Binghatti Twilight by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of a residential tower, palm trees and a landscaped entrance in Dubai - Presented by Tohid Fetrat

Binghatti · Al Jaddaf

Binghatti Twilight Construction Updates

The Register Record of a Mixed-Use Tower Rising in Al Jaddaf

Binghatti Twilight reached 55.41% on the DLD register on 14 September 2026, a climb carrying the Al Jaddaf tower from finished substructure into its 22-floor frame.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

55.41%Construction Progress
14 September 2026Latest RERA Inspection
228 ResidentialTotal Units
Project 3397DLD Registration

Construction Snapshot

Binghatti Twilight at a Glance

Binghatti Twilight is Binghatti's mixed-use tower in Al Jaddaf: 228 residences stacked above three office floors and one floor shared by offices and homes, on four basement levels and a three-level podium. Its register record is compact. Construction is recorded as starting on 01 April 2025, ten weeks before the 11 June 2025 registration, and the only dated reading so far, 55.41% on 14 September 2026, arrived after the registered completion date of 30 April 2026 had already passed. The six register anchors below are the frame every later reading on this page will be measured against.

DLD Project Number

3397

Project Status

Active

Construction Start

01 April 2025

Total Units

228 Residential

Total Built-Up Area

24,889.31 sq m

Registered Completion Date

30 April 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Binghatti Twilight Construction Update Timeline

Twilight's record holds two dated register events and one dated reading. Construction is recorded from 01 April 2025 and registration from 11 June 2025; the first dated inspection, on 14 September 2026, logged 55.41%, while the same register card shows a previous inspection at 32.01% with no date beside it. That earlier figure appears below as an undated dot rather than a table row, and the September 2026 row links the full monthly update for that cycle.

Inspection MonthConstruction ProgressInspection DateFull Update
September 202655.41%14 September 2026View the September 2026 update
!

Reading the dates: the DLD-registered completion date for project 3397 is 30 April 2026, which had passed 137 days before the 14 September 2026 reading of 55.41% and 177 days before this page was written in October 2026. Binghatti's original Q1 2026 handover schedule has passed as well. The registered date is an administrative anchor set at registration; the current expected handover is confirmed by Binghatti and should be checked in your SPA.

Pace Analysis

How Fast Binghatti Twilight Has Been Built

With one dated reading, Twilight's pace can only be read as an average from the recorded start, plus a gain against an undated earlier figure. Each line below is arithmetic, not a forecast:

  • Apr 2025 to Sep 2026: recorded start to 55.41% on 14 September 2026, over 531 daysAbout 3.13 points per month
  • Previous inspection (undated) to 14 Sep 2026: 32.01% to 55.41%23.40 points, no monthly rate
  • After 14 Sep 2026: from 55.41% to 100% at handover44.59 points remaining

There is no curve to read yet, and that is the finding. The 3.13 figure spreads 55.41 points evenly over 531 days on a 30-day month, but the 14 September 2026 report shows the work has not run evenly: everything below ground is recorded as finished, while superstructure, external envelope, MEP, internal works and finishes were all moving at once on a tower of four basements and 22 upper floors. Five packages in parallel is a mid-build profile, and the 23.40 point gain since the undated previous reading shows the register moving between visits without saying over how long. For an end user, 44.59 points remain and neither the 30 April 2026 registered date nor the original Q1 2026 schedule can anchor a move-in plan; for an investor, the next dated reading is the one that turns a single point into a measured pace.

Get the Next Inspection Figure First

Tell me you are tracking Binghatti Twilight and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Binghatti Twilight at Al Jaddaf

A 55.41% reading on 14 September 2026 means more once you know what the tower will hold at 100%. The project guide sets out what Twilight buyers are tracking toward:

Binghatti Twilight by Binghatti in Al Jaddaf project rendering of an illuminated high-rise residential tower against a night sky with surrounding city buildings in Dubai - Presented by Tohid Fetrat

Binghatti Twilight: A Glass-Grid Tower in Al Jaddaf

Binghatti Twilight is a mixed-use Al Jaddaf tower of 228 one, two and three bedroom residences with office floors and shops.

View the Binghatti Twilight Project Guide

Considering a Mid-Construction Entry?

Limited units are available at Binghatti Twilight at the time of writing, and the mix still open shifts as the tower advances. Under the 20/50/30 plan the construction share falls due before handover, so confirm the construction schedule with Binghatti, and if this record is what brought you here, ask me for current availability before you commit.

Ask About Remaining Availability on WhatsApp

Stage Record

Binghatti Twilight Build Stages, Mapped to the Inspections

Each stage below is pinned to what Twilight's own record shows: two dated register events in 2025, one dated reading in September 2026, and a RERA report that splits the works into completed and progressing, so you can see which stages the tower had cleared and which were running when the register logged 55.41% on 14 September 2026.

Apr 2025 to Jun 2025

Site Activation and Registration

Construction is recorded from 01 April 2025 and DLD registration from 11 June 2025; the enabling works that opened the Al Jaddaf site are listed as completed in the 14 September 2026 report.

Finished by Sep 2026

Piling, Foundations and Four Basements

Piling, foundation and substructure works for the four basement levels are recorded as completed on 14 September 2026; no dated reading isolates this stage on its own.

Current PhaseTo Sep 2026, 55.41% at last reading

Podium and 22-Floor Superstructure

The superstructure above the ground floor and three podium levels was progressing toward 22 upper floors when the register logged 55.41% on 14 September 2026, up from 32.01% at the undated previous inspection.

