Imtiaz Developments · Dubai Land Residence Complex
Cove by Imtiaz Construction Updates
The Register Record for a Single Tower in Dubai Land Residence Complex
Cove by Imtiaz recorded 47.21% in the DLD register on 11 August 2026, a climb carrying its single Dubailand tower past foundations into superstructure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Cove by Imtiaz at a Glance
Cove by Imtiaz is Imtiaz Developments' 738-residence apartment tower in Dubai Land Residence Complex, carried in the DLD register with a construction start of 15 April 2024 and a registration date of 07 May 2024. By 11 August 2026 the register read 47.21%, with handover expected in Q1 2027. Every studio, 1 and 2 bedroom apartment and all three amenity levels, the 1st floor podium, the 19th floor club room and the rooftop, sit in that one building, so each reading on this page measures a single structure rather than an average across separate blocks.
2973
Active
15 April 2024
738 residential units
44,508.85 sq m
15 April 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Cove by Imtiaz Construction Update Timeline
The Cove record holds two register figures so far: 47.21%, shown on the inspection report card dated 11 August 2026, and an earlier 29.49% that the DLD app labels the previous inspection without giving its date. Only the dated figure earns a table row and a monthly update; the undated one sits on the track below as a reference point with no month attached. The track ends at 100%, which the register ties to a 15 April 2027 registered completion date, while handover is expected in Q1 2027.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 47.21% | 11 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Cove by Imtiaz Has Been Built
With only one dated reading on file, Cove's pace can be read solely against its own start date, so both figures below are plain arithmetic from the register, not a forecast:
- Apr 2024 to Aug 2026: groundworks and structural phase, construction start to 47.21% over 848 daysAbout 1.67 points per month
- Aug 2026 to the 15 Apr 2027 registered completion date: 47.21% toward 100% over 247 days52.79 points still to record
A whole-build average flattens the shape that matters, and the shape is exactly where Cove's record is still thin. The app's earlier 29.49% confirms progress was already on the register before August, but with no date attached that climb cannot be turned into a monthly rate, so this page does not invent one. What the 11 August 2026 report does show is overlap: substructure works were far along but not closed out while superstructure, MEP and internal finishes ran at the same time, which places the single tower in parallel trades rather than sequential groundworks. For an end user counting toward Q1 2027 and an investor reading delivery pace, the next dated reading is the one that turns this record into a measured curve, because two dated points give a true rate to set against the 52.79 points remaining after August.
Get the Next Inspection Figure First
Tell me you are tracking Cove by Imtiaz and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Cove by Imtiaz at Dubai Land Residence Complex
A register percentage means more once you know what it is counting toward. The project guide sets out the tower these readings measure:

Cove by Imtiaz: A Vertical Community of 738 Apartments
Cove by Imtiaz stacks its leisure across the podium, the 19th floor and the rooftop of one tower of 738 apartments.
View the Cove by Imtiaz Project GuideConsidering a Mid-Stage Entry?
Imtiaz still lists limited units at Cove while the tower rises, and that list changes between register readings. If the record on this page is what brought you here, ask me for current availability before the next reading moves the picture again.
Ask About Remaining Availability on WhatsAppStage Record
Cove by Imtiaz Build Stages, Mapped to the Inspections
Each stage below is pinned to the register dates and the 11 August 2026 RERA notes for this one tower, so the record shows where Cove stood at each point instead of a textbook sequence.
Construction Start and DLD Registration
The register dates construction from 15 April 2024 and the project's DLD registration, under number 2973, to 07 May 2024.
Enabling Works and Foundations
The RERA report of 11 August 2026 lists enabling and foundation works on the Dubai Land Residence Complex plot as completed.
Substructure and Superstructure
The register read 47.21% on 11 August 2026, with substructure works far along and the superstructure rising, according to that day's RERA notes.
MEP, Internal Works, and Finishes
MEP, internal works and internal finishes were already running beside the structure in August 2026; ahead lie the podium, 19th floor club room and rooftop amenity levels.
Completion and Handover
52.79 points remained after the 11 August 2026 reading; handover is expected in Q1 2027, with 15 April 2027 the registered completion date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Cove by Imtiaz's own record.
Buyer Position
Tracking Your Position at Cove by Imtiaz
This page is one of four project resources that together cover a Cove by Imtiaz purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Cove by Imtiaz Construction Updates
This page: Cove's register record from the 15 April 2024 start, reading by reading, to handover.

