Creek Vista Heights Construction Updates
Two Towers, One Podium, One Dated Register Record in Sobha Hartland
Creek Vista Heights read 91.53% on the DLD register on 8 September 2026: structure works complete on both Sobha Hartland towers, 8.47 points left to 100%.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Creek Vista Heights at a Glance
Creek Vista Heights is Sobha Realty's two-tower development on a shared podium in Sobha Hartland, holding 1,342 residences from 1 to 3.5 bedrooms. Its register record runs from a 14 March 2023 construction start to 91.53% on 8 September 2026, and the two towers differ in floor count: per the RERA progress report, Tower A has a basement, ground, six podium floors and 52 floors above, while Tower B has the same base with 58. A single register percentage covers both towers, so every figure below describes the pair together rather than either tower on its own.
2717
Active
14 March 2023
1,342 residential units
119,163.91 sq m
Q2 2026 (developer handover passed)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Creek Vista Heights Construction Update Timeline
So far the Creek Vista Heights record holds one dated register reading, 91.53% on 8 September 2026, framed by two dated milestones: the construction start on 14 March 2023 and DLD registration on 19 July 2023. The register also shows a previous reading of 82.33% with no date attached, so it sits on the track below as a dot without a month and has no row of its own in the table.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 91.53% | 8 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Creek Vista Heights Has Been Built
One dated reading cannot draw a curve, so the Creek Vista Heights pace below is whole-build arithmetic from the 14 March 2023 start rather than a rate measured between two inspections:
- 14 Mar 2023 to 8 Sep 2026: whole build, start to 91.53% over 1,274 daysAbout 2.16 points per 30-day month
- 8 Sep 2026 onward: envelope, MEP, internal finishes and external works8.47 points remaining
That 2.16 is an average across two very different kinds of work. By the 8 September 2026 RERA report, enabling works, piling, foundations and structure were listed complete for both towers and the shared podium, while the envelope, MEP, internal finishes and external works were still progressing, so the figure blends a finished frame with fit-out that is still under way. It cannot be sharpened with the register's earlier 82.33% reading, which has no date, and it cannot be set against a required pace either: the register shows no completion date and the original Q2 2026 schedule has passed, so there is no target to divide the remaining 8.47 points by. It is arithmetic, not a forecast. For an end user, the useful reading is that the heaviest structural phase is behind the towers and the open question is the handover date, which Sobha Realty confirms; for an investor, the next dated register reading, not this average, is what will show how the last 8.47 points are moving.
Get the Next Inspection Figure First
Tell me you are tracking Creek Vista Heights and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Creek Vista Heights at Sobha Hartland
A register percentage reads better next to what it is measuring. The project guide covers the two towers this record follows:

Creek Vista Heights: Twin Towers With 1 to 3.5 Bedroom Apartments
Creek Vista Heights by Sobha Realty features 1,342 apartments across two residential towers with a shared podium in Sobha Hartland.
View the Creek Vista Heights Project GuideConsidering an Entry Above 90%?
Limited units available at Creek Vista Heights. With the register at 91.53% on 8 September 2026, a buyer entering now may find most or all of the construction instalments already called, so the amount due at signing can be well above 20%. Ask me what is available and what your unit would need at booking, then confirm both with Sobha Realty and in the SPA.
Ask About Remaining Availability on WhatsAppStage Record
Creek Vista Heights Build Stages, Mapped to the Inspections
The Creek Vista Heights record holds two dated milestones and one dated reading, so each stage below is anchored to those dates and to what the 8 September 2026 RERA report lists as complete or progressing, never to dates the record does not contain.
Construction Start, Enabling Works and Piling
Works began on 14 March 2023. Enabling works and piling appear as complete in the 8 September 2026 RERA report, which does not say when either one finished.
DLD Registration as Project 2717
The development entered the DLD register on 19 July 2023 as Sobha Creek Vista Heights, the registration every percentage on this page is read from.
Foundations and Two-Tower Structure
Foundation and structure works for Tower A, Tower B and the shared podium are listed complete in the 8 September 2026 RERA report, with no finishing date given for them.
Envelope, MEP and Internal Works
The external envelope, MEP and internal works were progressing at the 8 September 2026 inspection; the 82.33% previous register reading carries no date, so it cannot be placed in this window.
Internal Finishes, External Works and Handover
Internal finishes and external works were progressing at 91.53% on 8 September 2026, 8.47 points short of 100%; handover follows Sobha Realty's notice, and with the original Q2 2026 schedule passed, its date is one to confirm with Sobha Realty.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Creek Vista Heights's own record.
Buyer Position
Tracking Your Position at Creek Vista Heights
This page is one of four project resources that together cover a Creek Vista Heights purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Creek Vista Heights Construction Updates
This page: every dated DLD register reading for Creek Vista Heights since the March 2023 start.