Running alongside the frame

Envelope, MEP and Internal Works

External envelope, MEP, internal works and internal finishes were already progressing on 14 September 2026, moving in parallel with the frame rather than waiting for it.

44.59 points after Sep 2026

Fit-Out, Commissioning and Handover

Fit-out across 228 residences and the office floors closes the remaining 44.59 points; the original Q1 2026 schedule has passed, so the handover date is confirmed with Binghatti.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Binghatti Twilight's own record.

Buyer Position

Tracking Your Position at Binghatti Twilight

This page is one of four project resources that together cover a Binghatti Twilight purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Binghatti Twilight by Binghatti in Al Jaddaf construction updates cover image featuring a project rendering of a residential tower, palm trees and a landscaped entrance in Dubai - Presented by Tohid Fetrat
You Are Here

Binghatti Twilight Construction Updates

This page: the DLD register record for Binghatti Twilight, from the April 2025 start to handover.

Binghatti Twilight by Binghatti in Al Jaddaf Golden Visa concept graphic showing a gold card over a rendered residential tower and a sunset city view in Dubai - Presented by Tohid Fetrat

Binghatti Twilight Golden Visa: Residences Over Office Floors

Binghatti Twilight, a freehold mixed-use Binghatti tower in Al Jaddaf, holds 228 residences over three office floors, under Oqood now.

Read the Binghatti Twilight Golden Visa Guide
Binghatti Twilight by Binghatti in Al Jaddaf escrow account concept graphic featuring shield and padlock symbols beside an illuminated residential tower at night in Dubai - Presented by Tohid Fetrat

Binghatti Twilight Escrow: Al Jaddaf's Sharjah Islamic Bank Account

Binghatti Twilight, DLD project 3397, keeps 277 units' instalments at Sharjah Islamic Bank, 55.41% certified in September 2026.

Verify the Binghatti Twilight Escrow Account

Approaching Handover

Between 55.41% and Handover: What Binghatti Twilight Buyers Should Do Now

With 44.59 points still to be recorded after 14 September 2026 and the 50% construction share of the 20/50/30 plan falling due across that stretch, each Twilight instalment is best matched against the register rather than a calendar, because the original Q1 2026 schedule has passed and the current handover date is still to be confirmed with Binghatti. The three steps below belong before your next instalment, not after the next payment notice reaches you.

First, before any construction instalment leaves your account, confirm it is going to the escrow account registered for project 3397; the Binghatti Twilight escrow verification guide shows how to check it against the DLD record.

Second, if residency is part of your plan, settle eligibility before you sign; the Binghatti Twilight Golden Visa eligibility guide explains why the 2 bedroom tier sits exactly on the value line and how office units are assessed.

Third, pin your own unit's terms to this record; the Binghatti Twilight apartments and offices guide sets out the 20/50/30 plan with 30% due on handover, so you can confirm the construction schedule with Binghatti against what your SPA says.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

These three pages place the Binghatti Twilight record, 55.41% on 14 September 2026, beside the listings, the district and the developer it will be judged against at handover:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Binghatti luxury towers in Dubai – Bugatti Residences, Mercedes-Benz Places, and Skyblade by Binghatti, representing iconic branded architecture and innovation, presented by Tohid Fetrat.

Binghatti: Record Construction Speed and Branded Towers With Bugatti and Mercedes-Benz

Binghatti has delivered more than 60 projects since 2008, with 27 under development and two master communities across Dubai.

View the Binghatti Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Binghatti Twilight Construction Updates Frequently Asked Questions

Binghatti Twilight is an active project on the Dubai Land Department register (project 3397), recorded at 55.41% construction progress on 14 September 2026, with its superstructure, external envelope, MEP, internal works and internal finishes progressing on site at that date. The dated record is in the inspection timeline above.

The latest dated figure for Binghatti Twilight is 55.41%, logged on the DLD project register on 14 September 2026, which is 23.40 points above the 32.01% shown for the previous inspection, a reading the register lists without a date. The stage-by-stage notes for that cycle are in the Binghatti Twilight September 2026 construction update.

No current completion date for Binghatti Twilight is published on this page. By the 14 September 2026 reading of 55.41%, the register's 30 April 2026 completion date was 137 days in the past and Binghatti's original Q1 2026 handover schedule had also run its course, so the expected handover has to be confirmed with Binghatti and checked against the SPA; this page's record is updated as each new register reading is posted.

Binghatti Twilight is being built with 228 residences, split across one, two and three bedroom apartment types and set above dedicated office floors, with ground-floor retail shops completing the mixed-use tower. The residences fill the 18 residential floors and share one floor with offices, and the tower stood at 55.41% on the DLD register on 14 September 2026.

Construction of Binghatti Twilight started on 01 April 2025, and the project was registered with the Dubai Land Department on 11 June 2025, both dates as recorded on the register. The first dated reading followed on 14 September 2026 at 55.41%, 531 days after the recorded start.

Spread across the 531 days from the 01 April 2025 start to the 14 September 2026 reading of 55.41%, Binghatti Twilight has averaged about 3.13 points per 30-day month. That is arithmetic, not a forecast, and it is not a measured pace between inspections: the earlier 32.01% reading carries no date, so no rate can be drawn from the pair. The calculation is set out in the pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Binghatti Twilight construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status