Central Park Plaza Construction Updates
The Register Record of Two City Walk Towers Rising Beside Central Park
Central Park Plaza reached 43.68% on the DLD register at the 01 September 2026 inspection, with both City Walk towers climbing above a completed substructure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Central Park Plaza at a Glance
Central Park Plaza is the Meraas pair of residential towers at Central Park in City Walk, entered on the Dubai Land Department register as project 2796 on 11 October 2023, with construction starting on 08 December 2023 and a register reading of 43.68% at 01 September 2026. One detail shapes how that figure should be read: Tower A climbs to 23 floors and Tower B to 20 above a shared basement, so a single register percentage here describes two structures of unequal height, not one tower.
2796
Active
08 December 2023
212 residential units
32,590.95 sq m
08 October 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Central Park Plaza Construction Update Timeline
One dated reading anchors this record so far: 43.68% on the DLD register at the RERA inspection of 01 September 2026, 998 days after the 08 December 2023 construction start. The same register screen lists a previous inspection at 34.63% but gives it no date, so that figure sits on the track below as an undated dot and not as a table row. The September 2026 row links the full monthly update for both towers.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 43.68% | 01 September 2026 | View the September 2026 update |
Reading the dates: project 2796 carries a registered completion date of 08 October 2026 in the DLD record. As of this page's 24 October 2026 review that date is 16 days past, and the latest register reading, taken on 01 September 2026, stands at 43.68%. The register gives no explanation for the gap and this page offers none; Meraas puts handover in Q3 2027, and the registered date is re-checked against Dubai REST at every update.
Pace Analysis
How Fast Central Park Plaza Has Been Built
With a single dated reading on the register, Central Park Plaza has no inspection-to-inspection velocity yet. Two figures can still be computed from dated facts, both on a 30-day month and both arithmetic, not a forecast:
- Dec 2023 to Sep 2026: whole-build average, 43.68 points over the 998 days from the registered start to the 01 September 2026 readingAbout 1.31 points per month
- Sep 2026 to Sep 2027: the 56.32 points left after 01 September 2026, spread over the 394 days to the end of Q3 2027About 4.29 points per month
The distance between 1.31 and 4.29 is the headline of this record, not a verdict on it. The first figure spreads 43.68 points across everything since 08 December 2023, including the enabling, foundation and basement works the RERA report of 01 September 2026 lists as complete; the second is simply the points still to come divided by the days left in Q3 2027. Superstructure, MEP and finishing packages move a register percentage at different rates, so neither number predicts the next reading, and the undated 34.63% is left out of both because a pace needs two dates. For an end user, the figure to watch is the next register reading against Q3 2027; for an investor, it is whether the next few readings start closing the gap between those two rates.
Get the Next Inspection Figure First
Tell me you are tracking Central Park Plaza and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Central Park Plaza at City Walk
A register percentage tracks the build; the project guide explains what that build will deliver. For the residences and setting this record leads to, start here:

Central Park Plaza: The Final Apartment Phase at Central Park
Central Park Plaza is a Meraas project of two towers at City Walk with 212 residences, apartments, townhouses and penthouses.
View the Central Park Plaza Project GuideConsidering a Mid-Construction Entry?
Meraas releases and sells Central Park Plaza units while the towers rise, so what is available shifts between register readings. If the record on this page is what brought you here, ask me what is available today and on which terms.
Ask About Remaining Availability on WhatsAppStage Record
Central Park Plaza Build Stages, Mapped to the Inspections
Each stage below is tied to the dates the DLD register and the 01 September 2026 RERA report actually hold for Central Park Plaza, from its October 2023 registration to the Q3 2027 handover, rather than to a generic construction sequence.
Registration and Construction Start
Project 2796 entered the Dubai Land Department register on 11 October 2023, and the register records construction starting on 08 December 2023, 58 days later.
Enabling, Foundations and Basement
Enabling, foundation and substructure works, including the basement shared by Tower A and Tower B, are listed as complete in the RERA report of 01 September 2026; no separate completion date is recorded.
Superstructure of Two Towers
Superstructure, internal works and MEP were progressing at the 01 September 2026 inspection, with the register at 43.68%; Tower A rises to 23 floors and Tower B to 20 above the ground floor.
