Imtiaz · Dubai Land Residence Complex
Cove Edition 5 by Imtiaz Construction Updates
The Dated Register Record of One 2B+G+11+R Building in Dubailand
Cove Edition 5 by Imtiaz read 26.32% on the DLD register on 18 August 2026, a climb carrying the building from completed foundations into its rising superstructure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Cove Edition 5 by Imtiaz at a Glance
Cove Edition 5 by Imtiaz is a single 2B+G+11+R residential building of 198 apartments in Dubai Land Residence Complex, entered in the DLD project register as number 3705, with construction recorded as started on 20-05-2025 and the project registered on 22-05-2025. Its registered completion date of 20-05-2027 falls inside the Q2 2027 handover Imtiaz estimates, and the report card of 18 August 2026 read 26.32%. With two basement levels beneath 11 residential floors, part of the work that figure measures sits below ground, worth keeping in mind when reading a percentage taken while the superstructure was still rising.
3705
Active
20-05-2025
198 residences
10,534.37 sq m
20-05-2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Cove Edition 5 by Imtiaz Construction Update Timeline
The Cove Edition 5 record holds one dated reading so far: 26.32% on the DLD report card of 18 August 2026, printed beside an earlier 16.07% that the card leaves undated, a rise of 10.25 points since that previous reading. The track below marks both figures, but only the August reading carries a date, so it alone gets a table row and a link to the full August 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 26.32% | 18 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Cove Edition 5 by Imtiaz Has Been Built
With a single dated reading, the Cove Edition 5 record cannot yet show a pace between two inspections. What it can show is the average from the recorded start, and why the earlier figure on the same report card gives no pace:
- 20-05-2025 to 18-08-2026: enabling works, foundations and rising superstructure, construction start to 26.32%About 1.74 points per month
- Undated previous reading to 18-08-2026: 16.07% to 26.32%No pace, earlier date not shown
The 1.74 figure is arithmetic, not a forecast: 26.32 points spread over the 455 days between the recorded start and the August 2026 report card, on a 30-day month. Those 455 days carried the enabling works and foundations RERA recorded as completed, plus substructure work for two basement levels that was still progressing on 18 August 2026, so the average blends below-ground months with the first above-ground floors of the 2B+G+11+R frame. Whether the climb has quickened as the 11 residential floors repeat is the question the next dated reading answers; set against 18 August 2026, it will give this building its first measured pace between inspections. Until then, an end user tracking the Q2 2027 handover estimate and an investor timing an entry are reading the same two things: the newest DLD figure for project 3705 on Dubai REST, which has very likely moved since August, and the handover timetable Imtiaz confirms in writing.
Get the Next Inspection Figure First
Tell me you are tracking Cove Edition 5 by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Cove Edition 5 by Imtiaz at Dubai Land Residence Complex
A 26.32% reading only means something next to what is being built: one building of 198 furnished apartments over two basement levels. The full project guide covers what buyers are tracking toward on this page:

Cove Edition 5 by Imtiaz: A Rooftop Leisure Level in Dubailand
Cove Edition 5 by Imtiaz is a building of 198 studio, one and two bedroom apartments, each furnished with custom-designed furniture.
View the Cove Edition 5 by Imtiaz Project GuideConsidering a Mid-Construction Entry?
Limited units remain available at Cove Edition 5 as of this update, and availability moves as the building rises. If the record on this page is what brought you here, ask me for current availability and the instalments a buyer entering now would settle at signing, per the developer's current terms.
Ask About Remaining Availability on WhatsAppStage Record
Cove Edition 5 by Imtiaz Build Stages, Mapped to the Inspections
Each stage below is pinned to what the 18 August 2026 RERA report recorded for Cove Edition 5, so the record shows which work was finished, which was under way at 26.32%, and which lies ahead of that reading.
Site Activation and Enabling Works
Construction was recorded as started on 20-05-2025 and the project registered on 22-05-2025; the enabling works of this stage were listed as completed by RERA on 18 August 2026.
Foundations and Two Basement Levels
Foundation works were recorded as completed at the 18 August 2026 inspection, while substructure works for the two basement levels were still progressing that day.
The 2B+G+11+R Superstructure
RERA recorded the superstructure progressing on 18 August 2026, the day the DLD register read 26.32% for project 3705; the latest dated record sits in this stage.
Internal Works, Fit-Out and Furnishing
Internal works were noted at site on 18 August 2026; fit-out of the 198 furnished apartments and the rooftop pool deck, gym and clubhouse follows the frame.
Final Inspections and Handover
Readings climb toward 100% ahead of handover, estimated by Imtiaz for Q2 2027 against a registered completion date of 20-05-2027; confirm the timetable in writing.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Edition 5 by Imtiaz's own record.
Buyer Position
Tracking Your Position at Cove Edition 5 by Imtiaz
This page is one of four project resources that together cover a Cove Edition 5 by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Edition 5 by Imtiaz Construction Updates
This page: the dated DLD register record for Cove Edition 5 from its May 2025 start.

