
Meraas · City Walk
City Walk Crestlane Construction Updates
Two Mid-Rise Towers in City Walk, Recorded From the First Register Reading
City Walk Crestlane's first dated reading, 0.19% in the DLD register on 3 August 2026, sets the baseline for two mid-rise towers over one shared basement.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
City Walk Crestlane at a Glance
City Walk Crestlane is the Meraas pair of mid-rise towers holding 198 residences in City Walk, entered in the DLD register as City Walk Crestlane 1 under project 3801. Its record is still short: registration on 12 June 2025, a construction start on 8 September 2025, and a single dated reading of 0.19% on 3 August 2026. Because the register describes both towers standing on one shared basement level, every reading until structure begins speaks for one shared site rather than for Tower A and Tower B separately.
3801
Active
8 September 2025
198 residential units
26,271.26 sq m
30 September 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
City Walk Crestlane Construction Update Timeline
City Walk Crestlane's record holds one dated reading so far: 0.19% in the DLD register on 3 August 2026, the same date RERA logged enabling works progressing. The register's earlier 0% figure sits as an unlabelled dot at the left edge of the track because it carries no date, so it has no table row. Handover is estimated for April 2029, five months before the registered completion date of 30 September 2029, and the track below fills toward that handover as dated readings arrive.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 0.19% | 3 August 2026 | View the August 2026 update |
Pace Analysis
How Fast City Walk Crestlane Has Been Built
A measured pace needs two dated readings, and City Walk Crestlane has one. What the register dates do allow is arithmetic, not a forecast, set out in three lines:
- 8 Sep 2025 to 3 Aug 2026: enabling works, 0.19 points over 329 days since the registered startAbout 0.017 points per month
- 3 Aug 2026 to 30 Sep 2029: 99.81 points remaining over 1,154 days to the registered completion dateAbout 2.59 points per month
- 3 Aug 2026 to 30 Apr 2029: 99.81 points remaining over 1,001 days to the end of the estimated handover monthAbout 2.99 points per month
Read those three figures as a frame, not a curve. The 0.017 average spreads City Walk Crestlane's first 0.19 points across 329 days that the 3 August 2026 report places entirely inside enabling works, before the shared basement or either tower enters the record, so it measures ground preparation rather than building speed. The 2.59 and 2.99 figures are simply the average monthly climbs the remaining 99.81 points would take to reach 30 September 2029 or the end of April 2029, and neither is a verdict on the schedule. For an end user planning a move around April 2029, and for an investor deciding whether to enter at enabling works, the number worth waiting for is the first gap between two dated readings, which is the point at which this page can publish a measured pace for the project.
Get the Next Inspection Figure First
Tell me you are tracking City Walk Crestlane and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About City Walk Crestlane at City Walk
A register percentage this close to zero says little until you know what it is counting toward. The project guide sets out the finished development this record tracks:

City Walk Crestlane: Two Mid-Rise Meraas Towers by the Park
City Walk Crestlane is a Meraas project of two mid-rise towers with 198 residences, up to five bedroom penthouses.
View the City Walk Crestlane Project GuideConsidering a Pre-Structure Entry?
With enabling works the only stage on record, City Walk Crestlane is still being sold from plans, and what Meraas holds changes between releases. If this record is what brought you here, ask me what is available today and which dated instalments a purchase made now would carry.
Ask About Remaining Availability on WhatsAppStage Record
City Walk Crestlane Build Stages, Mapped to the Inspections
Only the first two stages below carry dates from City Walk Crestlane's own record; the three after them are drawn from the register's description of the scheme and will gain inspection windows as dated readings log them.
DLD Registration and Start
Project 3801 entered the DLD register on 12 June 2025, and the register dates the construction start to 8 September 2025, 88 days later.
Enabling Works
The RERA report of 3 August 2026 records enabling works progressing on site, with the DLD register at 0.19% that day.
Shared Basement and Ground Level
One basement level under both buildings, then the ground floor with the main lobby and four retail units opening onto the facade.
Tower A and Tower B Structure
Two mid-rise residential towers of 12 floors above ground each; no reading has logged structural work on either tower yet.
