Club Place Construction Update - February 2026

February 2026 Inspection Confirms Club Place Reaches 60.02% Construction Progress at Dubai Hills Estate

Envelope installation, building services, and internal fit out now drive activity across all three Club Place buildings, verified at 60.02 percent on 19 February 2026.

Direct advisor access. Every message answered personally, never by a call center.

60.02%Construction Progress
19 February 2026Inspection Date
Q4 2028Expected Completion
3197DLD Project Number

Verified DLD Inspection Data

Club Place Construction Snapshot

A 17.35 point rise since the previous recorded inspection puts Club Place in the envelope and services band, the stage where what gets certified stops being concrete and starts being the systems and finishes inside the apartments.

Project Name

Club Place by Emaar

Project Number

3197

Project Status

Active

Construction Progress

60.02%

Inspection Date

19 February 2026

Construction Start

10 September 2024

Total Units

473 residential units

Total Built Area

46,603.92 sq m

Expected Completion

Q4 2028

Data source: RERA inspection conducted on 19 February 2026, tracked against DLD inspection records for project 3197. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Club Place Construction Progress Summary

Club Place moved from a recorded 42.67% to 60.02% at the 19 February 2026 inspection, a 17.35 point gain logged on a site where the concrete phase is already closed. The RERA report for this cycle lists enabling, foundation, and structural works as complete, with external envelope, MEP, internal works, and internal finishes all progressing at different stages across the three buildings.

Completed
  • Enabling and foundation works across plot 4961
  • Structural works on Building A (B+G+P+20) and Building B (B+G+P+17)
  • Structural works on the low rise Building C over the shared podium
In Progress at 60.02%
  • External envelope installation across the tower elevations
  • MEP works: mechanical, electrical, and plumbing systems
  • Internal works advancing at different stages in both towers
  • Internal finishes across the 473 one, two, and three bedroom apartments
Ahead of Handover
  • Remaining RERA inspection cycles between 60.02% and 100%
  • Completion certification recorded against DLD project 3197
  • Handover to buyers from the Q4 2028 completion window
Next inspectionCommissioned by RERA and posted to the DLD project register once the site audit is filed; this page carries the February 2026 reading only.
Completion targetQ4 2028 per the current record, roughly two years and ten months beyond this inspection date.
Remaining distance39.98 percentage points remain between this reading and full certification at 100%.

Payment Linked Progress

What 60.02% Progress Means for Club Place Buyers

Emaar structured Club Place on an 80/20 construction linked plan, so several instalments are released by certified construction percentage rather than by calendar date. A verified reading of 60.02% therefore does more than describe the site: it tells you which triggers in that schedule have already been met. Four checks matter at this stage.

Before Your Next Transfer

Verify the escrow account

Every instalment ahead of handover should reach only the DLD regulated escrow account registered for project 3197, and the February 2026 RERA report names Emirates NBD Bank as the trust account holder. Confirm the account and the project number together through Club Place escrow account verification before you release funds; the lookup itself takes about two minutes against the official DLD project record.

Milestone Already Certified

Reread your SPA milestone schedule

The published schedule ties later instalments to 20%, 40%, 60%, 80%, and 100% construction completion, and the 60% threshold now sits below the certified reading. Not sure which triggers your unit has already cleared? Send me your SPA schedule and I will map it against the certified milestones.

Not Yet Open

Note where the snagging window sits

Buyers usually book independent defect documentation once a build clears about 70 percent, or once handover falls inside nine months. Club Place satisfies neither condition in February 2026, so this is a step to schedule ahead rather than act on now. The Club Place snagging inspection guide explains what an independent inspector records and when that report has to exist.

Every Cycle

Track the readings toward 80%

The next construction linked trigger in the published plan sits at 80%, so the cycles between now and then carry direct payment consequences. The Club Place construction updates hub keeps every certified percentage in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 60.02%?

Entering here means the structural risk is behind the project and the open question is delivery rather than construction: all three buildings are framed, inspected, and recorded, while the community around them has been trading for years. Every payment goes to the DLD-registered escrow account for project 3197, released against certified construction progress.

Entering Now at 60.02%
  • Structure certified: enabling, foundation, and all three buildings framed
  • Roughly two years and ten months to the expected Q4 2028 handover
  • Remaining balance still spreads across the construction linked schedule
Typical Launch Entry
  • Construction risk carried from excavation through to handover
  • Four to five years is the usual wait between launch and keys
  • Longer instalment runway, priced at launch levels
AED 1.45M ≈ USD 395KStarting Price
80/20 Plan20% Due on Completion
From Q4 2028Expected Handover

06 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Club Place Project Details

Club Place by Emaar in Dubai Hills Estate residential tower terrace overlooking the championship golf course villas and palm lined fairways in Dubai - Presented by Tohid Fetrat
Dubai Hills Estate · Emaar Properties

With every structural frame closed, Club Place is now a fit out stage development of 473 one, two, and three bedroom apartments across three buildings on the golf edge of Dubai Hills Estate. Starting prices: AED 1.45M ≈ USD 395K.

