Cove Edition 5 by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the residential building and landscaped frontage in Dubai - Presented by Tohid Fetrat

Imtiaz · Dubai Land Residence Complex

Cove Edition 5 by Imtiaz Construction Updates

The Dated Register Record of One 2B+G+11+R Building in Dubailand

Cove Edition 5 by Imtiaz read 26.32% on the DLD register on 18 August 2026, a climb carrying the building from completed foundations into its rising superstructure.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

26.32%Construction Progress
18 August 2026Latest RERA Inspection
198 residencesTotal Units
Project 3705DLD Registration

Construction Snapshot

Cove Edition 5 by Imtiaz at a Glance

Cove Edition 5 by Imtiaz is a single 2B+G+11+R residential building of 198 apartments in Dubai Land Residence Complex, entered in the DLD project register as number 3705, with construction recorded as started on 20-05-2025 and the project registered on 22-05-2025. Its registered completion date of 20-05-2027 falls inside the Q2 2027 handover Imtiaz estimates, and the report card of 18 August 2026 read 26.32%. With two basement levels beneath 11 residential floors, part of the work that figure measures sits below ground, worth keeping in mind when reading a percentage taken while the superstructure was still rising.

DLD Project Number

3705

Project Status

Active

Construction Start

20-05-2025

Total Units

198 residences

Total Built-Up Area

10,534.37 sq m

Registered Completion Date

20-05-2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Cove Edition 5 by Imtiaz Construction Update Timeline

The Cove Edition 5 record holds one dated reading so far: 26.32% on the DLD report card of 18 August 2026, printed beside an earlier 16.07% that the card leaves undated, a rise of 10.25 points since that previous reading. The track below marks both figures, but only the August reading carries a date, so it alone gets a table row and a link to the full August 2026 update.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202626.32%18 August 2026View the August 2026 update

Pace Analysis

How Fast Cove Edition 5 by Imtiaz Has Been Built

With a single dated reading, the Cove Edition 5 record cannot yet show a pace between two inspections. What it can show is the average from the recorded start, and why the earlier figure on the same report card gives no pace:

  • 20-05-2025 to 18-08-2026: enabling works, foundations and rising superstructure, construction start to 26.32%About 1.74 points per month
  • Undated previous reading to 18-08-2026: 16.07% to 26.32%No pace, earlier date not shown

The 1.74 figure is arithmetic, not a forecast: 26.32 points spread over the 455 days between the recorded start and the August 2026 report card, on a 30-day month. Those 455 days carried the enabling works and foundations RERA recorded as completed, plus substructure work for two basement levels that was still progressing on 18 August 2026, so the average blends below-ground months with the first above-ground floors of the 2B+G+11+R frame. Whether the climb has quickened as the 11 residential floors repeat is the question the next dated reading answers; set against 18 August 2026, it will give this building its first measured pace between inspections. Until then, an end user tracking the Q2 2027 handover estimate and an investor timing an entry are reading the same two things: the newest DLD figure for project 3705 on Dubai REST, which has very likely moved since August, and the handover timetable Imtiaz confirms in writing.

Get the Next Inspection Figure First

Tell me you are tracking Cove Edition 5 by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Cove Edition 5 by Imtiaz at Dubai Land Residence Complex

A 26.32% reading only means something next to what is being built: one building of 198 furnished apartments over two basement levels. The full project guide covers what buyers are tracking toward on this page:

Cove Edition 5 by Imtiaz in Dubai Land Residence Complex project rendering of the residential building with balconies and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Cove Edition 5 by Imtiaz: A Rooftop Leisure Level in Dubailand

Cove Edition 5 by Imtiaz is a building of 198 studio, one and two bedroom apartments, each furnished with custom-designed furniture.

View the Cove Edition 5 by Imtiaz Project Guide

Considering a Mid-Construction Entry?

Limited units remain available at Cove Edition 5 as of this update, and availability moves as the building rises. If the record on this page is what brought you here, ask me for current availability and the instalments a buyer entering now would settle at signing, per the developer's current terms.

Ask About Remaining Availability on WhatsApp

Stage Record

Cove Edition 5 by Imtiaz Build Stages, Mapped to the Inspections

Each stage below is pinned to what the 18 August 2026 RERA report recorded for Cove Edition 5, so the record shows which work was finished, which was under way at 26.32%, and which lies ahead of that reading.

From 20-05-2025

Site Activation and Enabling Works

Construction was recorded as started on 20-05-2025 and the project registered on 22-05-2025; the enabling works of this stage were listed as completed by RERA on 18 August 2026.

Completed by 18 Aug 2026

Foundations and Two Basement Levels

Foundation works were recorded as completed at the 18 August 2026 inspection, while substructure works for the two basement levels were still progressing that day.

Current PhaseUnder way at 26.32%, 18 Aug 2026

The 2B+G+11+R Superstructure

RERA recorded the superstructure progressing on 18 August 2026, the day the DLD register read 26.32% for project 3705; the latest dated record sits in this stage.

After the superstructure

Internal Works, Fit-Out and Furnishing

Internal works were noted at site on 18 August 2026; fit-out of the 198 furnished apartments and the rooftop pool deck, gym and clubhouse follows the frame.

Toward Q2 2027

Final Inspections and Handover

Readings climb toward 100% ahead of handover, estimated by Imtiaz for Q2 2027 against a registered completion date of 20-05-2027; confirm the timetable in writing.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Edition 5 by Imtiaz's own record.

