Binghatti Starlight by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the residential building with balconies and neighboring buildings in Dubai - Presented by Tohid Fetrat

Binghatti · Al Jaddaf

Binghatti Starlight Construction Updates

A 20-Floor Al Jaddaf Tower, Read Against Its DLD Register

Binghatti Starlight read 63.11% on the DLD register at the 14 May 2026 RERA inspection, its Al Jaddaf frame recorded complete and the climb moving into interiors.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

63.11%Construction Progress
14 May 2026Latest RERA Inspection
511 residential unitsTotal Units
Project 3195DLD Registration

Construction Snapshot

Binghatti Starlight at a Glance

Binghatti Starlight is Binghatti's single residential tower of 510 residences in Al Jaddaf, stacked as three basement levels, a ground floor and three podium levels beneath 20 residential floors and a roof. The Dubai Land Department register lists its construction start as 30 July 2024 and its registration as 15 November 2024, and the registered completion date of 31 March 2026 has since passed. Because this is one tower rather than a phase of a larger masterplan, every register reading below describes the whole building at once, from basement to roof.

DLD Project Number

3195

Project Status

Active

Construction Start

30 July 2024

Total Units

511 residential units

Total Built-Up Area

32,298.45 sq m

Registered Completion Date

31 March 2026 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Starlight Construction Update Timeline

The Binghatti Starlight record holds one dated reading so far: 63.11% on 14 May 2026, logged 653 days after the 30 July 2024 construction start. The register also shows an earlier reading of 28.94% without a date, so it appears on the track below as an undated dot rather than a table row, and the single row links the full May 2026 update with its inspection notes.

Inspection MonthConstruction ProgressInspection DateFull Update
May 202663.11%14 May 2026View the May 2026 update
!

Reading the dates: the DLD register gives project 3195 a registered completion date of 31 March 2026, and Binghatti's original Q1 2026 handover schedule has also passed. The latest reading on this page, 63.11% on 14 May 2026, came 44 days after that registered date, with interior, envelope and MEP works still listed as ongoing. Neither date is the one to plan a move or a final payment around: confirm the current expected handover with Binghatti and in your SPA, and check whether the register entry has been revised since.

Pace Analysis

How Fast Binghatti Starlight Has Been Built

With a single dated reading on file, the Binghatti Starlight record supports one measured span, from the 30 July 2024 construction start to the 14 May 2026 reading. The figures below are arithmetic, not a forecast:

  • Jul 2024 to May 2026: start to frame recorded complete, 0% to 63.11% over 653 daysAbout 2.90 points per month
  • Previous undated reading to 14 May 2026: 28.94% to 63.11%34.17 points, no measurable rate
  • Remaining at the 14 May 2026 reading: 63.11% to handover at 100%36.89 points to go

What the Binghatti Starlight numbers can and cannot say matters more than the average itself. The 34.17 point step from 28.94% to 63.11% is the largest movement on the record, yet the earlier reading carries no date, so it cannot be turned into a monthly speed and this page does not claim one. The 2.90 point average, on a 30-day month, spans everything from enabling works to the point where the RERA report of 14 May 2026 lists the superstructure as completed; the 36.89 points still open at that reading sit in interiors, finishes, the envelope, external works and MEP, which weigh differently from frame work, so the same average should not be stretched forward into a date. For an end user, the handover date has to come from Binghatti in writing rather than from this arithmetic; for an investor, the next dated reading is what will give this record its first measured pace between two points.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Starlight and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Starlight at Al Jaddaf

A register percentage only means something next to the building it measures. The full project guide covers what the 63.11% of 14 May 2026 is building toward:

Binghatti Starlight by Binghatti in Al Jaddaf project rendering of a residential tower with balconies, palm trees, passing cars and a street level view in Dubai - Presented by Tohid Fetrat

Binghatti Starlight: A Hexagon-Faceted Tower in Al Jaddaf

Binghatti Starlight is a single Al Jaddaf tower of 510 studio, one and two bedroom apartments over 20 residential floors.

View the Binghatti Starlight Project Guide

Considering a Late-Stage Entry?

Availability at Binghatti Starlight shifts as the build moves toward completion. If the record on this page is what brought you here, ask me what is available now and how much of the payment plan a new buyer would settle at signing.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Starlight Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Binghatti Starlight register entry and the RERA report of 14 May 2026 actually record, so the windows show where this one Al Jaddaf tower stood, from its July 2024 start to the 63.11% reading.

30 Jul 2024 to 15 Nov 2024

Construction Start and Registration

The register lists construction starting on 30 July 2024 and project 3195 registered on 15 November 2024, opening the record with enabling works on the plot.

Before 14 May 2026, 28.94% undated

Foundations and Three Basement Levels

Foundations and the substructure, three basement levels included, are listed as completed in the 14 May 2026 report; the earlier 28.94% reading carries no date.

Recorded complete by 14 May 2026

Ground, Podium, and 20 Residential Floors

The superstructure, from the ground floor and three podium levels up through 20 residential floors and the roof, is recorded as completed at the 14 May 2026 inspection.