Buyers entering at this reading trade a shorter construction risk window for a schedule that is already part paid, with handover expected in Q4 2028 and six units left with the developer.

Site Context This Cycle

Explore Club Place Location on Dubai Map

Club Place occupies plot 4961 on the eastern golf side of Dubai Hills Estate, its three buildings turned toward the championship fairways rather than the internal road, which is why external envelope work on the golf facing elevations is among the most visible items in this inspection cycle.

The golf club, the central park, Dubai Hills Mall, King's College Hospital, and the GEMS campus are already open and trading, so the district around plot 4961 is finished while the buildings on it are not. That inverts the usual off plan sequence: a Club Place buyer is underwriting the delivery of three towers, not the arrival of a neighborhood, and it removes the variable that normally decides whether a Q4 2028 handover lands into working rents and available school places. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Club Place During Active Construction Progress

The envelope and services band is where residency thresholds, payment protection, and delivery tracking start to overlap. Each resource below is matched to where Club Place stands right now.

Club Place by Emaar in Dubai Hills Estate construction updates showing the residential tower pool deck and landscaped podium in Dubai - Presented by Tohid Fetrat
You Are Here

Club Place Construction Updates

This page: the verified February 2026 inspection record for Club Place, from foundations to handover.

Club Place by Emaar in Dubai Hills Estate Golden Visa eligibility concept with illuminated residential entrance and Golden Visa card in Dubai - Presented by Tohid Fetrat

Club Place at Dubai Hills Estate Golden Visa by the Golf Course

At Club Place at Dubai Hills Estate, Emaar's 473 apartments, the threshold falls between the one and two bedroom tiers.

Read the Club Place Golden Visa Guide
Club Place by Emaar in Dubai Hills Estate escrow account protection concept for buyer payments with tower facade and pool deck in Dubai - Presented by Tohid Fetrat

Club Place at Dubai Hills Estate Escrow, an Emirates NBD Account

Club Place at Dubai Hills Estate pays Emirates NBD escrow under DLD project 3197, 473 units, 68.82% certified June 2026.

Verify the Club Place Escrow Account
Club Place by Emaar in Dubai Hills Estate snagging inspection concept for handover quality checks in a bedroom overlooking the community in Dubai - Presented by Tohid Fetrat

Club Place at Dubai Hills Estate Snagging Above a Landscaped Podium

Club Place at Dubai Hills Estate is a three-building Emaar Properties development on the golf course edge, holding 473 freehold residences.

Book the Club Place Snagging Inspection

Update Timeline

Other Club Place Construction Updates

Follow the full inspection history to see how Club Place has moved through each construction phase, reading by reading.

Next Update →June 2026 InspectionAll UpdatesClub Place Construction Updates Hub
Future Cycles · One Message Per CycleGet notified the day each reading publishes
All Club Place Construction Updates

FAQs

Club Place Construction Progress in February 2026: Frequently Asked Questions

As of the RERA inspection conducted on 19 February 2026, Club Place stands at 60.02% construction progress in the DLD project register under project number 3197.

The DLD record shows Club Place moving from 42.67% at the previous recorded inspection to 60.02% on 19 February 2026, a gain of 17.35 points logged across external envelope, MEP, internal works, and internal finishes.

The February 2026 record shows no revision: expected completion remains Q4 2028 as of this update, with 39.98 percentage points between the 19 February 2026 reading and full certification, and roughly two years and ten months before the registered completion window. The mechanics behind inspection cycles and completion certification are set out on the Club Place construction updates hub.

Yes. The DLD project register carries expected completion as a forecast rather than a guarantee, and it can be revised at any inspection cycle. Q4 2028 is what both the register and the published payment schedule showed when the 19 February 2026 reading was verified, and a revision would surface in the register first, then in the next update on this cluster.

With enabling, foundation, and structural works recorded as complete at the 19 February 2026 inspection, site activity centers on external envelope installation, mechanical, electrical, and plumbing systems, internal works, and internal finishes across the 473 apartments, all progressing at different stages.

Emaar's published Club Place schedule links later instalments to 20%, 40%, 60%, 80%, and 100% construction completion, so the 60% trigger sits below the 60.02% recorded on 19 February 2026. Whether a specific instalment has been called depends on the individual sale and purchase agreement and the developer's notice, not on the inspection record alone.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the February 2026 inspection record for Club Place at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.