Cove by Imtiaz Golden Visa: Each Apartment Stands Against the Line
At Cove by Imtiaz, 738 residences under DLD project 2973, the studio, 1 and 2 bedroom all start below the threshold.
Read the Cove by Imtiaz Golden Visa Guide
Cove by Imtiaz: The 744-Unit Escrow Account
Cove by Imtiaz holds 744 units in First Abu Dhabi Bank escrow, DLD project 2973, 47.21% certified in August 2026.
Verify the Cove by Imtiaz Escrow AccountApproaching Handover
Between 47.21% and Handover: What Cove by Imtiaz Buyers Should Do Now
At the 47.21% recorded on 11 August 2026, the work between now and handover is still largely physical: the structure has to finish rising before the podium, 19th floor and rooftop levels can be fitted out. Cove's payment plan runs on fixed dates rather than on that progress, and its six dated instalments, 60% of the price, had all fallen due by 15 July 2026, so the completion share is the next payment for existing buyers. That makes the months before the completion notice the time to settle three things, not the days after it arrives.
First, confirm that every remaining payment goes to the trust account for project 2973; the Cove by Imtiaz escrow account page explains how to match the First Abu Dhabi Bank account against the DLD record.
Second, if residency is part of your plan, read the Cove by Imtiaz Golden Visa guide early, because the AED 2M ≈ USD 545K threshold sits above every current Cove apartment price, so a single unit does not reach it on its own.
Third, keep the unit you are paying toward in view through the Cove by Imtiaz project guide, which carries the layouts, both payment plan options and the Q1 2027 expected handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Land Residence Complex Structure
One tower's record reads differently once you see what surrounds it. These three pages place Cove's construction progress in its market, community, and developer context:

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand
Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.
See Dubai Land Residence Complex Properties for Sale
Dubai Land Residence Complex: Dubailand's Established Apartment Community
Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.
Explore the Dubai Land Residence Complex Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Cove by Imtiaz Construction Updates Frequently Asked Questions
Cove by Imtiaz is an active DLD-registered project (number 2973) in its substructure and superstructure stage, with a DLD register reading of 47.21% as of 11 August 2026. The RERA report of that date records enabling and foundation works as completed and the main contract as progressing; the full record is in the inspection timeline above.
The latest Cove by Imtiaz reading is 47.21%, shown on the inspection report card dated 11 August 2026, which sits 17.72 points above the previous register figure of 29.49%. The DLD app gives no date for that earlier figure, so the gap is a difference between two readings rather than a monthly pace. The site notes behind the August figure are in the Cove by Imtiaz August 2026 construction update.
Handover at Cove by Imtiaz is expected in Q1 2027, while the DLD register lists 15 April 2027 as the registered completion date, about two weeks after that quarter ends. The registered date has not lapsed; as of the 11 August 2026 reading, 52.79 points of construction remained before 100%, and this page records any revision to either date once the register shows it.
Cove by Imtiaz has 738 residential units, made up of studio, 1 bedroom and 2 bedroom apartments in a single tower above ground-floor retail. Layouts, sizes and the amenity levels shared by those 738 homes are set out in the Cove by Imtiaz project overview.
Measured from the 15 April 2024 construction start, the 47.21% register reading of 11 August 2026 works out at about 1.67 points per month across 848 days, as arithmetic rather than a forecast. A measured rate between inspections needs two dated readings, and the earlier 29.49% carries no date, so the pace analysis adds one once the next dated reading posts.
Each Cove by Imtiaz percentage on this page is a reading from the Dubai Land Department project register for project 2973, listed there as Cove Living Residence By Imtiaz, paired with the date shown on its inspection report card. The RERA inspection report adds site notes but prints no percentage of its own, so the 11 August 2026 notes describe stages of work rather than figures, and every reading is checked against Dubai REST before it appears here.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Cove by Imtiaz construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.