Emaar · The Valley
Farm Gardens at The Valley Construction Updates
The Finished Build Record of a Gated Villa Enclave off the Dubai Al Ain Road
Farm Gardens at The Valley reached 100% on the DLD register at its 24 March 2026 inspection, completing 146 Emaar villas ahead of the August 2026 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Farm Gardens at The Valley at a Glance
Farm Gardens at The Valley is Emaar's gated enclave of 146 two-storey villas on plot 555 in Al Yufrah 1, registered with the Dubai Land Department on 31 October 2022 and started on 16 March 2023. Just over three years after that start, the register read 100% at the 24 March 2026 inspection with its status set to Finished. Because this is a low-rise neighbourhood rather than a tower, the closing RERA notes cover streets, utilities and infrastructure alongside the villas themselves, which is why the building completion certificate matters as much here as the percentage.
2479
Finished
16 March 2023
146 villas
127,691.17 sq m
31 August 2026
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Farm Gardens at The Valley Construction Update Timeline
The Farm Gardens record is short and ends at the top: one dated reading of 100% on 24 March 2026, preceded on the register by an undated previous reading of 90.26%, a final step of 9.74 points. Five months before that dated reading, on 22 October 2025, the RERA notes place the building completion certificate. The track below therefore carries a single dot, and the table row links the March 2026 update that documents the closing inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| March 2026 | 100% | 24 March 2026 | View the March 2026 update |
Reading the dates: the DLD-registered completion date for project 2479 is 31 August 2026, yet the RERA inspection notes record the building completion certificate (BCC) as received on 22 October 2025, about ten months earlier, and the register read 100% at the 24 March 2026 inspection. In this record the registered date trailed the build instead of leading it, and handover is dated August 2026, the same month.
Pace Analysis
How Fast Farm Gardens at The Valley Has Been Built
With only one dated reading on the register, the Farm Gardens pace story is told through the whole-build average, the size of the final step, and the gap between certificate and registered date:
- Mar 2023 to Mar 2026: construction start on 16 March 2023 to 100% on 24 March 2026About 2.8 points per month
- Previous register reading to 24 Mar 2026: 90.26% (undated) to 100%A 9.74 point final step
- Oct 2025 to Aug 2026: BCC on 22 October 2025 against registered completion on 31 August 2026313 days ahead of the registered date
Roughly 36 months separate the Farm Gardens start from the Finished status, and because the register prints no dated reading between those points, the curve in between is not on record; the 2.8 point average is the honest measure, not a phase-by-phase velocity. What the record does show clearly is the order of events. The building completion certificate arrived about 31 months into the build and roughly ten months before the 31 August 2026 registered date, and by 24 March 2026 the inspector found water, gas and electrical meters fixed while Emaar's own building-level snagging and deep cleaning were still running. For an end user, that sequence meant the construction wait was over well before the August 2026 handover month. For an investor judging Emaar's newer launches in The Valley, it is a delivery that ran inside its own registered timeline. None of these figures is a forecast: the record is closed at 100%.
Get the Next Inspection Figure First
Tell me you are tracking Farm Gardens at The Valley and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Farm Gardens at The Valley at The Valley by Emaar
A finished percentage only means something next to what was actually delivered. The full project guide sets out the 146 villas this record describes:

Farm Gardens at The Valley: Horizon and Earth Style Villas
Farm Gardens at The Valley is a gated Emaar enclave of 146 four and five bedroom villas built ground plus one.
View the Farm Gardens at The Valley Project GuideConsidering a Completed Villa?
Availability at Farm Gardens is limited now that construction is complete, and what remains can change at any time. If the record on this page is what brought you here, ask me what is currently available before the remaining villas are taken.
Ask About Remaining Availability on WhatsAppStage Record
Farm Gardens at The Valley Build Stages, Mapped to the Inspections
Only one dated reading exists for Farm Gardens, so each stage below is anchored to the milestones the DLD register and the RERA notes actually carry: registration in October 2022, the March 2023 start, the October 2025 BCC, and the 100% inspection of March 2026.
Registration and Mobilization
Project 2479 was registered with the DLD on 31 October 2022, and construction started on 16 March 2023 on plot 555 in Al Yufrah 1, with mobilization the first package the RERA notes list as done.
Structure Across 146 Villas
Concrete structure and blockwork went up across the 146 G+1 villas; the register prints no dated reading from this stage, so its pace sits inside the 2.8 point monthly average.
Envelope, MEP, and Internal Finishes
External envelope, MEP and internal finishes had advanced far enough for the building completion certificate to be received on 22 October 2025, and all three read substantially completed by 24 March 2026.
Streets, Parks, and Utilities
Infrastructure was substantially completed by 24 March 2026 with water, gas and electrical meters fixed, and the RERA photographs show finished asphalt streets, paved footpaths, street lights and a landscaped park.
Completion, Developer Snagging, and Handover
After the BCC of 22 October 2025 and the DCD of 28 November 2025 in the RERA notes, the register read 100% on 24 March 2026 while Emaar ran its own building-level snagging and deep cleaning, ahead of handover dated August 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Farm Gardens at The Valley's own record.
Buyer Position
Tracking Your Position at Farm Gardens at The Valley
This page is one of four project resources that together cover a Farm Gardens at The Valley purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Farm Gardens at The Valley Construction Updates
This page: the Farm Gardens record from its March 2023 start to 100% in March 2026.

