Imtiaz Developments · Dubai Islands
Cotier House Construction Updates
The Dated Build Record of a Marina-Front Building on Island A
Cotier House reached 43.47% construction at its 14 August 2026 RERA inspection, its frame, interiors and services on an Island A marina plot climbing together since foundations.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Cotier House at a Glance
Cotier House is a single G+2P+10+R building of 137 residences that Imtiaz Developments is raising on a marina-front plot on Island A at Dubai Islands. Work on site began on 15 January 2025, 29 days before the 13 February 2025 DLD registration, and the register read 43.47% on 14 August 2026. One building and one dated reading put this record at its opening chapter: every later inspection adds a dated point, and together those points will turn today's snapshot into a measurable curve.
3394
Active
15 January 2025
137 residential units
16,493.22 sq m
15 January 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Cotier House Construction Update Timeline
So far the Cotier House record holds one dated reading: 43.47% at the RERA inspection of 14 August 2026, listed in the register beside a previous reading of 29.21% that carries no date, a step of 14.26 points. The track below plots both, and the table links the August 2026 update, which is illustrated with a developer rendering rather than site photography, so the dated evidence here is the register figure and the inspection notes behind it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 43.47% | 14 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Cotier House Has Been Built
With only one dated reading, the Cotier House pace can be expressed only as arithmetic between registered dates, shown here as arithmetic and not as a forecast:
- 15 Jan 2025 to 14 Aug 2026: whole-build average, 0% to 43.47%About 2.3 points per month
- Undated previous reading to 14 Aug 2026: 29.21% to 43.47%Up 14.26 points, no monthly rate
- 14 Aug 2026 to the 15 Jan 2027 registered completion: 43.47% to 100%About 11.2 points per month needed
Two averages are not a curve, and this record does not have one yet. The 2.3-point figure folds roughly 19 months of enabling works, foundations and frame into a single line, while the 14.26-point step from 29.21% cannot be timed because the register leaves that earlier reading undated. What the arithmetic does expose is distance: holding the 15 January 2027 registered date would take close to five times the whole-build average across the 154 days after the 14 August 2026 reading. That is a gap to watch, not a verdict on delivery. An investor should treat the next dated reading as the first real velocity figure this building produces; an end user should read the completion and delay clauses of the sale and purchase agreement, because those, not this arithmetic, define the position if the registered date moves.
Get the Next Inspection Figure First
Tell me you are tracking Cotier House and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Cotier House at Island A
A construction percentage means little without the building it measures. The project guide sets out what the 43.47% recorded on 14 August 2026 is building toward:

Cotier House: A First-Line Marina Building on Island A
Cotier House by Imtiaz holds 137 freehold residences on Island A at Dubai Islands, apartments, townhouses and duplexes.
View the Cotier House Project GuideConsidering the Last Listed Unit?
Cotier House is close to sold out, with a single unit listed as available on the project page at the time of this record. If this construction record is what brought you here, ask me whether it is still open before you plan around it.
Ask About Remaining Availability on WhatsAppStage Record
Cotier House Build Stages, Mapped to the Inspections
Each stage below is pinned to the Cotier House dates that bound it, from the 15 January 2025 start to the 15 January 2027 registered completion, so the 43.47% recorded on 14 August 2026 reads as a position in a sequence rather than a number on its own.
Site Start and DLD Registration
Construction started on 15 January 2025, and the project was registered as DLD project 3394 on 13 February 2025, 29 days after work began on the Island A plot.
Enabling Works and Foundations
The 14 August 2026 inspection report lists enabling and foundation works as completed for the G+2P+10+R building, the first stage this record confirms as closed.
Frame, Interiors and MEP in Parallel
On 14 August 2026 the notes had the frame, internal works, internal finishes and MEP all moving at once, taking the register from an undated 29.21% to 43.47%, while mobilization continued.
Wave-Inspired Facade and Balconies
Nothing in the 14 August 2026 notes covers the wave-inspired facade or the curved glass balconies, so the building's most visible layer is still to come.
