Creek Waters at Dubai Creek Harbour Construction Updates

One Creek Island Tower, Tracked Reading by Reading to Handover

Creek Waters recorded 81.08% on the DLD register on 3 August 2026, leaving 18.92 points between its 50-floor Creek Island tower and the expected Q3 2027 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

81.08%Construction Progress
3 August 2026Latest RERA Inspection
450 residential unitsTotal Units
Project 2614DLD Registration

Construction Snapshot

Creek Waters at Dubai Creek Harbour at a Glance

Creek Waters is Emaar's 450-residence tower on the north-eastern edge of Creek Island in Dubai Creek Harbour, entered in the Dubai Land Department register as project 2614 on 31 March 2023, with THE LAGOONS PHASE ONE L.L.C (developer 1038) as registered developer on plot 142, Al Khairan First. Construction started on 15 August 2023, and 1,084 days later the register put the build at 81.08% on 3 August 2026. Where many Dubai Creek Harbour phases spread across several blocks, the RERA inspection report describes one 2B+G+P+50 residential building, so every figure below follows a single 50-floor tower rising over two basements, a ground floor and a podium.

DLD Project Number

2614

Project Status

Active

Construction Start

15 August 2023

Total Units

450 residential units

Total Built-Up Area

51,118.01 sq m

Registered Completion Date

30 September 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Creek Waters at Dubai Creek Harbour Construction Update Timeline

The Creek Waters record holds one dated reading so far: 81.08% on 3 August 2026, filed on the day of a RERA inspection report that prints no percentage of its own. The register sets that figure against a previous inspection of 72.18% that carries no date, so the track below marks the earlier point without a month, and only the August 2026 reading has its own table row and full monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202681.08%3 August 2026View the August 2026 update

Pace Analysis

How Fast Creek Waters at Dubai Creek Harbour Has Been Built

With one dated reading and one undated one, the Creek Waters record supports a movement figure and two pieces of labelled arithmetic rather than a measured pace between inspections:

  • Undated previous inspection to 3 Aug 2026: 72.18% to 81.08%Up 8.90 points, no monthly rate
  • 15 Aug 2023 start to 3 Aug 2026: whole-build average, 81.08 points over 1,084 daysAbout 2.24 points per 30 days
  • 3 Aug 2026 to the 30 Sep 2027 registered completion: 18.92 points in 423 daysAbout 1.34 points per 30 days

Two cautions shape how this record reads. The 8.90-point rise to 3 August 2026 cannot become a monthly velocity, because the register gives no date for the 72.18% inspection, and dividing by a guessed interval would invent a pace the record does not hold. The two rates above come straight from the registered dates: arithmetic, not a forecast, and no verdict on delivery timing. What the August 2026 inspection notes add is the work mix behind the number, with enabling, foundation and sub-structure works at very advanced stages while superstructure, internal and MEP works were still progressing on the 50-floor tower. For an investor, the next dated reading is the one that turns this record into a measurable curve; for an end user, the anchor remains the expected Q3 2027 handover, which the 30 September 2027 registered completion date matches.

Get the Next Inspection Figure First

Tell me you are tracking Creek Waters at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Creek Waters at Dubai Creek Harbour

An 81.08% reading on 3 August 2026 only means something next to what the tower will hold at handover. The full project guide covers what Creek Waters buyers are tracking toward on this page:

Creek Waters by Emaar in Dubai Creek Harbour rendering of illuminated waterfront residential towers beside a curved bridge at dusk in Dubai - Presented by Tohid Fetrat

Creek Waters at Dubai Creek Harbour: 450 Homes on Creek Island

Creek Waters at Dubai Creek Harbour is an Emaar tower of apartments, base townhouses and a duplex penthouse above a podium.

View the Creek Waters at Dubai Creek Harbour Project Guide

Considering a Late-Stage Entry?

Limited units remain available at Creek Waters, and the choice narrows as the tower moves toward its Q3 2027 handover. If the record on this page is what brought you here, ask me what is still on offer before the next register reading.

Ask About Remaining Availability on WhatsApp

Stage Record

Creek Waters at Dubai Creek Harbour Build Stages, Mapped to the Inspections

Each stage below is pinned to the register dates for project 2614 and to the RERA notes of 3 August 2026, so the sequence shows where Creek Waters actually sits rather than a textbook order of works.

Mar 2023 to Aug 2023

Registration and Site Activation

Project 2614 entered the DLD register on 31 March 2023 and construction formally started on 15 August 2023 on plot 142; the August 2026 report still lists mobilization as ongoing.

From Aug 2023, very advanced by Aug 2026

Enabling, Foundations and Two Basements

The 3 August 2026 inspection rated enabling, foundation and sub-structure works, the two basement levels included, as progressing at very advanced stages.

To the undated 72.18% reading

Podium and 50-Floor Superstructure

By the undated previous inspection the register stood at 72.18%; superstructure works on the 50-floor tower were still listed as progressing on 3 August 2026.

Current Phase3 Aug 2026 at 81.08%

Internal Works, MEP and Upper Envelope

At 81.08% on 3 August 2026, internal and MEP works were progressing at different stages, and the inspection photographs show upper-floor glazing and crown framing being installed.

Aug 2026 to Q3 2027

Finishing, Commissioning and Handover

The 18.92 points left after the 3 August 2026 reading cover finishes, building systems and external works toward the expected Q3 2027 handover; registered completion is 30 September 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Creek Waters at Dubai Creek Harbour's own record.

