City Walk Northline 2 Construction Updates
Two Podium-Linked Buildings on Central Park, Read Through the DLD Register
City Walk Northline 2 reached 37.06% on the DLD register at the 19 August 2026 inspection, its foundations complete and both podium-linked City Walk buildings climbing.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
City Walk Northline 2 at a Glance
City Walk Northline 2 is the 190-residence Meraas release on the north side of Central Park in City Walk, beside The Green Planet. Registered with the Dubai Land Department on 04 March 2024 and started on 10 August 2024, it read 37.06% on the register at the 19 August 2026 inspection, just over two years into construction. Building A and Building B share one project number and one podium, so a single register percentage covers both buildings; there is no separate reading for either one.
2972
Active
10 August 2024
190 Residential
21,204.09 sq m
Q3 2027 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
City Walk Northline 2 Construction Update Timeline
The City Walk Northline 2 record holds one dated reading so far: 37.06% on the DLD register on 19 August 2026, 739 days after the 10 August 2024 start. The register's inspection screen also shows a previous inspection at 22.62%, but without a date, so it sits on the track below as a dot and not as a table row. The single row links the August 2026 update, which lists the works recorded on that day.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 37.06% | 19 August 2026 | View the August 2026 update |
Pace Analysis
How Fast City Walk Northline 2 Has Been Built
With one dated reading on record, City Walk Northline 2 has no measured pace between inspections yet. What the record does support is two pieces of arithmetic, not a forecast, each shown with the dates it rests on:
- 10 Aug 2024 to 19 Aug 2026: whole-build average, 37.06 points over 739 daysAbout 1.50 points per month
- 19 Aug 2026 to 30 Sep 2027: the 62.94 points left to 100% by the end of Q3 2027, over 407 daysAbout 4.64 points per month
Both figures use a 30-day month, and neither is a verdict on timing. The first spreads 37.06 points evenly across two years that actually held very different work: enabling, piling and foundation works finished, then substructure, superstructure, MEP and internal finishes all progressing at once by 19 August 2026. The second simply divides what remains by the days left in the Q3 2027 estimate. The register does not add points at a constant rate: a stage dominated by structure and a stage dominated by finishing each move the percentage differently, and the handover date is for Meraas to confirm. The undated 22.62% previous reading cannot narrow the range, so the next dated reading is the one that gives this record its first measured interval: the figure an end user planning a move and an investor timing an exit should both watch, rather than either average.
Get the Next Inspection Figure First
Tell me you are tracking City Walk Northline 2 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About City Walk Northline 2 at City Walk
A 37.06% reading on 19 August 2026 is a share of two specific buildings: 190 apartments over a shared podium with an infinity-edge pool. The project guide sets out what that percentage is building toward:

City Walk Northline 2, Two Low-Rise Buildings Near Central Park
City Walk Northline 2 is a Meraas project of 190 apartments in two low-rise buildings linked by a podium.
View the City Walk Northline 2 Project GuideConsidering a Mid-Construction Entry?
Units at City Walk Northline 2 are limited, and what is open keeps shifting while the two buildings rise. If the record on this page is what brought you here, ask me what is available today before the remaining layouts narrow further.
Ask About Remaining Availability on WhatsAppStage Record
City Walk Northline 2 Build Stages, Mapped to the Inspections
Each stage below is pinned to what the register and the 19 August 2026 inspection notes actually record for City Walk Northline 2, so the finished groundworks, the structure in progress and the internal works already started are kept apart instead of being blended into one 37.06% figure.
Registration and Construction Start
Registered with the Dubai Land Department on 04 March 2024 as project 2972; the register logs construction as started on 10 August 2024, the date every figure on this page counts from.
Enabling, Piling and Foundations
The 19 August 2026 inspection notes record enabling, piling and foundation works as completed for the project, closing out the ground stage before the reading of 37.06%.
Substructure and Superstructure
Substructure and superstructure works were recorded as progressing on 19 August 2026, when the register stood at 37.06%, up from an undated previous reading of 22.62%.
MEP and Internal Finishes
Internal works with MEP and internal finishes were also recorded as progressing on 19 August 2026, running alongside the frame rather than waiting for it to finish.
Completion and Handover
The remaining 62.94 points after 19 August 2026 and the handover of 190 residences, estimated for Q3 2027 and confirmed by Meraas; no completion is recorded yet.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on City Walk Northline 2's own record.
Buyer Position
Tracking Your Position at City Walk Northline 2
This page is one of four project resources that together cover a City Walk Northline 2 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

City Walk Northline 2 Construction Updates
This page: every DLD register reading for City Walk Northline 2 from construction start to handover.