Farm Gardens at The Valley Golden Visa Through a Single Villa
Farm Gardens at The Valley, 146 Emaar villas on title deeds, qualifies at both the 4 bedroom and 5 bedroom villa.
Read the Farm Gardens at The Valley Golden Visa Guide
Farm Gardens at The Valley: A Finished Build's Emirates NBD Escrow
Farm Gardens at The Valley read 100% certified in March 2026; DLD project 2479 escrowed 146 units at Emirates NBD.
Verify the Farm Gardens at The Valley Escrow Account
Farm Gardens at The Valley Snagging: Horizon and Earth Villas
Farm Gardens at The Valley is a community of 146 Emaar villas, four and five bedroom homes beneath a roof terrace.
Book Farm Gardens at The Valley SnaggingApproaching Handover
Between 100% and Handover: What Farm Gardens at The Valley Buyers Should Do Now
Nothing structural stands between Farm Gardens and occupation: the register read 100% on 24 March 2026, the BCC dates from 22 October 2025, and handover is dated August 2026. What remains sits on the buyer's side, and handover appointments at completed communities typically leave owners a short window to respond, so the three steps below belong before your acceptance appointment, not after it.
First, if your villa has not yet been accepted, arrange independent snagging so every defect in the two-storey home is on record before you sign; the Farm Gardens villa snagging page covers timing and scope, separate from the building-level snagging Emaar was running at the March 2026 inspection.
Second, check any instalment still due under your SPA against the Emirates NBD account shown on the Farm Gardens escrow account page, so a final payment goes only to the registered project account for 2479.
Third, if residency is part of your plan, confirm eligibility through the Farm Gardens residency visa guide; with construction finished, the title deed position now shapes the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore The Valley by Emaar Structure
A finished build record reads differently once you see what is still rising around it. These three pages set the Farm Gardens completion against The Valley's newer phases, the wider community, and Emaar's portfolio:

The Valley by Emaar Properties for Sale
Browse townhouses and villas for sale in The Valley, comparing phases, prices and payment plans.
See The Valley by Emaar Properties for Sale
The Valley by Emaar: Nature-Inspired Villas and Townhouses on Dubai-Al Ain Road
Launched in 2019, The Valley has villa and townhouse clusters with a central Town Centre, Golden Beach and parks.
Explore the The Valley by Emaar Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Farm Gardens at The Valley Construction Updates Frequently Asked Questions
The Dubai Land Department register lists Farm Gardens at The Valley as project 2479 with the status Finished and 100% construction progress at the inspection of 24 March 2026. The same record shows 146 units, registration on 31 October 2022, a construction start on 16 March 2023, a registered completion date of 31 August 2026, and no remarks against the project.
The inspection of 24 March 2026 closed the Farm Gardens at The Valley record, with the DLD register reading 100%, a 9.74 point step from its previous reading of 90.26%, which the register prints without a date. The RERA inspection report of the same day gives the progress status as Completed, and the site detail sits in the Farm Gardens at The Valley March 2026 construction update.
Farm Gardens at The Valley carries a registered completion date of 31 August 2026 on the DLD register, while the RERA inspection notes record the building completion certificate (BCC) as received on 22 October 2025, 313 days earlier. The registered date was fixed at project registration and the physical build finished well inside it; handover is dated August 2026, and as of 17 September 2026 both that month and the registered date have passed.
The Farm Gardens at The Valley record covers 146 villas, the unit count on the DLD register at the 24 March 2026 inspection, built as two-storey (G+1) homes in four and five bedroom layouts with Horizon and Earth exteriors. The floor plans give total areas of about 4,950 sq ft (460 sq m) for the 4 bedroom villa and about 5,657 sq ft (526 sq m) for the 5 bedroom villa.
Farm Gardens at The Valley took about 36 months from its 16 March 2023 construction start to the 100% DLD register reading of 24 March 2026, an average of roughly 2.8 percentage points per month. The building completion certificate followed about 31 months after the start, on 22 October 2025, according to the RERA inspection notes; the full arithmetic is in the pace analysis above.
Construction at Farm Gardens at The Valley started on 16 March 2023 according to the DLD register, about four and a half months after the project was registered on 31 October 2022. The launch payment plan of record set its 10% down payment in December 2022 and its first 10% instalment in February 2023, so both fell due before the recorded start, and the first dated progress reading on the register is the 100% of 24 March 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Farm Gardens at The Valley construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.