Buyer Position

Tracking Your Position at Cove Edition 5 by Imtiaz

This page is one of four project resources that together cover a Cove Edition 5 by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Edition 5 by Imtiaz in Dubai Land Residence Complex construction updates cover image featuring a project rendering of the residential building and landscaped frontage in Dubai - Presented by Tohid Fetrat
You Are Here

Cove Edition 5 by Imtiaz Construction Updates

This page: the dated DLD register record for Cove Edition 5 from its May 2025 start.

Cove Edition 5 by Imtiaz in Dubai Land Residence Complex Golden Visa concept graphic featuring a gold card over a rendered residential building facade in Dubai - Presented by Tohid Fetrat

Cove Edition 5 by Imtiaz Golden Visa: A 2B+G+11+R Building

Cove Edition 5, Imtiaz Developments' 198 apartments under DLD project 3705, has no studio, 1 or 2 bedroom at the threshold.

Read the Cove Edition 5 by Imtiaz Golden Visa Guide
Cove Edition 5 by Imtiaz in Dubai Land Residence Complex escrow account concept graphic with a shield and padlock above a rendered landscaped building podium in Dubai - Presented by Tohid Fetrat

Cove Edition 5 by Imtiaz Escrow: 198 Units, One Account

Cove Edition 5 by Imtiaz escrows 198 units at Dubai Islamic Bank under DLD project 3705, 26.32% certified in August 2026.

Verify the Cove Edition 5 by Imtiaz Escrow Account

Approaching Handover

Between 26.32% and Handover: What Cove Edition 5 by Imtiaz Buyers Should Do Now

At the 18 August 2026 reading the Cove Edition 5 superstructure was still rising, so the useful work for buyers sits on the payment side rather than the handover side: on that date the dated shares already due came to 40% of the price on Option 1 (50/50) and 50% on Option 2 (70/30), set against a 26.32% register figure. The 15 October 2026 instalment in both plans fell due after that reading, and Option 1 carries a further 5% dated 15 February 2027, so the three checks below belong before the next transfer, not after it.

First, before any construction-period transfer, confirm the receiving account on the Cove Edition 5 escrow account page, which walks through the Dubai Islamic Bank account registered to project 3705.

Second, if UAE residency is part of the plan, read the Cove Edition 5 Golden Visa guide while the building is still off plan, since how your apartment price compares with the property route shapes the options before any title deed exists.

Third, follow the dated readings rather than the calendar: each new DLD figure for project 3705 joins the inspection timeline on this page, and the Q2 2027 handover estimate is worth confirming in writing with Imtiaz as the record moves.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Land Residence Complex Structure

A register reading is only half the picture; the rest is the community the building joins and the developer delivering it. These three pages put Cove Edition 5 in that context:

Dubailand Residence Complex properties for sale in Dubai showing a modern residential building with balconies and landscaped surroundings, Presented by Tohid Fetrat

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand

Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.

See Dubai Land Residence Complex Properties for Sale
Street view of Dubailand Residence Complex community in Dubai showing modern residential buildings, landscaped roads and pedestrian areas, Presented by Tohid Fetrat

Dubai Land Residence Complex: Dubailand's Established Apartment Community

Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.

Explore the Dubai Land Residence Complex Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Cove Edition 5 by Imtiaz Construction Updates Frequently Asked Questions

Cove Edition 5 by Imtiaz is an active DLD-registered project (number 3705) whose latest reading on this record is 26.32%, from the DLD report card of 18 August 2026, when RERA recorded the main contract as progressing with substructure, superstructure and internal works under way. A newer reading may have been posted on Dubai REST since then; the dated record sits in the inspection timeline above.

The latest reading on this record is 26.32%, shown on the DLD report card dated 18 August 2026 for project 3705 beside an earlier figure of 16.07% that the card leaves undated. Both figures come from the DLD register, because the RERA monitoring report issued for that inspection carries no percentage, and the month is covered in full in the Cove Edition 5 August 2026 construction update.

The DLD register lists 20-05-2027 as the registered completion date for project 3705, a date still ahead at the 18 August 2026 reading of 26.32%, while Imtiaz estimates handover for Q2 2027, the quarter that contains it. Either date can be revised as the build moves, so the timetable worth relying on is the one Imtiaz confirms to buyers in writing, read next to the newest register figure on Dubai REST.

Cove Edition 5 is entered in the DLD project register with 198 units, the same 198 residences Imtiaz lists: studio, 1 bedroom and 2 bedroom apartments that the developer markets as fully furnished. All 198 sit in a single residential building, which read 26.32% at the 18 August 2026 inspection.

The 2B+G+11+R configuration of Cove Edition 5 means two basement levels, a ground floor, 11 residential floors and a roof level, the description carried by both the RERA report of 18 August 2026 and Imtiaz's fact sheet. The developer's floor plans place the main lobby on the ground floor and the pool deck, gym and clubhouse on the roof; at that inspection the substructure and superstructure were both recorded as progressing.

Counting from the 20-05-2025 construction start in the register, Cove Edition 5 averaged about 1.74 points per month up to its 26.32% reading of 18 August 2026, which is 26.32 points over 455 days on a 30-day month; that figure is arithmetic, not a forecast. The earlier 16.07% reading carries no date, so a pace between two inspections becomes measurable only with the next dated reading, as the pace analysis above explains.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Edition 5 by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status