Capri 1 at DAMAC Riverside Views by DAMAC Properties in DAMAC Riverside project rendering used for the September 2026 construction update showing the planned residential buildings, courtyards and water features from above in Dubai - Presented by Tohid Fetrat

DAMAC Properties · DAMAC Riverside · Construction Update

Capri 1 at DAMAC Riverside Views Construction Update - September 2026

September 2026 DLD Reading Places Capri 1 at 8.18% in the Enabling Works Stage

The 22 September 2026 inspection found mobilisation ongoing, enabling works well advanced and foundation and substructure works under way at Capri 1, logged at 8.18 percent.

Direct advisor access. Every message answered personally, never by a call center.

8.18%DLD Register Reading
22 September 2026Inspection Date
Q1 2029Expected Handover
3663DLD Project Number

Dated DLD Inspection Data

Capri 1 Construction Snapshot

8.18% recorded on 22 September 2026 places Capri 1 in the enabling works stage of construction. It is the only dated reading in the register record used for this page, so the figure stands on its own rather than as a change from an earlier cycle.

Project Name

Capri 1 at DAMAC Riverside Views

Project Number

3663

Project Status

Active

Construction Progress

8.18%

Inspection Date

22 September 2026

Construction Start

11 August 2025

Total Units

824 residences

Total Built Area

69,283.78 sq m

Expected Completion

Q1 2029

Data source: Dubai Land Department project register, project 3663 "Damac Riverside Views - Capri 1" (Status Active; registered 16-05-2025, started 11-08-2025, registered completion date 31-03-2029), with the reading of 8.18% dated 22-09-2026, and the RERA Independent Progress Monitoring Report from the 22 September 2026 inspection, which gives the status "Enabling Works - Progressing" and prints no percentage. The image at the top of this page is a DAMAC rendering of the planned project, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Capri 1 Construction Progress Summary

The DLD's IPMR describes the project as a G+3P+14 residential building (ground, three podium levels and 14 floors), designed with a concrete structure and blockwork and finished inside and out. On 22 September 2026 the record placed Capri 1 at the opening phase of that sequence, with the status "Enabling Works - Progressing": the work logged was enabling works, foundations and substructure, and every residential floor is still to come.

Completed
  • Project registration in the DLD register on 16 May 2025
  • Construction start recorded on 11 August 2025
  • Trust account bank named on the record: Mashreq Bank
In Progress at 8.18%
  • Mobilisation, ongoing at the 22 September 2026 inspection
  • Enabling works, progressing at an advanced stage
  • Foundation and substructure works, progressing at different stages
  • IPMR progress status: Enabling Works - Progressing
Ahead of Handover
  • Structural frame for the ground floor, three podium levels and 14 floors described in the IPMR
  • Blockwork and internal and external finishes for 824 residences
  • Further RERA inspection cycles and DLD register readings
  • Registered completion date 31 March 2029; expected handover Q1 2029
Next inspectionNo date is published in the register; the next reading appears after the next RERA site visit, and this page remains the record of the 22 September 2026 cycle.
Completion targetThe DLD record lists a registered completion date of 31 March 2029, in line with the expected Q1 2029 handover; the contractual completion date is the one in the SPA.
Remaining distance91.82 percentage points separate the 22 September 2026 reading from 100%. Arithmetic, not a forecast: 8.18 points over the 407 days since the registered start on 11 August 2025 averages about 0.60 points per 30-day month, while reaching 100% by the registered date, 921 days after the reading, would take about 2.99 points per 30-day month. The registered date is the developer's filing, not a promise, and neither figure predicts the handover date.

Time-Linked Instalments

What 8.18% Progress Means for Capri 1 Buyers

The Capri 1 plan is time-linked: its 40 instalments fall due by months from booking, so a register reading of 8.18% neither triggers a payment nor moves a due date. What the reading does show is how much construction sits between today and the 20% due on completion. At this enabling works stage, four actions matter most.

Before Your First Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account held with Mashreq Bank for project 3663, registered as "Damac Riverside Views - Capri 1". Capri 1 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Signing the SPA

Read your SPA payment schedule

The DAMAC Riverside Views regular payment plan is 20% plus the 4% DLD registration fee on booking, 60% in 40 instalments after booking and the final 20% on completion; handover is expected in Q1 2029. Check how your SPA dates each instalment and defines completion. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

At Booking

Confirm your Oqood registration

An off plan purchase is registered with the DLD as an Oqood contract, and the 4% DLD registration fee paid at booking goes to the Dubai Land Department, not into escrow. Confirm that your Capri 1 contract sits on the register under project 3663 before the instalment calendar starts.

Every Cycle

Track each new reading

With 91.82 points still to be recorded, many inspection cycles lie between this reading and completion. The Capri 1 construction updates hub lists every dated reading as it is published.

General framework, not legal advice: instalment dates, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly. This is DAMAC's regular payment plan for DAMAC Riverside Views, issued for a later release of the collection; confirm the Capri 1 schedule with DAMAC and in the SPA.

Buying at 8.18%?

Entering at the enabling works stage trades certainty for runway: most of the construction is still to be inspected, and in exchange the 60% block is spread over 40 instalments set by the calendar from booking. Every instalment goes to the DLD-registered escrow account for project 3663, released against construction progress.

Entering Now at 8.18%
  • One dated register reading so far: 8.18% on 22 September 2026
  • Expected handover Q1 2029, with most of the build still to be inspected
  • 20% of the price due on completion under the regular plan
Typical Near-Handover Entry
  • Most of the construction inspected before you commit
  • A short wait between purchase and handover
  • A shorter instalment runway, with more of the price due sooner
AED 1.00M ≈ USD 272KStarting Price
80/20 Plan20% Due on Completion
Q1 2029Expected Handover
Ask What Is Available at Capri 1

Units Available at Capri 1 as of this update, with no count published; availability shifts between cycles.

