DAMAC Properties · Downtown Dubai
Elegance Tower Construction Updates
From Plot 469 to a Certified Zuhair Murad Tower in Downtown Dubai
Elegance Tower reached 100% at its 16 September 2026 RERA inspection, closing a 25-floor Downtown Dubai build begun in January 2023 and opening the handover stage.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Elegance Tower at a Glance
Elegance Tower is DAMAC's 296-apartment tower on plot 469 in Downtown Dubai, branded by Zuhair Murad and registered with the DLD on 10 November 2022. Forty-four months separate its 16 January 2023 construction start from the 100% and Completed status recorded at the 16 September 2026 inspection. What sets this record apart is how late it becomes visible: both dated readings fall in 2026, so the history here is read from its closing stretch and from the two approvals issued in July 2026 rather than from a long run of site visits.
2475
Finished
16 January 2023
296 apartments
26,281.01 sq m
28 February 2026
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Elegance Tower Construction Update Timeline
Two dated RERA inspections anchor the Elegance Tower record: 86.23% on 12 April 2026, with the facade, MEP systems and interiors still in progress, and 100% on 16 September 2026, when the report classed the tower Completed. The April report also shows an earlier 66.55% as the previous inspection but gives no date for it, so that figure appears on the track below as an undated marker and has no table row. Each row links the full monthly update for that visit.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 100% | 16 September 2026 | View the September 2026 update |
| April 2026 | 86.23% | 12 April 2026 | View the April 2026 update |
Reading the dates: the DLD-registered completion date for project 2475 is 28 February 2026 and the scheduled handover was Q1 2026, yet the inspection of 12 April 2026 still recorded 86.23%, and 100% arrived only on 16 September 2026, after DCD approval on 20 July 2026 and the Building Completion Certificate on 28 July 2026. The registered date was fixed when the project entered the DLD register on 10 November 2022; the handover of each apartment is confirmed by DAMAC to its owner.
Pace Analysis
How Fast Elegance Tower Has Been Built
Elegance Tower's record offers one measured interval between dated inspections and one derived average across the whole build, and the gap between the two is the story:
- 12 Apr 2026 to 16 Sep 2026: finishing and commissioning, 86.23% to 100%About 2.6 points per month
- 16 Jan 2023 to 16 Sep 2026: derived whole-build average, start to 100%About 2.3 points per month
The closing 13.77 points took 157 days, which works out to 2.63 points per month on a 30-day month, a touch faster than the tower's 44-month average of about 2.3. That runs against the usual taper, where the last points of a build come slowest, and the reason sits inside the interval: DCD approval on 20 July 2026, the Building Completion Certificate on 28 July 2026 and the fixed utility meters were all in place by the September visit, so the final reading captured sign-offs as well as site work. The undated 66.55% before April cannot be turned into a rate, because the time behind its 19.68-point gap is not on record. For an end user, the curve says the building is certified and the open question is the handover date; for an investor, it shows a delivery that arrived 200 days after the 28 February 2026 registered date: a late finish, but a finish, with both certificates in hand.
Get the Next Inspection Figure First
Tell me you are tracking Elegance Tower and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Elegance Tower at Downtown Dubai
The 100% recorded on 16 September 2026 only means something next to the building it describes. The project guide covers what this record was tracking toward:

Elegance Tower: Zuhair Murad-Branded Homes in Downtown Dubai
Elegance Tower is a DAMAC tower in Downtown Dubai of 296 one and two bedroom apartments, branded by Zuhair Murad.
View the Elegance Tower Project GuideConsidering a Completed-Building Entry?
Units at Elegance Tower are limited now that the building is recorded complete. If the record on this page is what brought you here, ask me what is currently available before the remaining choice narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Elegance Tower Build Stages, Mapped to the Inspections
Each stage below is tied to the window it occupied in the Elegance Tower record, from the November 2022 registration to the September 2026 reading, so the long undocumented middle and the fast, well-documented finish are both visible.
Registration and Construction Start
Registered with the DLD on 10 November 2022 as project 2475 on plot 469, with construction recorded as started on 16 January 2023.
Foundations, Podium, and Tower Frame
By the 12 April 2026 inspection, enabling works, foundations, substructure, and superstructure for the ground, four podium levels, 25 floors, and roof were all recorded complete.
Envelope, Services, and Finishes
With the frame finished, work had moved to the facade, MEP systems, and interiors, with external works spread across several stages, when the tower read 86.23% on 12 April 2026, 19.68 points above the undated 66.55%.
DCD Approval and Completion Certificate
DCD approval followed on 20 July 2026 and the Building Completion Certificate on 28 July 2026, both dates recorded in the September 2026 inspection report.
Completion Recorded, Handover Stage
The September report counted every package from structure to infrastructure as essentially finished and the water, gas, and electrical meters installed at the 100% reading of 16 September 2026; each owner's handover date is confirmed by DAMAC.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Elegance Tower's own record.
Buyer Position
Tracking Your Position at Elegance Tower
This page is one of four project resources that together cover a Elegance Tower purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Elegance Tower Construction Updates
This page: every dated RERA reading for Elegance Tower, from the January 2023 start to 100%.

