Meraas · City Walk
City Walk Northline 1 Construction Updates
Tracking 114 Homes From Finished Foundations to the Q3 2027 Estimate
City Walk Northline 1 reached 38.09% on the DLD register at the 19 August 2026 inspection, its foundations finished and the low-rise frame climbing toward handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
City Walk Northline 1 at a Glance
City Walk Northline 1 is the 114-home Meraas building beside The Green Planet in City Walk, registered with the DLD as project 2970 on 1 March 2024, with construction under way from 10 August 2024. Because the register describes one residential building of ground plus eight floors over a basement, every figure here measures a single structure rather than an average spread across several towers, which makes the 38.09% recorded on 19 August 2026 an unusually direct reading of where this one address stands.
2970
Active
10 August 2024
114 residential units
12,860.57 sq m
Q3 2027 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
City Walk Northline 1 Construction Update Timeline
The DLD register holds two readings for City Walk Northline 1: a previous inspection figure of 26.73% that carries no date, and 38.09% dated 19 August 2026, the only dated reading on file and so the only row in the table below. The undated figure sits on the track as a dot without a month, which means the dated history of this building opens two years after its 10 August 2024 start; the August 2026 row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 38.09% | 19 August 2026 | View the August 2026 update |
Pace Analysis
How Fast City Walk Northline 1 Has Been Built
With one dated reading and one undated, the City Walk Northline 1 record cannot yet show a measured pace between inspections. What it can show is plain arithmetic, labelled as such:
- 10 Aug 2024 to 19 Aug 2026: registered start to the dated reading, 0% to 38.09% over 739 days, a whole-build average (arithmetic, not a forecast)About 1.55 points per 30-day month
- Previous inspection (undated) to 19 Aug 2026: 26.73% to 38.09%No pace measured: the earlier reading has no date
- 19 Aug 2026 to the Q3 2027 estimate: 61.91 points still to be recordedLater readings will show whether Q3 2027 holds
The 1.55 figure is a straight line drawn from a 0% start to a single dated point, so it flattens everything between the two: those 739 days include the enabling, piling and foundation works that the RERA report of 19 August 2026 lists as completed, and none of that sequencing is visible in an average. The undated 26.73% sits somewhere between the ends but cannot be placed in time, so it proves the register recorded progress in steps without saying how quickly they came. For an end user weighing a Q3 2027 move, the useful test is how far the next dated reading closes the 61.91-point gap; for an investor, that next dated reading paired with 19 August 2026 will produce the first measured velocity for this building, and this section will carry it once it exists.
Get the Next Inspection Figure First
Tell me you are tracking City Walk Northline 1 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About City Walk Northline 1 at City Walk
A 38.09% reading only means something against the building it is measuring. The project guide covers the 114 homes this record is tracking toward:

City Walk Northline 1: A Low-Rise Building by The Green Planet
City Walk Northline 1 is a Meraas building of ground plus eight floors with 114 apartments of one to three bedrooms.
View the City Walk Northline 1 Project GuideConsidering a Mid-Construction Entry?
With its foundations recorded as completed and the superstructure progressing, City Walk Northline 1 is past its below-ground works but still short of handover. Limited units remain available at the time of writing; if the record on this page is what brought you here, ask me what is open before the choice of floors narrows further.
Ask About Remaining Availability on WhatsAppStage Record
City Walk Northline 1 Build Stages, Mapped to the Inspections
Each stage below is pinned to what the City Walk Northline 1 record actually holds: two register dates, one dated reading of 38.09% on 19 August 2026 and the RERA report of the same day, so a stage without a recorded date says so instead of borrowing one.
Registration and Site Activation
Registered with the DLD as project 2970 on 1 March 2024, with construction starting on 10 August 2024 on the City Walk plot beside The Green Planet.
Enabling, Piling and Foundations
Listed as completed in the RERA report of 19 August 2026: the below-ground works carrying a basement, a ground floor and eight upper floors.
Substructure and Superstructure
Progressing at the 19 August 2026 inspection, with the RERA progress status for the single residential building recorded as Main Contract, Progressing.
MEP, Internal Works, Finishes and Envelope
Not waiting for the frame: the same 19 August 2026 report lists MEP, internal works, internal finishes and external envelope works as progressing alongside it.
