Imtiaz · Dubai Land Residence Complex
Cove Edition by Imtiaz Construction Updates
Tracking a Single 2B+G+13+R Tower in Dubailand to Its Q4 2026 Handover
Cove Edition by Imtiaz read 90.22% on the DLD register on 12 October 2026, leaving 9.78 points between its Dubailand tower and the Q4 2026 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Cove Edition by Imtiaz at a Glance
Cove Edition by Imtiaz is a single Imtiaz Developments tower of 182 residences in Dubai Land Residence Complex, built as 2B+G+13+R with its pool, gym and club room planned for the roof rather than a podium. The register records the start of work on 25 August 2024 and registration as project 3248 on 16 September 2024, 22 days apart, and its 90.22% reading of 12 October 2026 came 778 days into the build. One dated reading and one undated earlier figure make this a short record, and the cards below are the register anchors it rests on.
3248
Active
25 August 2024
182 residential units
12,612.43 sq m
25 August 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Cove Edition by Imtiaz Construction Update Timeline
Two figures make up the Cove Edition by Imtiaz record so far, and only one of them carries a date. The 90.22% reading is dated 12 October 2026, the same day as RERA's progress monitoring report for project 3248; the 66.48% before it is listed as the previous inspection with no date, so it appears on the track below as a dot without a month and has no row in the table. The October 2026 row links the full monthly update, which is illustrated with a developer rendering rather than site photography.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| October 2026 | 90.22% | 12 October 2026 | View the October 2026 update |
Reading the dates: the DLD-registered completion date for project 3248 is 25 August 2026, and it was still on the register when the 12 October 2026 reading of 90.22% was posted 48 days later, with the project shown as Active. The handover timing stated for Cove Edition by Imtiaz is Q4 2026. A registered date is not fixed: the regulator can revise it, so rely on the current entry on Dubai REST together with a written handover timetable from Imtiaz.
Pace Analysis
How Fast Cove Edition by Imtiaz Has Been Built
Cove Edition by Imtiaz has a single dated reading, so there is no pair of inspections to measure a phase-by-phase pace from; the earlier 66.48% figure has no date in the register. The recorded dates still support two calculations, both arithmetic, not a forecast:
- 25 Aug 2024 to 12 Oct 2026: whole-build average, construction start to 90.22% over 778 daysAbout 3.48 points per month
- 12 Oct 2026 to 31 Dec 2026: benchmark only, the remaining 9.78 points over the 80 days to the end of the Q4 2026 handover quarterAbout 3.67 points per month
The two rates sit about 0.19 points per month apart, so the benchmark asks for little more than the average this tower has carried since August 2024. What the average cannot show is how the 90.22% was spread across those 778 days, and the work still open is of a different kind: RERA's 12 October 2026 report records the 2B+G+13+R structure as completed and lists internal works, the external envelope, internal finishes, MEP and external works as still in progress, items that usually move a register percentage less per month than concrete floors do. For an end user planning a move after the Q4 2026 handover, or an investor preparing a completion payment of 50% under Option 1 or 15% under Option 2, the next dated reading is the figure that turns these two calculations into a measured pace.
Get the Next Inspection Figure First
Tell me you are tracking Cove Edition by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Cove Edition by Imtiaz at Dubai Land Residence Complex
A register percentage describes a building, so here is the building: the project guide covers what the 90.22% recorded on 12 October 2026 is counting toward.

Cove Edition by Imtiaz: A Tower with Its Club on the Roof
Cove Edition by Imtiaz is one tower of 182 furnished studio, one and two bedroom apartments over 13 floors in Dubailand.
View the Cove Edition by Imtiaz Project GuideConsidering a Late-Stage Entry?
Limited units are available at Cove Edition by Imtiaz, and a buyer entering now settles the instalments already due at signing, per the developer's current terms. If the record on this page is what brought you here, ask me what is still available and how the Q4 2026 timing fits your plans.
Ask About Remaining Availability on WhatsAppStage Record
Cove Edition by Imtiaz Build Stages, Mapped to the Inspections
The five stages below follow the Cove Edition by Imtiaz record itself: two register dates from 2024, an undated 66.48% reading, and RERA's 12 October 2026 report alongside the 90.22% register figure. Where the register gives no date, the window says so instead of estimating one.
Site Start and DLD Registration
Work is recorded as starting on 25 August 2024, and the project entered the Dubai Land Department register as number 3248 on 16 September 2024.
Basements and Concrete Structure
The concrete frame from the two basement levels to the roof of the 2B+G+13+R tower, recorded as completed in RERA's report of 12 October 2026.
Register Reading of 66.48%
The register's previous inspection figure for Cove Edition by Imtiaz; with no date attached, this page gives it no month and no pace.
Envelope, Internal Works and MEP
RERA's 12 October 2026 report lists the external envelope, internal works and MEP as in progress, with the register at 90.22%.
Finishes, External Works and Handover
Internal finishes for the fully furnished apartments and the external works around the tower, with 9.78 points left and handover stated for Q4 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove Edition by Imtiaz's own record.
Buyer Position
Tracking Your Position at Cove Edition by Imtiaz
This page is one of four project resources that together cover a Cove Edition by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove Edition by Imtiaz Construction Updates
This page: the DLD register record for project 3248, from the August 2024 start to handover.

