes place all recorded work in enabling and piling, the ground stage that comes before any tower frame.
- DLD registration as project 4002 on 28 July 2025
- Construction start recorded on 24 December 2025
- Escrow trust account on record with Abu Dhabi Commercial Bank
- Enabling works on plot 654, status Enabling Works - Progressing
- Piling works, noted as progressing at the 16 June 2026 visit
- Foundations and structural frame for Tower 1 (G+P+20, 177 units)
- Foundations and structural frame for Tower 2 (G+P+16, 142 units), plus 9 ground-floor retail units
- Registered completion on 31 December 2029, inside the Q4 2029 handover window
Payment Linked Progress
What 6.3% Progress Means for Baystar by Vida Buyers
The Baystar by Vida launch schedule of record lists its instalments against dates: 10% on booking, seven instalments of 10% dated September 2025 to October 2028, and a final 20% in December 2029. With the build at 6.3%, almost all of that schedule runs ahead of the construction it funds, so four checks matter most at this stage.
Verify the escrow account
Every instalment should go only to the DLD regulated escrow account for project 4002, which the June 2026 record lists with Abu Dhabi Commercial Bank as trust bank. Baystar by Vida escrow account verification sets out the check; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA against the dated schedule
Compare the instalment dates in your sale and purchase agreement with the launch schedule of record, including the dates that fell before this inspection, and note which payments your SPA ties to dates and which to progress. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
Oqood is the DLD interim register for off plan sales, and registration against project 4002 is completed on payment of the 4% DLD registration fee. Request the certificate and check that the unit number and price it records match your SPA.
Track the move past piling
After piling come foundations and then the frames of both towers. The Baystar by Vida construction updates hub records each new reading, so a cycle that stalls at the enabling stage is visible early.
General framework, not legal advice: instalment triggers, registration steps, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 6.3%?
Entering at the enabling stage trades certainty for runway: the recorded works are enabling and piling, the delivery horizon is long, and the entry price is set years before the finished apartment can be inspected. Every payment goes to the DLD-registered escrow account for project 4002, released against certified construction progress.
- An independent inspection record already exists: 6.3% on 16 June 2026
- Enabling and piling works progressing at the latest visit
- Timetable for a new booking confirmed by Emaar at reservation
- No inspection data yet: the plan and the developer are the whole case
- Full instalment runway from the first scheduled date
- Priced before any site works are recorded
15 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Baystar by Vida Project Details

With enabling and piling works under way at 6.3%, Baystar by Vida is still a ground stage development of 319 one to four bedroom apartments in two mid-rise towers on the Marina Promenade. Starting prices: AED 2.10M ≈ USD 572K.
For buyers entering at this stage, the trade off is the longest wait in the project's life against the earliest position in its payment schedule, with handover scheduled for Q4 2029 and a registered completion date of 31 December 2029.
Baystar by Vida Project GuideSite Context This Cycle
Explore Baystar by Vida Location on Dubai Map
Baystar by Vida occupies plot 654, registered under the Madinat Dubai Almelaheyah location in the DLD record, with its two mid-rise towers set along the Marina Promenade of Rashid Yachts & Marina. On a waterfront plot beside the marina basin, the piles that will carry both towers come first, and the 16 June 2026 inspection found them progressing alongside the wider enabling package.
Rashid Yachts & Marina is still taking shape on the site of the historic Port Rashid, with the QE2 already berthed there and road access running through Sheikh Rashid Road and Al Mina Road, so Baystar by Vida buyers are committing to a district that will mature alongside the towers through to the Q4 2029 handover rather than one that is finished today. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Baystar by Vida During Early Construction Progress
The enabling band is where payment protection and residency planning are settled, years before handover preparation begins. Each resource below is matched to where Baystar by Vida stands right now.

Baystar by Vida Construction Updates
This page: the verified June 2026 inspection record for Baystar by Vida, from enabling works onward.

Baystar by Vida at Rashid Yachts & Marina Golden Visa: Four Tiers
All four apartment tiers at Baystar by Vida at Rashid Yachts & Marina, on the Marina Promenade, qualify individually.
Read Baystar by Vida Golden Visa Guide
Baystar by Vida at Rashid Yachts & Marina: Escrow in Brief
Baystar by Vida at Rashid Yachts & Marina, DLD project 4002: Abu Dhabi Commercial Bank escrow, 6.3% certified June 2026.
Verify Baystar by Vida Escrow AccountUpdate Timeline
Other Baystar by Vida Construction Updates
June 2026 opens the Baystar by Vida monthly series, so there is no earlier monthly report to step back to; the construction updates hub carries the record forward from this reading.
Where This Update Fits
Explore Baystar by Vida Structure
This June 2026 report sits inside a wider record: the apartment launches Baystar by Vida competes with, the marina district around its plot, and the developer building it.

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Baystar by Vida Construction Progress in June 2026: Frequently Asked Questions
The independent RERA inspection of 16 June 2026 recorded Baystar by Vida, DLD project 4002, at 6.3% construction progress, up from a previous inspection reading of 0.42%: a gain of 5.88 percentage points. The DLD record does not date the 0.42% reading, so that gain cannot be converted into a monthly pace.
As of the 16 June 2026 record, the registered completion date for Baystar by Vida is 31 December 2029, inside the Q4 2029 handover window. With 93.7 percentage points still to be recorded across roughly three and a half years, the signal to watch is whether later readings keep pace with that window. Registered dates can be revised between cycles and are re-checked for every update; how completion dates and handover relate is covered on the Baystar by Vida construction updates hub.
At 6.3%, Baystar by Vida sits in the enabling stage: the Progress Status in the 16 June 2026 inspection report reads Enabling Works - Progressing, the ground stage that precedes the structural frames of Tower 1 (G+P+20) and Tower 2 (G+P+16). For buyers, most of the 10 / 70 / 20 launch schedule of record still lies ahead of the build, with the final 20% dated December 2029.
The inspection notes of 16 June 2026 read: "At the time of inspection found that :Enabling work and Piling works were Progressing at site". Enabling works typically cover site setup, temporary services, and excavation support, while piling installs the deep foundation elements that will carry both towers once pile caps and raft foundations follow.
Search project number 4002, registered as Baystar by VIDA, in the project status lookup of the Dubai Land Department app: the June 2026 record shows 6.3% current progress, 0.42% previous inspection, status Active, and the inspection date 16-06-2026. The full Independent Progress Monitoring Report for that visit can be downloaded from the same screen.
The next update publishes once a new RERA inspection reading for project 4002 appears in the DLD record after 16 June 2026. Readings are not released on a fixed monthly date, so each report is named for its inspection rather than for the month it goes live; the milestone to watch in the next reading is whether piling has given way to foundation works.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Baystar by Vida at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.