Emaar · Emaar South
Golf Acres at Emaar South Construction Updates
The Verified Build Record Beside the Emaar South Golf Course
Golf Acres recorded 3.47% construction at its 23 June 2026 RERA inspection, with enabling and piling works opening the verified record beside the Emaar South golf course.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Golf Acres at Emaar South at a Glance
Golf Acres is Emaar's 158-home release on plot 7099 at Madinat Al Mataar, registered with the Dubai Land Department as a G+P+16 residential building alongside ten G+1 townhouses. Thirteen months separate the 23 May 2025 construction start from the 3.47% recorded at the June 2026 inspection, so this record is short by design rather than by neglect. That is the position most Emaar South buyers are actually in right now: holding an off-plan contract on a building whose verified history fits in a single row, which makes every registration figure below worth reading closely.
3426
Active
23 May 2025
158 homes
18,679.79 sq m
31 December 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Golf Acres at Emaar South Construction Update Timeline
One reading carries a published inspection date so far: 3.47% on 23 June 2026, with the RERA report describing mobilization, enabling works and piling in progress on plot 7099. The project register also shows an earlier reading of 0.01% with no published inspection date attached, so it is mentioned here for completeness but is not plotted on the track and holds no table row. The track below therefore reads as a starting line rather than a curve, and it gains a dot with each new inspection.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 3.47% | 23 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Golf Acres at Emaar South Has Been Built
With a single dated reading on file, pace at Golf Acres cannot yet be measured between inspections. Two derived figures frame what 3.47% actually represents:
- 23 May 2025 start to the 23 June 2026 reading, zero to 3.47%About 0.3 points per month, derived
- 23 June 2026 to the 31 December 2028 registered completion, 96.53 points outstandingAbout 3.2 points per month, implied
Neither number is a velocity in the sense a mid-build project produces, and the first one flatters nobody: thirteen months of site work converting into 3.47% is what certified progress looks like while the money goes into mobilization, enabling works and piles that end up below ground. The figure worth carrying forward is the second. Closing 96.53 points before 31 December 2028 asks the site for roughly ten times the recorded pace of its first year, which is normal once a G+P+16 frame starts climbing but is exactly the assumption the next two or three inspections will test. For a buyer, that means the useful question at Golf Acres right now is not whether 3.47% is low, but how quickly the reading moves once the structure is out of the ground.
Get the Next Inspection Figure First
Tell me you are tracking Golf Acres at Emaar South and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Golf Acres at Emaar South at Emaar South Dubai
A percentage only means something next to what it is building toward. Here is what 158 homes on plot 7099 are scheduled to become:

Golf Acres at Emaar South, Apartments and Townhouses on the Course
Golf Acres at Emaar South is a 158 residence address on the course edge, mixing apartments with ten ground level townhouses.
View the Golf Acres at Emaar South Project GuideConsidering an Early-Stage Entry?
Inventory at Golf Acres is limited at this point in the release, and early-stage entries are the ones that carry the longest run of inspections on this page. Ask me what is still available before that narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Golf Acres at Emaar South Build Stages, Mapped to the Inspections
Each stage below is tied to the window it occupies in this project's own record, from the 11 December 2024 DLD registration through to the registered completion date, so you can see exactly where the 3.47% reading sits in the sequence.
Registration and Pre-Construction
Project 3426 was registered with the Dubai Land Department on 11 December 2024, with the escrow trust account opened at Abu Dhabi Commercial Bank before site work began.
Mobilization, Enabling and Piling
From the 23 May 2025 start: site mobilization, enabling works and piling on plot 7099, all three recorded as in progress at the 23 June 2026 inspection.
Substructure and Podium
Pile caps, basement and podium slabs for the residential building. This is the stage where the recorded percentage typically begins to move faster than the 0.3 points per month of the first year.
Tower Frame and Townhouse Shells
Sixteen residential floors above the podium plus the ten G+1 townhouse shells. The longest and heaviest-weighted stretch of the 96.53 points still outstanding at Golf Acres.
Facade, Fit-Out and Handover
Envelope, apartment fit-out, amenity decks, landscaping and commissioning ahead of the Q4 2028 handover Emaar has set for the 158 homes.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Golf Acres at Emaar South's own record.
Buyer Position
Tracking Your Position at Golf Acres at Emaar South
This page is one of four project resources that together cover a Golf Acres at Emaar South purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Golf Acres at Emaar South Construction Updates
The running record: every Golf Acres inspection percentage and date from 2025 through to handover.