Cove Edition by Imtiaz Golden Visa: A 2B+G+13+R Tower
Cove Edition by Imtiaz, 182 studio, one and two bedroom apartments, has no type that reaches the threshold on its own.
Read the Cove Edition by Imtiaz Golden Visa Guide
Cove Edition by Imtiaz Escrow: Past 90% Certified
Cove Edition by Imtiaz, DLD project 3248, escrows 182 units at First Abu Dhabi Bank, 90.22% certified in October 2026.
Verify the Cove Edition by Imtiaz Escrow Account
Cove Edition by Imtiaz Snagging for Furnished Studios in Dubailand
Cove Edition by Imtiaz is one tower in Dubai Land Residence Complex, 182 studio, one and two bedroom apartments, fully furnished.
Book Cove Edition by Imtiaz SnaggingApproaching Handover
Between 90.22% and Handover: What Cove Edition by Imtiaz Buyers Should Do Now
At Cove Edition by Imtiaz the last 9.78 points sit with the internal works, envelope, internal finishes, MEP and external works that RERA's 12 October 2026 report lists as in progress, so most of what remains happens inside and around the tower rather than in its outline. No handover notice was on record at that reading; when one is issued, the time between notice and appointment is set by your SPA and can be short, which is why the three steps below are worth starting before it arrives.
First, plan an independent inspection of your fully furnished apartment, covering the furniture and appliances, the terrace or balcony and, where the developer's plans show one, the private balcony pool; the Cove Edition snagging guide sets out the checks.
Second, check the completion payment against your plan before it falls due, 50% under Option 1 or 15% under Option 2, and confirm where it goes using the Cove Edition escrow account page, which shows how to verify the account against the DLD record.
Third, if residency is part of your plan, read the Cove Edition Golden Visa guide before handover: at starting prices up to AED 1.20M ≈ USD 327K, a single apartment here sits below the AED 2M ≈ USD 545K property threshold, and the guide explains how that threshold applies to your purchase.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Land Residence Complex Structure
A single tower's register record reads differently once you see what surrounds it. These three pages set Cove Edition by Imtiaz in its Dubai Land Residence Complex market, its community and its developer's wider portfolio:

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand
Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.
See Dubai Land Residence Complex Properties for Sale
Dubai Land Residence Complex: Dubailand's Established Apartment Community
Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.
Explore the Dubai Land Residence Complex Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Cove Edition by Imtiaz Construction Updates Frequently Asked Questions
Cove Edition by Imtiaz is an Active project in the Dubai Land Department register, number 3248, recorded at 90.22% on 12 October 2026. RERA's report of the same date places the 2B+G+13+R tower past its structural stage, with structure works completed and the remaining works in progress under a status of Main Contract, Progressing. The full record is in the Cove Edition inspection timeline above.
The 12 October 2026 reading of 90.22% for Cove Edition by Imtiaz is 23.74 points above the register's previous inspection figure of 66.48%. The register shows no date for the 66.48% reading, so the rise cannot be expressed as a rate per month; the dated reading is covered in full in the Cove Edition by Imtiaz October 2026 construction update.
Handover for Cove Edition by Imtiaz is stated for Q4 2026. The DLD register still carried 25 August 2026 as the registered completion date for project 3248 when the 12 October 2026 reading of 90.22% was posted, 48 days after that date, with the status unchanged at Active. A registered date can be revised by the regulator, so the current Dubai REST entry and a written handover timetable from Imtiaz are the references to rely on, and this page's record is updated when the next reading is posted.
Cove Edition by Imtiaz has 182 residences, the count shown for project 3248 in the DLD register at the 12 October 2026 reading. They are studio, one bedroom and two bedroom apartments on 13 residential floors, sold fully furnished according to Imtiaz's brochure; prices and layouts are in the Cove Edition by Imtiaz project guide.
At Cove Edition by Imtiaz, 2B+G+13+R means two basement levels, a ground floor, 13 residential floors and a roof level, the description RERA's report of 12 October 2026 gives for the building, with a concrete structure and block and internal and external finishes. The developer's rooftop plan places the pool, cabanas, sun beds, gym and club room on the roof, and the same report records the structure works as completed.
Construction at Cove Edition by Imtiaz is recorded as starting on 25 August 2024, and the project was registered with the Dubai Land Department as number 3248 on 16 September 2024. The only dated reading the register shows so far is the 90.22% of 12 October 2026, taken 778 days after the recorded start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove Edition by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.