Current Phase14 May 2026, 63.11% at last reading

Interiors, Envelope, and MEP

Internal works, internal finishes, the external envelope, external works and MEP systems were all listed as ongoing when the register read 63.11% on 14 May 2026.

Handover date to be confirmed

Completion, Snagging, and Handover

36.89 points remained at the 14 May 2026 reading; with 31 March 2026 and the original Q1 2026 schedule both passed, the handover date comes from Binghatti.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Starlight's own record.

Buyer Position

Tracking Your Position at Binghatti Starlight

This page is one of four project resources that together cover a Binghatti Starlight purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Starlight by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of the residential building with balconies and neighboring buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Starlight Construction Updates

This page: every dated DLD register reading for Binghatti Starlight, from the July 2024 start onward.

Binghatti Starlight by Binghatti in Al Jaddaf Golden Visa concept graphic with a gold visa card over a rendered residential tower at sunset in Dubai - Presented by Tohid Fetrat

Binghatti Starlight Golden Visa Begins at the Two Bedroom Tier

Binghatti Starlight, 510 residences in Al Jaddaf, qualifies only at the 2 bedroom; studios and 1 bedrooms sit below.

Read the Binghatti Starlight Golden Visa Guide
Binghatti Starlight by Binghatti in Al Jaddaf escrow account concept graphic showing a shield and padlock over a rendered residential building entrance in Dubai - Presented by Tohid Fetrat

Binghatti Starlight Escrow: 63% Certified at Emirates NBD

Binghatti Starlight in Al Jaddaf is DLD project 3195, 511 units escrowed at Emirates NBD, certified 63.11% in May 2026.

Verify the Binghatti Starlight Escrow Account
Binghatti Starlight by Binghatti in Al Jaddaf snagging inspection concept cover featuring a rendered contemporary living room interior in Dubai - Presented by Tohid Fetrat

Binghatti Starlight Snagging in Al Jaddaf

Binghatti Starlight is a Binghatti tower in Al Jaddaf over three podium levels, holding 510 studio, 1 and 2 bedroom apartments.

Book Binghatti Starlight Snagging

Approaching Handover

Between 63.11% and Handover: What Binghatti Starlight Buyers Should Do Now

At the 14 May 2026 reading, 36.89 points still separated Binghatti Starlight from 100%, almost all of it in interiors, finishes, the envelope and MEP, and the handover date itself is still to be confirmed by Binghatti now that the original Q1 2026 schedule has passed. A completion notice normally leaves only a short window to settle the handover payment and inspect the unit, so the three checks below belong before it arrives, not after.

First, match what you have paid so far against the 50% construction share of the 20/50/30 plan and the record on the Binghatti Starlight escrow account page, so any instalment still to come goes only to the Emirates NBD account for project 3195.

Second, choose your snagging inspector before the completion notice rather than after it; the Binghatti Starlight snagging page sets out what to check in a studio, one or two bedroom apartment.

Third, if you hold or are weighing a two bedroom unit from AED 2.12M ≈ USD 578K, settle residency eligibility early through the Binghatti Starlight Golden Visa guide, since the application route depends on whether you hold the off plan registration or the title deed.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

A single tower's build record reads best beside what surrounds it. These three pages place Binghatti Starlight's progress in its Al Jaddaf market, its district, and its developer's wider portfolio:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Starlight Construction Updates Frequently Asked Questions

Binghatti Starlight is an active project on the Dubai Land Department register under number 3195, recorded at 63.11% at the RERA inspection of 14 May 2026, with its superstructure listed as completed and interior, envelope, external and MEP works ongoing. That is the latest reading held for this page, so check the register for anything newer; the dated record is in the inspection timeline above.

The latest reading on this record is 63.11%, dated 14 May 2026, up 34.17 points from the previous register reading of 28.94%, which carries no date. The RERA report for that inspection prints no percentage of its own, and its site notes are summarised in the Binghatti Starlight May 2026 construction update.

Yes. The DLD register gives project 3195 a registered completion date of 31 March 2026, and Binghatti's original Q1 2026 handover schedule has passed as well; at the 14 May 2026 reading the tower stood at 63.11% with interior, envelope and MEP works still under way. No revised date appears in the record used for this page, so the current expected handover date has to be confirmed with Binghatti and written into the SPA, and this page's record is updated when the closing inspection is recorded.

Binghatti Starlight is one residential tower of 510 residences, built as three basement levels, a ground floor and three podium levels below 20 residential floors and a roof, the configuration listed in both Binghatti's fact sheet and the RERA report of 14 May 2026. The residences are studio, one bedroom and two bedroom apartments.

Measured from the recorded construction start of 30 July 2024 to the 63.11% reading of 14 May 2026, Binghatti Starlight averaged about 2.90 percentage points per 30-day month over 653 days. That figure is arithmetic, not a forecast: the earlier 28.94% reading is undated, so no pace between the two readings can be measured, and the remaining interior, envelope and MEP works need not follow the rate of the frame. The breakdown is in the pace analysis above.

The Dubai Land Department register records the Binghatti Starlight construction start as 30 July 2024 and the project registration, under number 3195, as 15 November 2024. The first dated reading on this page's record is 63.11% on 14 May 2026, 653 days after that start.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Starlight construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status