Golf Acres at Emaar South Golden Visa Starts at the 3 Bedroom
In Golf Acres at Emaar South the threshold falls between 2 and 3 bedrooms; only 3 bedroom apartments and townhouses qualify.
Read the Golf Acres at Emaar South Golden Visa Guide
Golf Acres at Emaar South Escrow Account, Abu Dhabi Commercial Bank
Golf Acres at Emaar South, DLD project 3426, holds 158 units in Abu Dhabi Commercial Bank escrow, 3.47% certified June 2026.
Verify the Golf Acres at Emaar South Escrow AccountApproaching Handover
Between 3.47% and Handover: What Golf Acres at Emaar South Buyers Should Do Now
At this point in a build there is no finished unit to inspect and no keys to collect, which tempts buyers to stop paying attention for two years. That is the wrong instinct on a project whose payment schedule keeps running while the recorded percentage barely moves. Three things are worth doing between now and the structural inspections.
First, confirm that every installment you pay is going into the project trust account rather than a developer operating account; the Golf Acres escrow account page covers the registered account for project 3426 and how released funds are tied to certified progress.
Second, read the inspection record rather than the launch material. The June 2026 Golf Acres construction update sets out what the 3.47% reading was based on, and each new inspection becomes the reference point for whether the 31 December 2028 registered date still looks sound.
Third, if residency is part of your reason for buying, settle the eligibility question early instead of at title deed stage; the Golf Acres Golden Visa eligibility guide sets out how an off-plan purchase at this stage is assessed.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar South Dubai Structure
An inspection percentage is a narrow lens. These three pages widen it to the surrounding inventory, the district itself, and the developer behind project 3426:

Emaar South Dubai Properties for Sale
Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.
See Emaar South Dubai Properties for Sale
Emaar South Dubai Community Overview
Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.
Explore the Emaar South Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Golf Acres at Emaar South Construction Updates Frequently Asked Questions
Golf Acres is an active DLD-registered project (number 3426) recorded at 3.47% at the inspection of 23 June 2026, with its RERA progress status logged as pre-construction progressing. The single dated reading on file is set out in the inspection timeline above.
The 23 June 2026 inspection recorded 3.47% construction progress on plot 7099, with mobilization, enabling works and piling all noted as in progress. The register shows an earlier reading of 0.01% but publishes no date against it, so no point delta is stated here. The full write-up is in the June 2026 construction update for Golf Acres.
The DLD-registered completion date for project 3426 is 31 December 2028, matching the Q4 2028 handover Emaar states for the development. That date has not lapsed, and with 3.47% recorded on 23 June 2026 it implies roughly 3.2 percentage points of certified progress per month across the remaining window.
DLD registration records show 158 homes across a total built-up area of 18,679.79 sq m, split between a G+P+16 residential building and ten G+1 townhouses on plot 7099 at Madinat Al Mataar.
As of the 23 June 2026 inspection: site mobilization, enabling works and piling, all recorded as ongoing rather than complete. Nothing is standing above ground yet, which is why certified progress reads 3.47% after thirteen months of site activity. The stage sequence from here is mapped in the Golf Acres stage record.
Construction officially started on 23 May 2025, six months after the project was registered with the Dubai Land Department on 11 December 2024. The first inspection carrying a published date, on 23 June 2026, recorded 3.47%.
The registered description is a G+P+16 floor residential building plus ten G+1 townhouses. Within that, layouts run from one bedroom apartments on the podium and tower floors to three bedroom apartments and townhouses, with golf course orientation across the keyplan. Full layouts sit on the Golf Acres project page.
Project 3426 holds a registered trust account at Abu Dhabi Commercial Bank, and funds are released against progress certified by the same RERA inspections that produce the 3.47% figure on this page. How that release mechanism works sits on the Golf Acres escrow account guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Golf Acres at Emaar South construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.