Enclosure, Interiors, and Landscape
Facades, interiors for the 198 residences, and the pools, water features and park landscape, closing the record at the April 2029 handover estimate.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Crestlane's own record.
Buyer Position
Tracking Your Position at City Walk Crestlane
This page is one of four project resources that together cover a City Walk Crestlane purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Crestlane Construction Updates
This page: City Walk Crestlane's dated register readings, from 0.19% in August 2026 to handover.

City Walk Crestlane Golden Visa: Five Apartment Tiers in Jumeirah
Meraas's City Walk Crestlane, 198 residences in Jumeirah, starts every unit type above AED 2M, from the 1 bedroom to penthouse.
Read the City Walk Crestlane Golden Visa Guide
City Walk Crestlane Escrow: Meraas's City Walk Account
Meraas's City Walk Crestlane is DLD project 3801, 202 units, National Bank of Ras Al Khaimah escrow, 0.19% certified August 2026.
Verify the City Walk Crestlane Escrow AccountApproaching Handover
Between 0.19% and Handover: What City Walk Crestlane Buyers Should Do Now
At 0.19% on 3 August 2026, the distance that matters for City Walk Crestlane buyers is the one to the first structural reading rather than the one to handover, and the Meraas instalments run on calendar dates, not on that progress. In the developer's launch schedule the next dated instalment after today falls in February 2027, so the three checks below belong before that payment rather than after it; your SPA confirms the dates that apply to your unit.
First, make sure every instalment goes to the trust account registered for project 3801; the City Walk Crestlane escrow account page shows how to match it against the DLD record before any transfer.
Second, if residency is part of the plan, settle eligibility while the towers are still unbuilt through the City Walk Crestlane Golden Visa guide, since the route for an off plan purchase can differ from one made after the title deed is issued.
Third, follow the readings as they arrive: the City Walk Crestlane August 2026 construction update holds the full detail for the 0.19% figure, and each later reading gets its own dated page in the timeline above.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
Crestlane's two towers are rising inside a City Walk that already operates around them. These three pages place its 0.19% reading of 3 August 2026 in market, community, and developer context:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
City Walk Crestlane Construction Updates Frequently Asked Questions
City Walk Crestlane is an active DLD-registered project, number 3801, entered in the register under the name City Walk Crestlane 1, and it sits at the enabling works stage with a DLD register reading of 0.19% dated 3 August 2026. The RERA progress report of that date lists Enabling Works, Progressing as the only stage on site; every reading so far is laid out in the City Walk Crestlane inspection timeline above.
One dated reading is on record: 0.19% in the DLD register on 3 August 2026, a rise of 0.19 points over the previous inspection figure of 0%, which the register shows without a date. Because only the August 2026 entry carries a date, the timeline holds a single row, and the full detail for it sits on the August 2026 City Walk Crestlane inspection page.
Handover at City Walk Crestlane is estimated for April 2029, the month in which the Meraas schedule places its final 25% instalment, while the DLD register for project 3801, read on 3 August 2026, gives 30 September 2029 as the registered completion date, five months after the estimate. The registered date is the completion anchor filed with the project record; the five-month gap is not a forecast in either direction, and this page is updated whenever the register entry changes.
City Walk Crestlane comprises 198 residences in Tower A and Tower B, a pair of mid-rise residential towers that the RERA project description records as B+G+12+R each above one shared basement level, with four retail units at ground level beside the main lobby. The mix covers 1, 2 and 3 bedroom apartments, 4 bedroom apartments and duplexes, and 5 bedroom penthouses.
The DLD register records a construction start of 8 September 2025 for City Walk Crestlane, 88 days after the project was registered on 12 June 2025. The first dated reading followed 329 days after that start, at 0.19% on 3 August 2026.
No structural stage appears in the City Walk Crestlane record yet. The RERA report of 3 August 2026 places the site at enabling works, progressing, with a DLD register reading of 0.19% that day, so the shared basement, the ground level with its lobby and retail units, and both towers all remain ahead in the City Walk Crestlane stage record.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Crestlane construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.