Buyer Position

Tracking Your Position at Creek Waters at Dubai Creek Harbour

This page is one of four project resources that together cover a Creek Waters at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Creek Waters by Emaar in Dubai Creek Harbour construction updates cover image featuring a project rendering of two waterfront residential towers under a blue sky in Dubai - Presented by Tohid Fetrat
You Are Here

Creek Waters at Dubai Creek Harbour Construction Updates

This page: the Creek Waters register record for project 2614, from its 2023 start toward handover.

Creek Waters by Emaar in Dubai Creek Harbour Golden Visa information graphic with a gold card above a landscaped waterfront swimming pool in Dubai - Presented by Tohid Fetrat

Creek Waters at Dubai Creek Harbour Golden Visa From 2 Bedrooms Upwards

Emaar's Creek Waters at Dubai Creek Harbour, 450 residences on Creek Island, qualifies individually at five of six types.

Read the Creek Waters at Dubai Creek Harbour Golden Visa Guide
Creek Waters by Emaar in Dubai Creek Harbour escrow account concept graphic with shield and padlock icons above a waterfront balcony and skyline in Dubai - Presented by Tohid Fetrat

Creek Waters at Dubai Creek Harbour: The First Creek Waters Escrow

Creek Waters at Dubai Creek Harbour, DLD project 2614: 453 units, First Abu Dhabi Bank escrow, 81.08% certified August 2026.

Verify the Creek Waters at Dubai Creek Harbour Escrow Account
Creek Waters by Emaar in Dubai Creek Harbour snagging inspection cover featuring a rendered dining area with pink chairs, a round table and large windows in Dubai - Presented by Tohid Fetrat

Creek Waters at Dubai Creek Harbour Snagging on the Creek Island Waterfront

Creek Waters at Dubai Creek Harbour is an Emaar tower of 450 residences in three forms: apartments, townhouses and a penthouse.

Book Creek Waters at Dubai Creek Harbour Snagging

Approaching Handover

Between 81.08% and Handover: What Creek Waters at Dubai Creek Harbour Buyers Should Do Now

After the 3 August 2026 reading, 18.92 points of Creek Waters work remain, most of it inside the tower: internal works, MEP and the last of the upper-floor envelope rather than new foundations. With handover expected in Q3 2027 and registered completion set for 30 September 2027, Emaar's handover notice is the point from which deadlines run, and the appointment follows it within whatever period your SPA sets, so the three steps below are easier to settle before that notice than after it.

First, choose an independent inspector ahead of the notice so your residence is checked before you accept it; the Creek Waters snagging inspection guide explains what is checked in the apartments, the podium townhouses and the duplex penthouse.

Second, confirm that each remaining installment goes into the First Abu Dhabi Bank escrow account for project 2614 and matches your SPA schedule; the Creek Waters escrow account page shows how to verify it against the DLD record.

Third, if your purchase may qualify for residency, settle eligibility before handover through the Creek Waters Golden Visa eligibility guide, since the title deed timing shapes the application route.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Creek Harbour Structure

A single tower's record is only half the picture; the other half is the district rising around it. These three pages set the Creek Waters build in its market, community and developer context:

Dubai Creek Harbour Properties for Sale waterfront community view with Creek waters modern residential towers and Downtown Dubai skyline Presented by Tohid Fetrat

Dubai Creek Harbour Properties for Sale

Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.

See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour skyline with The Grand by Emaar and Dubai Creek Tower – luxury waterfront community with marina and skyline views, presented by Tohid Fetrat.

Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach

Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.

Explore the Dubai Creek Harbour Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Creek Waters at Dubai Creek Harbour Construction Updates Frequently Asked Questions

Creek Waters is an active DLD-registered project (number 2614) in its late construction stage, recorded at 81.08% on the Dubai Land Department register on 3 August 2026. The RERA inspection report of the same date gives its progress status as Main Contract - Progressing, and the full record is in the Creek Waters inspection timeline above.

Because the register dates only the latest Creek Waters inspection: 81.08% on 3 August 2026, up 8.90 points on a previous inspection of 72.18% that the Dubai Land Department lists without a date. The rise is shown as a movement only, since no monthly rate can be drawn from a pair with one undated end. The August reading is set out in the Creek Waters August 2026 construction update.

For Creek Waters it means the main construction contract was still under way when RERA inspected project 2614 on 3 August 2026, the same day the register recorded 81.08%. It is a progress status rather than a finishing status: the report records nothing as finished and prints no percentage of its own, which is why every figure on this page is attributed to the DLD register.

The 3 August 2026 RERA report for Creek Waters places enabling, foundation and sub-structure works at very advanced stages, while superstructure, internal and MEP works were progressing at different stages and mobilization was still ongoing. Its photographs show upper-floor glazing and crown framing going in with some floors still open, alongside the 81.08% register reading of that date. How these works map onto the record is shown in the Creek Waters stage record above.

The two agree: Creek Waters handover is expected in Q3 2027, and the DLD register lists 30 September 2027, the last day of that quarter, as the registered completion date for project 2614. That date falls 423 days after the 81.08% reading of 3 August 2026; registered dates can be revised between inspection cycles, and this page's record is updated as each new inspection is recorded.

Creek Waters comprises 450 residential units in the single 2B+G+P+50 building described by the 3 August 2026 RERA report: two basements, a ground floor, a podium and 50 floors. The mix runs from one to four bedroom apartments to three-bedroom podium townhouses and a five-bedroom duplex penthouse on the 49th and 50th floors, with layouts in the Creek Waters project guide.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Creek Waters at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.