Dubai Creek Residences at Dubai Creek Harbour Construction Updates

The Closed Record of a Six-Tower Build Beside the Creek Marina

Dubai Creek Residences reached 100% in the DLD register on 06 March 2019, completing six towers on two podiums beside the Dubai Creek Harbour marina.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
06 March 2019Latest RERA Inspection
924 unitsTotal Units
Project 1597DLD Registration

Construction Snapshot

Dubai Creek Residences at Dubai Creek Harbour at a Glance

Dubai Creek Residences is Emaar's 924-unit waterfront development in the Island District of Dubai Creek Harbour, registered with the DLD as project 1597 on 26 October 2014. Its record runs from the 01 January 2015 construction start to the 100% reading of 06 March 2019, a little over four years and two months, and the register now lists it as Finished, with the handover status at Ready. That makes this a closed record: the six towers have stood complete since early 2019, so the figures below date a finished building rather than one still rising.

DLD Project Number

1597

Project Status

Finished

Construction Start

01 January 2015

Total Units

924 units

Total Built-Up Area

140,748.06 sq m

Registered Completion Date

15 January 2019 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Dubai Creek Residences at Dubai Creek Harbour Construction Update Timeline

One dated reading carries this record: 100% on 06 March 2019, entered in the DLD register 3.82 points above a 96.18% inspection for which no date is recorded. That 96.18% reading is the unlabelled dot just short of the finish on the track below, and the single table row links the March 2019 update, the only monthly page in the Dubai Creek Residences series. Counted to 02 October 2026, 2,767 days have passed since that final inspection.

Inspection MonthConstruction ProgressInspection DateFull Update
March 2019100%06 March 2019View the March 2019 update
!

Reading the dates: the DLD register gives project 1597 a registered completion date of 15 January 2019. Set beside it, the RERA inspection report of 06 March 2019 records Dubai Civil Defence completion (DCDs) received on 11 November 2018 and Building Completion Certificates (BCCs) issued by Dubai Development Authority on 13 February 2019, 29 days after the registered date, while the 100% register reading is dated 06 March 2019, 50 days after it. The register now lists the project as Finished.

Pace Analysis

How Fast Dubai Creek Residences at Dubai Creek Harbour Has Been Built

With a single dated reading there is no inspection pair to measure, so the figures below are the date arithmetic that the register and the March 2019 report allow, each labelled for what it is:

  • Jan 2015 to Mar 2019: whole build, registered start to 100% over 1,525 days (arithmetic, not a forecast)About 2.0 points per month
  • Undated previous inspection to 06 Mar 2019: closing step, 96.18% to 100%+3.82 points, no monthly rate
  • 11 Nov 2018 to 13 Feb 2019: DCDs received to BCCs issued94 days
  • 13 Feb 2019 to 06 Mar 2019: BCCs issued to the 100% reading21 days

The shape of this curve cannot be drawn from the register, because the only movement it dates is the last one. What can be read is the order of the closing events: Civil Defence sign-off in November 2018, Building Completion Certificates in February 2019, then the 100% reading three weeks later, with the inspection report noting finishing and cleaning works still under way and DEWA meters already connected. Averaged over the whole build, 100 points across about 51 months works out at about 2.0 points per month, a figure that describes the past and predicts nothing. For an investor, that is a six-tower delivery closed a little over four years after the registered start; for an end user arriving now, the build pace matters less than how a specific apartment or penthouse has held up in the seven years since.

Get the Next Inspection Figure First

Tell me you are tracking Dubai Creek Residences at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Dubai Creek Residences at Dubai Creek Harbour

A 100% reading only matters next to what it completed. The full project guide covers the homes this record describes:

Dubai Creek Residences at Dubai Creek Harbour by Emaar Properties aerial waterfront view showcasing residential towers, marina, and Dubai skyline in Dubai Presented by Tohid Fetrat

Dubai Creek Residences at Dubai Creek Harbour: Six Towers on the Promenade

Dubai Creek Residences at Dubai Creek Harbour spreads 924 Emaar apartments and penthouses over six towers of up to 40 storeys.

View the Dubai Creek Residences at Dubai Creek Harbour Project Guide

Considering a Ready Unit Here?

Units at Dubai Creek Residences now change hands as finished homes, and what is on offer shifts as owners list and sell. If this completion record is what brought you here, ask me what is available before you compare towers.

Ask About Remaining Availability on WhatsApp

Stage Record

Dubai Creek Residences at Dubai Creek Harbour Build Stages, Mapped to the Inspections

Only one inspection in this record carries a date, so the stages below are anchored to the register dates and to the completion events listed in the March 2019 report, showing when Dubai Creek Residences passed each one rather than how a generic tower is built.

Oct 2014 to Jan 2015

Registration and Construction Start

Project 1597 was registered with the DLD on 26 October 2014, and the register dates the construction start to 01 January 2015, 67 days later.

From Jan 2015, no dated reading

Two Podiums and Six Towers

Two plots, each with a shared podium of two basements, ground and two podium levels, carrying three towers of 30, 35 and 40 floors plus roof levels.

By 11 Nov 2018

Civil Defence Completion

The March 2019 report records Dubai Civil Defence completion (DCDs) as received on 11 November 2018, 65 days before the registered completion date.

By 13 Feb 2019

Building Completion Certificates

Dubai Development Authority issued the Building Completion Certificates (BCCs) on 13 February 2019, 29 days after the registered completion date of 15 January 2019.

Current Phase06 Mar 2019 onward, 100% at last reading

Completion, Finishing and Handover

Recorded at 100% on 06 March 2019, up 3.82 points from an undated 96.18%, with DEWA meters connected and finishing and cleaning works closing out; the register now reads Finished and handover status is Ready.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Dubai Creek Residences at Dubai Creek Harbour's own record.