Completion and Handover
61.91 points remain between the 19 August 2026 reading and 100%; handover of the 114 apartments is estimated for Q3 2027, with no registered completion date in the evidence.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Northline 1's own record.
Buyer Position
Tracking Your Position at City Walk Northline 1
This page is one of four project resources that together cover a City Walk Northline 1 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Northline 1 Construction Updates
This page: the City Walk Northline 1 register record, from its August 2024 start to handover.

City Walk Northline 1 Golden Visa: Between One and Two Bedrooms
City Walk Northline 1, Meraas's 114 residences, qualifies at 2 and 3 bedroom apartments; the 1 bedroom starts short.
Read the City Walk Northline 1 Golden Visa Guide
City Walk Northline 1 Escrow: Meraas's First Northline Account
Meraas's City Walk Northline 1 escrows 115 units at First Abu Dhabi Bank, DLD project 2970, 38.09% certified August 2026.
Verify the City Walk Northline 1 Escrow AccountApproaching Handover
Between 38.09% and Handover: What City Walk Northline 1 Buyers Should Do Now
With the register at 38.09% on 19 August 2026, the City Walk Northline 1 build sits inside the stretch where the 55% paid during construction under the 20/55/25 plan comes due, while the frame, building services and envelope advance together. Each installment within that 55% falls due on the Meraas sales agreement schedule whether or not the latest reading has been checked, so the three steps below belong before the next transfer, not after it.
First, confirm that every construction-period payment goes only to the account set out on the City Walk Northline 1 escrow account page, which shows how to check the account registered for project 2970 against the DLD record.
Second, if residency is part of the plan, settle eligibility first through the City Walk Northline 1 Golden Visa guide, because the 2 bedroom tier at AED 3.00M ≈ USD 817K and the 3 bedroom tier at AED 4.70M ≈ USD 1.28M each clear the threshold, while the 1 bedroom tier at AED 1.80M ≈ USD 490K does not on its own.
Third, read each new dated reading as it lands: the City Walk Northline 1 August 2026 construction update is the baseline the next dated inspection will be measured against, and that pair will give this building its first measured pace.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
One building at 38.09% on 19 August 2026 sits inside a district that already operates around it. These three pages put the City Walk Northline 1 record in its market, community and developer context:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
City Walk Northline 1 Construction Updates Frequently Asked Questions
City Walk Northline 1 is an active DLD-registered project (number 2970) in its superstructure stage, at 38.09% on the DLD project register following the RERA inspection of 19 August 2026, with the RERA progress status recorded as Main Contract, Progressing. The dated reading and the undated one before it are set out in the inspection timeline above.
Two readings sit in the DLD register for City Walk Northline 1: 38.09% dated 19 August 2026, and an earlier figure of 26.73% listed as the previous inspection with no date attached, an 11.36 point rise since the previous inspection. Only the dated reading forms a timeline row, and the inspection that produced it is covered in the City Walk Northline 1 August 2026 inspection report.
No registered completion date for City Walk Northline 1 appears in the DLD register extract used for this record, which shows registration on 1 March 2024 and the construction start on 10 August 2024 but ends before any completion date, so none is printed or estimated here. Handover is estimated for Q3 2027, and the readings that follow 19 August 2026, when the register showed 38.09%, will show whether that estimate holds.
City Walk Northline 1 is a single residential building of ground plus eight floors over a basement, with a roof level, holding 114 residential units of 1, 2 and 3 bedrooms plus one retail unit, as described in the RERA report of 19 August 2026. At that inspection the register reading for the whole building was 38.09%.
Across the whole build, City Walk Northline 1 has averaged about 1.55 points per 30-day month: 38.09 points over the 739 days from the 10 August 2024 start to the 19 August 2026 reading. That figure is arithmetic, not a forecast, and no pace between inspections can be measured yet because the earlier reading carries no date. The working is in the pace arithmetic above.
Construction at City Walk Northline 1 started on 10 August 2024, about five months after the project was registered with the DLD on 1 March 2024. The first dated reading in this record came 739 days after the start, at 38.09% on 19 August 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Northline 1 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.