DAMAC · Dubai Maritime City
Chelsea Residences Construction Updates
The Dated DLD Record for Three Waterfront Towers on Plot 28
Chelsea Residences by DAMAC read 5.19% in the DLD register on 7 August 2026; three dated readings now establish the groundwork baseline for its waterfront towers.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Chelsea Residences at a Glance
Chelsea Residences by DAMAC is registered with the Dubai Land Department as project 3719: 703 units in three residential towers on Plot 28 of Dubai Maritime City, the tallest at G+2P+30. Its record is still young, registered on 30 April 2025, started on 19 July 2025 and read at 5.19% on 7 August 2026, so the anchors below carry more weight here than on a project nearing handover: they are the fixed points every later reading on this waterfront plot will be measured from.
3719
Active
19 July 2025
703 residential units
63,603.74 sq m
31 December 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Chelsea Residences Construction Update Timeline
Three dated readings make up the Chelsea Residences record so far, spread across 288 days: 0.06% on 23 October 2025 as enabling works were only beginning, 0.65% on 9 April 2026 with shoring under way, and 5.19% on 7 August 2026 with piling at an advanced stage in the inspector's notes. Each dot on the track below marks one of those readings, and each table row links the full monthly update for that inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 5.19% | 7 August 2026 | View the August 2026 update |
| April 2026 | 0.65% | 9 April 2026 | View the April 2026 update |
| October 2025 | 0.06% | 23 October 2025 | View the October 2025 update |
Pace Analysis
How Fast Chelsea Residences Has Been Built
Only two intervals separate the three Chelsea Residences readings, and they run at very different speeds. Each rate below is arithmetic on the dated DLD register readings, not a forecast:
- Oct 2025 to Apr 2026: mobilization and enabling works with shoring, 0.06% to 0.65%About 0.11 points per month
- Apr 2026 to Aug 2026: enabling and piling works, 0.65% to 5.19%About 1.15 points per month
The shape so far is a slow opening followed by a clear step up. Across the 168 days to 9 April 2026 the register added only 0.59 points while the inspector recorded mobilization and enabling works with shoring; across the 120 days to 7 August 2026 it added 4.54 points, roughly ten times the monthly rate, in the interval that closed with piling at an advanced stage in the inspector's notes. Two intervals are too few to call a trend. The 94.81 points still open to the registered completion on 31 December 2029 come to about 2.3 points per month over the roughly 41 months left if spread evenly, a benchmark of arithmetic rather than a forecast. For an end user, the useful reading is that the Plot 28 record has only just reached the ground engineering that precedes any tower structure; for an investor weighing entry now, it is the next few readings, not these first three, that will show the delivery pace for Tower A, Tower B and Tower C.
Get the Next Inspection Figure First
Tell me you are tracking Chelsea Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Chelsea Residences at Maritime City
A 5.19% reading on 7 August 2026 means more once you know what it is building toward: 703 apartments across three towers on the Dubai Maritime City waterfront. The project guide sets out that finished product:

Chelsea Residences: DAMAC Waterfront Towers in Dubai Maritime City
Chelsea Residences is a 703 unit waterfront project in Dubai Maritime City, with one to three bedroom apartments across three towers.
View the Chelsea Residences Project GuideConsidering an Early-Stage Entry?
Availability at Chelsea Residences shifts from one DAMAC release to the next while the site is still in enabling works. If the record on this page is what brought you here, ask me what is available now, by tower, floor and layout, before the choice narrows.
Ask About Remaining Availability on WhatsAppStage Record
Chelsea Residences Build Stages, Mapped to the Inspections
Only the first two stages below have dated readings behind them; the last three are the registered design still ahead of Chelsea Residences, anchored to the three tower heights and the 31 December 2029 completion rather than to a generic sequence.
Registration, Start and Mobilization
Registered with the DLD on 30 April 2025 and started on 19 July 2025; the first dated reading, 0.06% on 23 October 2025, found mobilization under way on Plot 28.
Enabling Works, Shoring and Piling
Enabling works were only beginning in October 2025, carried shoring at 0.65% on 9 April 2026, and reached piling at an advanced stage by 7 August 2026, read at 5.19%.
Foundations Beneath Three Towers
No inspection to date records foundation work; it follows the close-out of piling on Plot 28, beneath Tower A, Tower B and Tower C.
Concrete Structures to G+2P+30
The registered design calls for concrete structures of G+2P+25 on Tower A, G+2P+28 on Tower B and G+2P+30 on Tower C, plus roof.
Blockwork, Finishes and Handover
Block walls with internal and external finishes, then handover of 703 units, with 94.81 points to cover after the 7 August 2026 reading.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Chelsea Residences's own record.
Buyer Position
Tracking Your Position at Chelsea Residences
This page is one of four project resources that together cover a Chelsea Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Chelsea Residences Construction Updates
This page: every dated DLD register reading for Chelsea Residences, from 0.06% in October 2025 onward.