City Walk Northline 2 Golden Visa: The Narrowest Margin at 1 Bedroom
City Walk Northline 2, 190 Meraas apartments, clears the threshold at all three types, the 1 bedroom by the narrowest margin.
Read the City Walk Northline 2 Golden Visa Guide
City Walk Northline 2: The Second Northline Escrow Account
First Abu Dhabi Bank holds City Walk Northline 2 escrow, DLD project 2972, 192 units, certified 37.06% in August 2026.
Verify the City Walk Northline 2 Escrow AccountApproaching Handover
Between 37.06% and Handover: What City Walk Northline 2 Buyers Should Do Now
At 37.06% on 19 August 2026, City Walk Northline 2 sits in the middle portion of its 75/25 Payment Plan: after the 20% paid on booking and before the 25% due on handover, the 55% construction share is the part of the price that moves while the two buildings rise, on dates your SPA sets. An instalment that has not yet left your account is far easier to check than one that has, so the three steps below belong before the next payment, not after it.
First, before each construction-share instalment, confirm the receiving account against the City Walk Northline 2 escrow account page, which sets out the First Abu Dhabi Bank trust account registered for project 2972.
Second, if residency is part of the plan, settle the timing question on the City Walk Northline 2 Golden Visa guide, since the Oqood held during construction and the title deed issued after handover lead to different application paths.
Third, read the inspection notes that explain the percentage in the City Walk Northline 2 August 2026 construction update, which separates the completed foundations from the structure and internal works still progressing.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore City Walk Structure
Two low-rise buildings at 37.06% on 19 August 2026 are rising inside a district that is already built and trading. These three pages put the City Walk Northline 2 record in its market, neighbourhood and developer context:

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
City Walk Northline 2 Construction Updates Frequently Asked Questions
City Walk Northline 2 (DLD project 2972) was registered with the Dubai Land Department on 04 March 2024, construction started on 10 August 2024, and the register recorded 37.06% progress on 19 August 2026. Handover is estimated for Q3 2027. Each dated reading is listed in the inspection timeline above.
Two figures appear on the register's inspection screen for City Walk Northline 2: 37.06% dated 19 August 2026, and a previous inspection reading of 22.62% that carries no date, 14.44 points lower. Only the dated reading has a timeline row; the undated one is shown as a dot on the track. The inspection notes for the dated reading are in the City Walk Northline 2 August 2026 inspection update.
No measured pace exists yet for City Walk Northline 2, because 19 August 2026 is the only dated reading. As arithmetic, not a forecast, 37.06 points over the 739 days since the 10 August 2024 start averages about 1.50 points per 30-day month, and the 62.94 points still open after 19 August 2026, spread over the 407 days to 30 September 2027, come to about 4.64 points per 30-day month. Register percentages do not accrue evenly from one inspection to the next, and the handover date is the developer's to confirm. The working is in the pace analysis above.
The DLD record reviewed for this page shows City Walk Northline 2 as registered on 04 March 2024 and started on 10 August 2024, but the registered completion date is not part of that evidence, and the RERA report of 19 August 2026 has no field for it, so none is printed here. The handover estimate for the project is Q3 2027, a date Meraas confirms.
The record sits under DLD project number 2972 in the Dubai Land Department's Dubai REST app, where the project details screen lists the status (Active) and the registration and start dates, and the inspection report screen shows the current and previous progress readings. Searching 2972 there shows whether a reading newer than the 37.06% of 19 August 2026 has been published since this page was updated.
Every percentage for City Walk Northline 2 on this page is a Dubai Land Department register reading for project 2972, read alongside the RERA Independent Progress Monitoring Report of the same date. The report for 19 August 2026 records the works and a progress status of Main Contract, Progressing, but prints no percentage, so the 37.06% figure is attributed to the register. A new timeline row is added for each dated reading, and the method shared by every project is described on the Dubai Construction Updates hub.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the City Walk Northline 2 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.