External Envelope and Internal Finishes
Already recorded as progressing at the September 2026 inspection, these packages share the 56.32 points still to be registered with the remaining structure and MEP works.
Completion and Handover
Final works and handover of the 212 residences, which Meraas expects in Q3 2027; the registered completion date of 08 October 2026 has passed, as noted under the timeline.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Central Park Plaza's own record.
Buyer Position
Tracking Your Position at Central Park Plaza
This page is one of four project resources that together cover a Central Park Plaza purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Central Park Plaza Construction Updates
This page: the DLD register record for project 2796, from the 2023 registration to handover.

Central Park Plaza Golden Visa: Six Unit Types, Two Towers
Meraas's Central Park Plaza at City Walk, 212 residences in two towers, qualifies at all six unit types from 1 bedroom.
Read the Central Park Plaza Golden Visa Guide
Central Park Plaza Escrow: Meraas at City Walk, Banked With Emirates NBD
Central Park Plaza at City Walk is DLD project 2796, 212 units in Emirates NBD escrow, certified 43.68% September 2026.
Verify the Central Park Plaza Escrow AccountApproaching Handover
Between 43.68% and Handover: What Central Park Plaza Buyers Should Do Now
At 43.68% on 01 September 2026, Central Park Plaza is past its basement but short of its full structure, so the decisions open to buyers now concern payment protection and residency planning rather than preparing for the keys. None of the three steps below needs to wait for the next register reading, and each is simpler to settle before handover paperwork for the Q3 2027 estimate begins.
First, make sure every payment toward your unit goes only to the project's escrow account; the Central Park Plaza escrow account page shows how to check the Emirates NBD account registered for project 2796.
Second, if residency is part of your plan, work out the timing now through the Central Park Plaza Golden Visa guide, since eligibility for a unit still under construction depends on how the purchase is registered.
Third, follow each new register reading in the timeline above and the monthly report it links, starting with the September 2026 Central Park Plaza report, so the 56.32 points still to come are tracked against Q3 2027 rather than assumed.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
Two towers at 43.68% on 01 September 2026 are only part of the picture; the rest is the district they will deliver into. These three pages put Central Park Plaza's progress in its market, community and developer context:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Central Park Plaza Construction Updates Frequently Asked Questions
Central Park Plaza is an active project on the Dubai Land Department register, number 2796, and stood at 43.68% construction progress on that register at 01 September 2026. The RERA report of the same date lists the enabling, foundation and substructure works as complete and the superstructure, internal works, MEP, external envelope and internal finishes as progressing, under the status Main Contract, Progressing. The dated record sits in the inspection timeline above.
The latest DLD register reading for Central Park Plaza is 43.68%, dated 01 September 2026, which is 9.05 points above the previous inspection reading of 34.63% listed on the same register screen. The register gives no date for that previous reading, so the 9.05 points cannot be converted into a monthly rate. The reading is set out in full in the Central Park Plaza September 2026 construction update.
Yes. The DLD record for project 2796 lists a registered completion date of 08 October 2026, which was 16 days in the past when this page was reviewed on 24 October 2026; at the last register reading, on 01 September 2026, Central Park Plaza stood at 43.68%. Meraas expects handover in Q3 2027. A registered date can be revised in the DLD record, so it is re-checked against the register whenever this page is updated.
Central Park Plaza holds 212 residential units in two towers over a shared basement, with no retail: Tower A rises to a ground floor, 23 floors and a roof, and Tower B to a ground floor, 20 floors and a roof (B+G+23+R and B+G+20+R in the RERA report of 01 September 2026). The DLD register reading of 43.68% at 01 September 2026 covers both towers together.
Central Park Plaza has added about 1.31 percentage points per 30-day month on average: 43.68 points between the registered construction start on 08 December 2023 and the register reading of 01 September 2026, a span of 998 days. Reaching 100% by the end of Q3 2027 would take about 4.29 points per 30-day month over the remaining 394 days. Both figures are arithmetic from dated register facts, not a forecast, and no rate is drawn from the undated previous reading. The working is shown in the pace analysis above.
The DLD register records construction at Central Park Plaza as started on 08 December 2023, 58 days after the project was registered as number 2796 on 11 October 2023. The first dated register reading in this record is 43.68% at 01 September 2026, by which point the RERA report listed the enabling, foundation and substructure works as complete.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Central Park Plaza construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.