Cove Edition 5 by Imtiaz Golden Visa: A 2B+G+11+R Building
Cove Edition 5, Imtiaz Developments' 198 apartments under DLD project 3705, has no studio, 1 or 2 bedroom at the threshold.
Read the Cove Edition 5 by Imtiaz Golden Visa Guide
Cove Edition 5 by Imtiaz Escrow: 198 Units, One Account
Cove Edition 5 by Imtiaz escrows 198 units at Dubai Islamic Bank under DLD project 3705, 26.32% certified in August 2026.
Verify the Cove Edition 5 by Imtiaz Escrow AccountApproaching Handover
Between 26.32% and Handover: What Cove Edition 5 by Imtiaz Buyers Should Do Now
At the 18 August 2026 reading the Cove Edition 5 superstructure was still rising, so the useful work for buyers sits on the payment side rather than the handover side: on that date the dated shares already due came to 40% of the price on Option 1 (50/50) and 50% on Option 2 (70/30), set against a 26.32% register figure. The 15 October 2026 instalment in both plans fell due after that reading, and Option 1 carries a further 5% dated 15 February 2027, so the three checks below belong before the next transfer, not after it.
First, before any construction-period transfer, confirm the receiving account on the Cove Edition 5 escrow account page, which walks through the Dubai Islamic Bank account registered to project 3705.
Second, if UAE residency is part of the plan, read the Cove Edition 5 Golden Visa guide while the building is still off plan, since how your apartment price compares with the property route shapes the options before any title deed exists.
Third, follow the dated readings rather than the calendar: each new DLD figure for project 3705 joins the inspection timeline on this page, and the Q2 2027 handover estimate is worth confirming in writing with Imtiaz as the record moves.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Land Residence Complex Structure
A register reading is only half the picture; the rest is the community the building joins and the developer delivering it. These three pages put Cove Edition 5 in that context:

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand
Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.
See Dubai Land Residence Complex Properties for Sale
Dubai Land Residence Complex: Dubailand's Established Apartment Community
Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.
Explore the Dubai Land Residence Complex Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Cove Edition 5 by Imtiaz Construction Updates Frequently Asked Questions
Cove Edition 5 by Imtiaz is an active DLD-registered project (number 3705) whose latest reading on this record is 26.32%, from the DLD report card of 18 August 2026, when RERA recorded the main contract as progressing with substructure, superstructure and internal works under way. A newer reading may have been posted on Dubai REST since then; the dated record sits in the inspection timeline above.
The latest reading on this record is 26.32%, shown on the DLD report card dated 18 August 2026 for project 3705 beside an earlier figure of 16.07% that the card leaves undated. Both figures come from the DLD register, because the RERA monitoring report issued for that inspection carries no percentage, and the month is covered in full in the Cove Edition 5 August 2026 construction update.
The DLD register lists 20-05-2027 as the registered completion date for project 3705, a date still ahead at the 18 August 2026 reading of 26.32%, while Imtiaz estimates handover for Q2 2027, the quarter that contains it. Either date can be revised as the build moves, so the timetable worth relying on is the one Imtiaz confirms to buyers in writing, read next to the newest register figure on Dubai REST.
Cove Edition 5 is entered in the DLD project register with 198 units, the same 198 residences Imtiaz lists: studio, 1 bedroom and 2 bedroom apartments that the developer markets as fully furnished. All 198 sit in a single residential building, which read 26.32% at the 18 August 2026 inspection.
The 2B+G+11+R configuration of Cove Edition 5 means two basement levels, a ground floor, 11 residential floors and a roof level, the description carried by both the RERA report of 18 August 2026 and Imtiaz's fact sheet. The developer's floor plans place the main lobby on the ground floor and the pool deck, gym and clubhouse on the roof; at that inspection the substructure and superstructure were both recorded as progressing.
Counting from the 20-05-2025 construction start in the register, Cove Edition 5 averaged about 1.74 points per month up to its 26.32% reading of 18 August 2026, which is 26.32 points over 455 days on a 30-day month; that figure is arithmetic, not a forecast. The earlier 16.07% reading carries no date, so a pace between two inspections becomes measurable only with the next dated reading, as the pace analysis above explains.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Edition 5 by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.