Creek Vista Heights Golden Visa: 2.5, 3 and 3.5 Bedroom Apartments Qualify
Creek Vista Heights by Sobha Realty in Sobha Hartland qualifies through 2.5, 3 and 3.5 bedroom apartment starting prices.
Read the Creek Vista Heights Golden Visa Guide
Creek Vista Heights Escrow Account With Dubai Islamic Bank
Creek Vista Heights, DLD project 2717, holds 1,342 residences under Dubai Islamic Bank escrow; the register read 91.53% in September 2026.
Verify the Creek Vista Heights Escrow Account
Creek Vista Heights Snagging: Full-Height Windows, Balconies and AC Systems
Creek Vista Heights snagging covers Sobha Realty's apartments in Sobha Hartland, checking full-height windows, balcony drainage, air conditioning and interior finishes.
Book Creek Vista Heights SnaggingApproaching Handover
Between 91.53% and Handover: What Creek Vista Heights Buyers Should Do Now
At the 8 September 2026 reading, 8.47 points separated Creek Vista Heights from 100%, and the work still listed as progressing (envelope, MEP, internal finishes and external works across two towers and their podium) is the kind a buyer cannot judge from the street. The original Q2 2026 handover schedule has passed, so the current expected date has to come from Sobha Realty in writing and be checked against your SPA. Once the handover notice is issued, it sets the time you have for an inspection and for the payment due on handover, which is why the three steps below are worth settling before it arrives.
First, line up an independent inspection now so it can run as soon as the notice lands; the window has not opened on record yet, and the Creek Vista Heights snagging inspection page explains what gets checked inside the apartment.
Second, make sure any payment still due under your SPA goes to the Dubai Islamic Bank account set out on the Creek Vista Heights escrow account page, so money paid above 91.53% still follows the register record.
Third, if your unit is a 2.5 bedroom or larger type, settle residency eligibility before handover with the Creek Vista Heights Golden Visa guide, since the title deed and the SPA price drive the application.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Hartland Structure
The two Creek Vista Heights towers are one part of a larger Sobha Realty community. These three pages set the September 2026 reading against the listings, the neighbourhood and the developer around it:

Sobha Hartland Properties for Sale
Apartments, duplexes, Quad Homes townhouses and 4 to 6 bedroom villas currently available across the community's eleven sub-communities.
See Sobha Hartland Properties for Sale
Sobha Hartland Community in MBR City by Sobha Realty
Explore Sobha Hartland's waterfront residences, landscaped parks, schools and residential clusters in MBR City, with community insights and amenities.
Explore the Sobha Hartland Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Creek Vista Heights Construction Updates Frequently Asked Questions
Creek Vista Heights is an active DLD-registered project (number 2717) that read 91.53% on the DLD register on 8 September 2026. The RERA progress report of the same date lists enabling works, piling, foundations and structure as complete, with the envelope, MEP, internal finishes and external works progressing. The full record is in the inspection timeline above.
The DLD register put Creek Vista Heights at 91.53% on 8 September 2026, up 9.20 points from a previous reading of 82.33% that the register shows without a date. Because the earlier reading is undated, that gap cannot be turned into a monthly rate. The full report for the September reading is in the Creek Vista Heights September 2026 construction update.
Sobha Realty's original handover schedule for Creek Vista Heights was Q2 2026, and that quarter has passed; at the 8 September 2026 reading of 91.53% the build was still progressing. The register details for project 2717 show no completion date, so the current expected handover date has to be confirmed in writing with Sobha Realty and checked against the handover clause of the SPA before committing, and this page's record is updated when a newer reading is recorded.
The record covers 1,342 residences in two towers on a shared podium, registered with the DLD as project 2717. Per the RERA progress report of 8 September 2026, Tower A has a basement, ground, six podium floors and 52 floors above, and Tower B the same base with 58 floors, so one register percentage, 91.53% on that date, describes both towers together.
Across the whole build, Creek Vista Heights averaged about 2.16 points per 30-day month: 91.53 points over the 1,274 days from the 14 March 2023 start to the 8 September 2026 reading. That is arithmetic, not a forecast, and no required pace is given because the register shows no completion date; the working is in the pace analysis above.
Construction at Creek Vista Heights started on 14 March 2023, and the project was registered with the DLD on 19 July 2023 as Sobha Creek Vista Heights, project 2717. The first dated reading on this record is 91.53% on 8 September 2026; the register's previous reading of 82.33% has no date attached.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Creek Vista Heights construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.