Elegance Tower Golden Visa Through a 2 Bedroom Downtown Apartment
Only the 2 bedroom apartments at DAMAC's Elegance Tower, 296 freehold apartments in Downtown Dubai, clear the threshold individually.
Read the Elegance Tower Golden Visa Guide
Elegance Tower Escrow: DAMAC's Downtown Account, Certified 100%
Elegance Tower, DAMAC's Downtown Dubai project 2475 with the DLD, read 100% certified September 2026; 296 units escrowed at Emirates NBD.
Verify the Elegance Tower Escrow Account
Elegance Tower Snagging for a Zuhair Murad Downtown Tower
Elegance Tower is DAMAC Properties' Downtown Dubai tower branded by Zuhair Murad, with 296 one and two bedroom apartments.
Book Elegance Tower SnaggingApproaching Handover
Between 100% and Handover: What Elegance Tower Buyers Should Do Now
The 16 September 2026 reading leaves no construction gap at Elegance Tower; what stands between the certified building and an owner's keys is DAMAC's handover notice, the 20% completion instalment for buyers on the 2022 launch plan of record, and title registration. Handover notices typically give owners a short window to complete their appointment, so the three steps below belong now, before the notice lands.
First, have your own apartment inspected independently so any defects are on record before you sign acceptance; the Elegance Tower snagging inspection page explains how to time it against the handover notice.
Second, confirm that the completion instalment goes only to the project's Emirates NBD escrow account by checking it on the Elegance Tower escrow account page, not against a payment request alone.
Third, if you hold a 2 bedroom unit and residency is part of the plan, settle eligibility through the Elegance Tower Golden Visa guide before the title deed is issued, since the deed is what the application rests on.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Downtown Dubai Structure
Elegance Tower is one finished building in a district that was already built out around Burj Khalifa long before its January 2023 start. These three pages set the record in its market, community, and developer context:

Downtown Dubai Properties for Sale
Browse apartments, branded residences and penthouses for sale around Burj Khalifa and The Dubai Mall.
See Downtown Dubai Properties for Sale
Downtown Dubai Community Overview
Read the Downtown Dubai guide: Emaar's city core around Burj Khalifa, The Dubai Mall and Dubai Opera, with prices and returns.
Explore the Downtown Dubai Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Elegance Tower Construction Updates Frequently Asked Questions
Elegance Tower is recorded as Completed: the RERA inspection of 16 September 2026 measured 100% construction progress, and the DLD register listed project 2475 as Finished when checked on 23 September 2026. The building is at the handover stage, and every reading behind that status is in the inspection timeline above.
The 16 September 2026 inspection recorded 100%, a rise of 13.77 points from the 86.23% measured on 12 April 2026, and the same report notes DCD approval dated 20 July 2026 and the Building Completion Certificate dated 28 July 2026. The visit itself is covered in the Elegance Tower September 2026 construction update.
The DLD-registered completion date for project 2475 was 28 February 2026 and the scheduled handover was Q1 2026, while the tower reached 100% only on 16 September 2026, 200 days after the registered date. The handover of each apartment is confirmed by DAMAC to its owner, and this page's record is updated if the DLD entry for the project changes.
DLD records show 296 apartments at Elegance Tower, all in 1 and 2 bedroom layouts, and a total built area of 26,281.01 sq m on plot 469. The inspection reports describe the building as ground, four podium levels, 25 floors and roof.
Over its one dated interval, Elegance Tower rose from 86.23% on 12 April 2026 to 100% on 16 September 2026, about 2.6 points per month across 157 days. Measured from the 16 January 2023 start, the derived whole-build average is about 2.3 points per month over 44 months; both figures are set out in the pace analysis above.
Construction started on 16 January 2023, about two months after the project was registered with the DLD on 10 November 2022. The first dated reading on this record is 86.23% on 12 April 2026, documented in the Elegance Tower April 2026 construction update, while the 66.55% shown before it carries no inspection date.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Elegance Tower construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.