Emaar · Dubai Hills Estate · Construction Update
Golf Grand Construction Update - July 2025
July 2025 Inspection Confirms Golf Grand Reaches 77.02% Construction Progress in Dubai Hills Estate
External envelope, MEP, and internal finishes now progress at different stages across Golf Grand, verified at 77.02 percent in the 30 July 2025 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Golf Grand Construction Snapshot
A 7.13 point rise from the previous recorded reading carries Golf Grand to 77.02% and into the finishing band, the stage where the next construction-linked payment trigger arrives sooner than the next visible change on site.
Golf Grand at Dubai Hills Estate
2599
Active
77.02%
30 July 2025
01 August 2023
323 residential units
31,421.99 sq m
31 March 2027
Data source: RERA Independent Progress Monitoring Report inspection conducted on 30 July 2025 for developer Dubai Hills Estate L.L.C, tracked against the DLD project register for project 2599. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Golf Grand Construction Progress Summary
Between the previous recorded reading of 69.89% and the 30 July 2025 visit at 77.02%, Golf Grand crossed the line that separates building a tower from fitting one out. The inspector signed off enabling, foundation, substructure and superstructure works as complete, and logged the envelope, MEP, internal works and external works as progressing at different stages. Roughly twenty months of registered programme remained at that reading.
- Enabling and foundation works across plot 2447
- Substructure through the basement and podium levels
- Superstructure to the full fifteen residential floors
- External envelope across the tower elevations
- MEP systems: mechanical, electrical, and plumbing installation
- Internal works and finishes across the 323 apartments
- External works around the podium and street level retail
- The 80% construction milestone on the published payment schedule
- Remaining RERA inspection cycles toward 100%
- Building completion certificate procedures
- Handover from the registered completion date of 31 March 2027
Payment Linked Progress
What 77.02% Progress Means for Golf Grand Buyers
Golf Grand was launched on a schedule that attaches instalments to certified construction percentages rather than to calendar dates alone, so a verified reading of 77.02% is a countdown as much as a status line. At this point in the build, four actions matter most.
Verify the escrow account
Every payment ahead of handover belongs in the DLD regulated escrow account registered for project 2599, held with Emirates NBD per the 30 July 2025 monitoring report. Golf Grand escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA to the certified percentage
The published Golf Grand schedule places a 10% instalment at 80% construction, and the July 2025 reading of 77.02% sits under three points below that line. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Plan the snagging window early
Golf Grand has cleared the structural threshold, but with registered completion at 31 March 2027 the booking window opens later in the programme rather than now. Golf Grand snagging inspection guide sets out what to arrange and when.
Track the remaining cycles
Several inspection readings separate 77.02% from completion certification, and each one can move a payment date. Golf Grand construction updates hub keeps the sequence in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 77.02%?
Entering a Dubai Hills Estate tower at this point trades payment-plan runway for a verified structure: the frame is certified, the community around it is already trading, and the open question narrows to which layouts remain. Every payment goes to the DLD-registered escrow account for project 2599, released against certified construction progress.
- Certified structure: enabling to superstructure complete on the July 2025 record
- Roughly twenty months to the registered completion date
- Only the closing instalments of the 10/80/10 plan sit ahead
- Construction risk carried from excavation through to handover
- Two to four years of waiting is the usual delivery horizon
- Longer instalment runway, priced at launch levels
The project page records limited availability on request across a 323 unit mix of 129 one bedroom, 159 two bedroom, and 35 three bedroom homes; availability shifts between cycles.
About the Development
Golf Grand Project Details

With the frame topped out, Golf Grand is a finishing stage building of 323 one, two, and three bedroom apartments across fifteen residential floors above an amenity podium with street level retail, on the Club Villas edge of the Dubai Hills Golf Course. Starting prices: AED 1.40M ≈ USD 381K.
For buyers entering at this stage, the trade off is a shorter wait against a later position in the payment plan, with handover scheduled for Q1 2027 and 31 March 2027 carried as the registered completion date.
Site Context This Cycle
Explore Golf Grand Location on Dubai Map
Golf Grand occupies plot 2447 in Hadaeq Sheikh Mohammed Bin Rashid, set on the Club Villas edge of Dubai Hills Estate with its principal elevations turned toward the fairways, and that orientation is exactly why the external envelope package dominates this cycle: the glazing and balcony line facing the golf course is the most exposed and most sequenced part of the remaining build.
Because the surrounding district was delivered years ahead of this tower, with the golf club, Dubai Hills Park, Dubai Hills Mall, King's College Hospital, and the GEMS school all open and operating, Golf Grand is finishing into a working neighbourhood rather than a construction zone, which changes what the remaining twenty months actually cost a buyer weighing occupancy or rental plans. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Golf Grand During Finishing Stage Construction
Once a project clears its structure, residency planning, payment protection, and handover preparation stop being theoretical. Each resource below is matched to where Golf Grand stood at the July 2025 reading.

Golf Grand Construction Updates
This page: the verified 30 July 2025 inspection record for Golf Grand, reading by reading.

Golf Grand at Dubai Hills Estate Golden Visa in a Finished Tower
Golf Grand at Dubai Hills Estate, Emaar's 323-apartment golf course tower, qualifies at 2 and 3 bedrooms, not at 1.
Read the Golf Grand Golden Visa Guide
Golf Grand at Dubai Hills Estate: A Fully Certified Escrow Record
Golf Grand at Dubai Hills Estate read 100% certified January 2026; DLD project 2599 kept 323 units' money at Emirates NBD.
Verify the Golf Grand Escrow Account
Golf Grand at Dubai Hills Estate Snagging on the Golf Course Edge
Golf Grand at Dubai Hills Estate is a 15-storey Emaar tower of 323 residences above an amenity podium with street-level retail.
Book a Golf Grand Snagging InspectionUpdate Timeline
Other Golf Grand Construction Updates
Follow the full inspection history to see how Golf Grand has moved through each construction phase, reading by reading.
Where This Update Fits
Explore Golf Grand Structure
This monthly report is one node in the wider record: the community that surrounds the site, the developer delivering it, and the listings competing with it.

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Golf Grand Construction Progress in July 2025: Frequently Asked Questions
As of the RERA Independent Progress Monitoring Report inspection carried out on 30 July 2025, Golf Grand stands at 77.02% construction progress in the DLD project register for project 2599.
Golf Grand moved from 69.89% at the previous recorded inspection to 77.02% on 30 July 2025, a gain of 7.13 points. The register publishes the previous reading as a percentage without a paired date, so the interval itself is not stated in the record.
The 30 July 2025 record shows no slippage: registered completion remains 31 March 2027, with 22.98 percentage points between that reading and full certification and roughly twenty months of programme still to run. How inspection cycles and completion certification work is covered on the Golf Grand construction updates hub.
Yes. Completion dates in the DLD project register are revised between inspection cycles when a programme moves. The date shown here reflects the register as it stood at the 30 July 2025 inspection; any revision appears in a later update on this cluster.
The inspector recorded enabling, foundation, substructure and superstructure works as completed. Internal works, the external envelope, MEP, internal finishes and external works were all progressing at different stages across the fifteen residential floors and the amenity podium.
Emaar published Golf Grand on a construction-linked schedule in which the seventh instalment of 10% falls due at 80% construction and the final 10% at 100%. At the 30 July 2025 reading of 77.02%, the 80% trigger sat under three points ahead, which is why this cycle matters more to instalment timing than the raw percentage suggests. Individual obligations are set by each buyer's own sale and purchase agreement.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2025 inspection record for Golf Grand at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.