Finishing, Completion and Handover
The 56.53 points still open after the 14 August 2026 reading close out the build, with registered completion on 15 January 2027 and handover expected in Q1 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cotier House's own record.
Buyer Position
Tracking Your Position at Cotier House
This page is one of four project resources that together cover a Cotier House purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cotier House Construction Updates
This page: the dated DLD inspection record for Cotier House, from its January 2025 start.

Cotier House Golden Visa From Any Single Marina-Front Home
Imtiaz Developments' Cotier House, 137 residences on Island A, qualifies at every tier from 1 bedroom apartment to duplex.
Read the Cotier House Golden Visa Guide
Cotier House Escrow: Imtiaz Developments on Island A
Cotier House on Island A escrows 137 units with First Abu Dhabi Bank, DLD project 3394, certified 43.47% in August 2026.
Verify the Cotier House Escrow AccountApproaching Handover
Between 43.47% and Handover: What Cotier House Buyers Should Do Now
At 43.47% on 14 August 2026, Cotier House is past its foundations but short of its facade, so buyer attention belongs on the money and the record rather than on handover logistics. The launch schedule had billed 60% of the price by 15 July 2026 while 40% waits for completion, and with every dated instalment now past its date, a buyer coming in today usually clears those on signing, with the exact split confirmed with the developer: the three steps below come before that transfer, not after it.
First, match every transfer to the project 3394 escrow account through the Cotier House escrow account page, so instalments already due and the later 40% completion payment land in the regulated account and nowhere else.
Second, read each new register figure as it arrives; the Cotier House August 2026 construction update holds the inspection notes behind the current 43.47%, and later months join the timeline above as dated readings.
Third, if residency is part of the plan, work through the Cotier House Golden Visa eligibility guide now, since the ownership evidence available for an unfinished unit differs from the title deed issued after completion.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
One building's record reads differently when the island around it is still taking shape. These three pages place the Cotier House reading of 43.47% on 14 August 2026 in its market, community and developer context:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Cotier House Construction Updates Frequently Asked Questions
Cotier House stood at 43.47% construction progress on 14 August 2026 in the DLD register for project 3394, which places the building in its frame-and-interiors stage: foundations are closed out, and the frame, interior works and MEP are advancing side by side. Facade works do not yet appear in the inspection notes; the full sequence is in the Cotier House stage record above.
The Cotier House record holds one dated reading, 43.47% on 14 August 2026, and one undated previous reading of 29.21% shown beside it in the DLD register, a difference of 14.26 percentage points. Both sit in the inspection timeline above, and the inspection notes behind the dated figure are on the August 2026 Cotier House inspection page.
The DLD register lists 15 January 2027 as the registered completion date for Cotier House, a date inside the expected Q1 2027 handover that had not yet passed when this record was prepared. From the 14 August 2026 reading of 43.47%, the building had 154 days and 56.53 percentage points to cover before that date. Should a later registered date ever be filed, the change appears in the DLD register itself, and this page is updated when the next reading is recorded.
G+2P+10+R is the configuration recorded for Cotier House in the RERA inspection report of 14 August 2026: a ground floor, two podium levels, ten residential floors and a roof, all in one building holding 137 residential units, including the podium-level townhouses. At that inspection the register read 43.47% for the whole building.
Across the 576 days from the 15 January 2025 start to the 14 August 2026 reading of 43.47%, Cotier House averaged about 2.3 percentage points per month; reaching 100% by the 15 January 2027 registered completion would need about 11.2 points per month over the remaining 154 days. Both figures are arithmetic, not a forecast, and because the 29.21% previous reading is undated, no measured monthly pace exists yet. The workings are in the Cotier House pace analysis above.
Construction at Cotier House started on 15 January 2025, and the project was registered with the DLD as project 3394 on 13 February 2025, 29 days later. The first dated reading in this record, 43.47%, came from the RERA inspection of 14 August 2026, 576 days after the start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cotier House construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.