Chelsea Residences Golden Visa in Dubai Maritime City, From One Bedroom
DAMAC's Chelsea Residences, 703 freehold apartments in Dubai Maritime City, qualifies at every current release, 1 to 3 bedrooms.
Read the Chelsea Residences Golden Visa Guide
Chelsea Residences Escrow: DAMAC's Maritime City Account
DAMAC's Chelsea Residences in Dubai Maritime City escrows 703 units at Dubai Islamic Bank, DLD project 3719, 5.19% certified August 2026.
Verify the Chelsea Residences Escrow AccountApproaching Handover
Between 5.19% and Handover: What Chelsea Residences Buyers Should Do Now
At 5.19% on 7 August 2026 the Chelsea Residences record sits in enabling and piling works, so anyone who bought under DAMAC's 60/40 launch plan is paying 1% a month while the ground on Plot 28 is still being prepared. Those transfers do not wait for the towers, which is why the three steps below belong before your next instalment rather than at the December 2029 handover.
First, before the next monthly transfer, confirm that the payee is the escrow account held for project 3719; the Chelsea Residences escrow account page shows how to check it against the DLD record.
Second, if residency is part of the reason you are buying, work through the Chelsea Residences Golden Visa guide now rather than at handover, so the price point and ownership structure you choose fit the route you intend to use.
Third, read each new figure beside its inspector notes rather than on its own; the Chelsea Residences August 2026 construction update is the latest, with piling recorded at an advanced stage.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Maritime City Structure
A register reading of 5.19% on 7 August 2026 is one project's position; the three pages below show the waterfront district, the developer and the competing stock around Plot 28:

Dubai Maritime City: Waterfront Apartments and Branded Residences on the Northern Coastline
Dubai Maritime City lists 7 projects of waterfront apartments and branded residences in DP World's district, freehold for all nationalities.
See Maritime City Properties for Sale
Maritime City Community Overview
Read the Dubai Maritime City guide: a waterfront district between Port Rashid and Dubai Drydocks with high-rise coastal living.
Explore the Maritime City Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Chelsea Residences Construction Updates Frequently Asked Questions
Chelsea Residences by DAMAC is an active Dubai Land Department project (number 3719) in its enabling works stage, read at 5.19% in the DLD register on 7 August 2026. The independent progress monitoring report of that date records enabling and piling works progressing at an advanced stage, with the progress status still given as Enabling Works - Progressing. The full record is in the inspection timeline above.
Three dated readings are on record for Chelsea Residences as of September 2026: 0.06% on 23 October 2025, 0.65% on 9 April 2026 and 5.19% on 7 August 2026. The latest reading added 4.54 points to the April 2026 figure. The 0% opening value in the register carries no inspection date, so it is not counted as an inspection.
Across the 288 days from 23 October 2025 to 7 August 2026, Chelsea Residences gained 5.13 points in the DLD register, an average of about 0.54 points per month. That average blends two very different intervals: about 0.11 points per month up to 9 April 2026, then about 1.15 points per month up to 7 August 2026. All three rates are arithmetic on the register dates rather than a projection, and the breakdown is in the pace analysis above.
They agree. The Dubai Land Department register records completion for project 3719 on 31 December 2029, and DAMAC's published documents give the same anticipated completion date, so handover is planned for December 2029. That date has not passed: after the 5.19% reading of 7 August 2026, about 41 months remained to it, and this page's record is updated as each new reading is recorded.
DLD registration records show 703 residential units for Chelsea Residences by DAMAC, project 3719, sold as one, two and three bedroom apartments. The register describes them across three residential towers on Plot 28 in Dubai Maritime City: Tower A at G+2P+25, Tower B at G+2P+28 and Tower C at G+2P+30, plus roof, each designed with a concrete structure.
The DLD register records construction at Chelsea Residences as started on 19 July 2025, 80 days after the project was registered on 30 April 2025. The first dated reading followed on 23 October 2025 at 0.06%, and that opening inspection is covered in the Chelsea Residences October 2025 construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Chelsea Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.