Buyer Position

Tracking Your Position at Dubai Creek Residences at Dubai Creek Harbour

This page is one of four project resources that together cover a Dubai Creek Residences at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Dubai Creek Residences by Emaar Properties in Dubai Creek Harbour construction updates cover image featuring a project rendering of waterfront residential towers and a pedestrian promenade in Dubai - Presented by Tohid Fetrat
You Are Here

Dubai Creek Residences at Dubai Creek Harbour Construction Updates

This page: the Dubai Creek Residences build record, from the 2015 start to 100% in 2019.

Dubai Creek Residences by Emaar Properties in Dubai Creek Harbour Golden Visa concept with a Golden Visa card above marina waterfront towers and yachts in Dubai - Presented by Tohid Fetrat

Dubai Creek Residences at Dubai Creek Harbour Golden Visa: Six Towers

Dubai Creek Residences at Dubai Creek Harbour, Emaar's six towers above two podiums, clears the line at every listed tier.

Read the Dubai Creek Residences at Dubai Creek Harbour Golden Visa Guide
Dubai Creek Residences by Emaar Properties in Dubai Creek Harbour escrow account protection concept with shield and padlock icons above marina waterfront towers and yachts in Dubai - Presented by Tohid Fetrat

Dubai Creek Residences at Dubai Creek Harbour: Escrow Certified 100% in 2019

Dubai Creek Residences at Dubai Creek Harbour, DLD project 1597, read 100% certified March 2019 with Dubai Islamic Bank escrow.

Verify the Dubai Creek Residences at Dubai Creek Harbour Escrow Account
Dubai Creek Residences by Emaar Properties in Dubai Creek Harbour snagging inspection concept featuring a furnished bedroom interior with floor to ceiling window and snagging inspection graphic in Dubai - Presented by Tohid Fetrat

Dubai Creek Residences at Dubai Creek Harbour Snagging Before Transfer

Dubai Creek Residences at Dubai Creek Harbour is six Emaar towers rising to 40 storeys on the promenade, with 924 units.

Book Dubai Creek Residences at Dubai Creek Harbour Snagging

Approaching Handover

Between 100% and Handover: What Dubai Creek Residences at Dubai Creek Harbour Buyers Should Do Now

Construction at Dubai Creek Residences ended with the 06 March 2019 reading, so the work left for a buyer is no longer about progress but about the unit, the paperwork and the payment route. A ready purchase typically moves from agreed offer to DLD transfer in weeks rather than years, so the three steps below belong before you sign, not after the transfer date is set.

First, have the apartment or penthouse inspected independently, since seven years of occupancy or vacancy leave their own marks; the Dubai Creek Residences snagging inspection guide sets out what gets checked in a building completed in 2019.

Second, establish who receives your money before any transfer: the Dubai Creek Residences escrow account page separates a purchase of remaining developer stock from a resale between owners, which follow different payment routes.

Third, if residency is part of the plan, check your unit's registered price against the threshold before committing, using the Dubai Creek Residences Golden Visa guide, since on a ready purchase the application usually follows the title deed issued at transfer.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Creek Harbour Structure

A finished six-tower record reads differently once you see what has risen around it since 2019. These three pages set Dubai Creek Residences in its market, master community and developer context:

Dubai Creek Harbour Properties for Sale waterfront community view with Creek waters modern residential towers and Downtown Dubai skyline Presented by Tohid Fetrat

Dubai Creek Harbour Properties for Sale

Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.

See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour skyline with The Grand by Emaar and Dubai Creek Tower – luxury waterfront community with marina and skyline views, presented by Tohid Fetrat.

Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach

Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.

Explore the Dubai Creek Harbour Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Dubai Creek Residences at Dubai Creek Harbour Construction Updates Frequently Asked Questions

The DLD register lists Dubai Creek Residences, project 1597 under the name "The Dubai Creek Residences", as Finished, with its latest inspection dated 06 March 2019 at 100%. The RERA inspection report for that visit records the progress status as Completed, and the handover status of the project is Ready. The dated record is laid out in the completion timeline above.

Two readings appear in the record supplied for this page: the 100% reading of 06 March 2019 and, before it, a 96.18% inspection carried with no date, so the final step measured 3.82 points. No other inspection appears in that record, which is why the track above labels one dot and the table holds a single row.

According to the RERA inspection report of 06 March 2019, Dubai Development Authority issued the Building Completion Certificates (BCCs) for Dubai Creek Residences on 13 February 2019, and Dubai Civil Defence completion (DCDs) had been received on 11 November 2018, 94 days earlier.

The DLD registered completion date for Dubai Creek Residences is 15 January 2019. The Building Completion Certificates are dated 13 February 2019, 29 days after it, and the 100% register reading is dated 06 March 2019, 50 days after it; the project is now listed as Finished. Both dates sit side by side in the reading the dates note under the timeline.

Dubai Creek Residences comprises 924 units registered as a single DLD project, number 1597. The RERA inspection report describes two plots, each with a shared podium of two basements, ground and two podium levels carrying three towers of 30, 35 and 40 floors plus roof levels, six towers in all.

From the registered construction start on 01 January 2015 to the 100% reading on 06 March 2019, Dubai Creek Residences took 1,525 days, about 51 months. Spread evenly, that is about 2.0 points per month, an arithmetic average of the whole build rather than a measured pace or a forecast; the project had been registered with the DLD on 26 October 2014, 67 days before the start. The working is shown in the pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Dubai Creek Residences at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status