About the Development

Capri 1 Project Details

Capri 1 at DAMAC Riverside Views by DAMAC Properties in DAMAC Riverside aerial project rendering of low-rise residential buildings with stepped roofs and landscaped surroundings in Dubai - Presented by Tohid Fetrat
DAMAC Riverside · DAMAC Properties

With enabling works and foundation and substructure work both in progress at the September 2026 inspection, Capri 1 is an early-stage DAMAC Riverside build of 824 one and two bedroom apartments. 1 Bedroom Apartments start from AED 1.00M ≈ USD 272K (693 to 1,157 sq ft) and 2 Bedroom Apartments from AED 1.77M ≈ USD 482K (1,364 to 1,481 sq ft).

For buyers entering now, the trade off is the longest instalment runway against the longest wait, with handover expected in Q1 2029; the image here is a DAMAC rendering, not the current site.

Capri 1 at DAMAC Riverside Views Project Guide

Site Context This Cycle

Explore the Capri 1 Site on Dubai Map

Capri 1 sits in DAMAC Riverside in Dubai Investment Park 2, where DAMAC's project presentation lays the community out along a Green Vein of planted open space and a Water Vein of lakes. None of that landscape is part of the current record: at the 22 September 2026 inspection the work logged on the Capri 1 plot was enabling works, foundations and substructure.

DAMAC's investment presentation points to direct links with the E311 and E611 highways, and DAMAC's factsheet lists community drive times of roughly 12 minutes to Al Maktoum International Airport and to the Expo 2020 site. The road links exist today while the community amenities are planned, which matters for buyers weighing a Q1 2029 handover against how much of DAMAC Riverside will be operating by then. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Capri 1 on Dubai Map

Buyer Resources for This Project

Capri 1 Buyer Resources at the Enabling Works Stage

Early in a build, the questions that decide a purchase are where instalments go, what the price can support, and how progress is recorded. Each resource below is matched to where Capri 1 stands right now.

Capri 1 at DAMAC Riverside Views by DAMAC Properties in DAMAC Riverside construction updates cover image featuring a project rendering of several residential buildings above a long podium in Dubai - Presented by Tohid Fetrat
You Are Here

Capri 1 Construction Updates

This page: the dated 22 September 2026 DLD record placing Capri 1 at 8.18% progress.

Capri 1 at DAMAC Riverside Views by DAMAC Properties in DAMAC Riverside Golden Visa concept graphic with a gold card above a rendered waterfront pedestrian plaza and low-rise buildings in Dubai - Presented by Tohid Fetrat

Capri 1 Golden Visa: Both Apartment Types Below AED 2M

Capri 1 at DAMAC Riverside Views, DAMAC Properties' 824-residence release, has no apartment type that reaches the AED 2M threshold alone.

Read the Capri 1 Golden Visa Guide
Capri 1 at DAMAC Riverside Views by DAMAC Properties in DAMAC Riverside escrow account concept graphic with a shield and padlock above a rendered waterfront promenade and residential buildings in Dubai - Presented by Tohid Fetrat

Capri 1 Escrow: Protected Payments From the Enabling Works Stage

Capri 1, DLD project 3663, escrows instalments for 824 residences at Mashreq Bank and read 8.18% in September 2026.

Verify the Capri 1 Escrow Account

Update Timeline

Other Capri 1 Construction Updates

This September 2026 page opens the dated Capri 1 series; each later reading joins the hub as its inspection cycle publishes.

All Capri 1 Construction Updates

FAQs

Capri 1 at DAMAC Riverside Views Construction Progress in September 2026: Frequently Asked Questions

The Dubai Land Department register shows Capri 1, registered as project 3663 "Damac Riverside Views - Capri 1", at 8.18% construction progress on 22 September 2026. The RERA Independent Progress Monitoring Report from the same inspection gives the progress status "Enabling Works - Progressing" and prints no percentage of its own, so 8.18% is the DLD register reading for that date.

Yes. The DLD record lists a registered completion date of 31 March 2029, in line with the expected Q1 2029 handover; the contractual completion date is the one in the SPA. A registered completion date is the developer's filing and can be revised in the register between inspection cycles; as of the reading recorded on 22 September 2026 it stood at 31 March 2029, and any revision would appear in a later Capri 1 update.

At the 22 September 2026 inspection, the IPMR notes found mobilisation still ongoing, enabling works at an advanced stage of progress, and foundation and substructure works progressing at different stages. The same report describes the project as a G+3P+14 residential building (ground, three podium levels and 14 floors) with a concrete structure and blockwork and internal and external finishes; it notes no works above the substructure at that date.

The DLD register record used for this page carries a single dated reading for Capri 1, 8.18% on 22 September 2026, with no earlier inspection value alongside it, so there is nothing yet to set the figure against. A rate of progress becomes measurable only once a second dated reading is published, and until then any monthly figure for Capri 1 is arithmetic over the time since the registered start rather than a measured pace.

No. The top image is a DAMAC rendering of the planned project seen from above, used to illustrate this September 2026 update; it does not show the site as it stood on 22 September 2026. The register record carries inspection photographs from the RERA report, and those are not reproduced on this page.

The 8.18% figure was recorded on 22 September 2026 and is the reading this page reports; a newer inspection may have been logged since. The live record for project 3663, "Damac Riverside Views - Capri 1", can be checked in the Dubai Land Department's Dubai REST app, and each new dated reading is added to the Capri 1 construction updates hub.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2026 inspection record for Capri 1 at DAMAC Riverside Views correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts