Emaar · Emaar South
Greenridge at Emaar South Construction Updates
The Verified Build Record for 520 Townhouses at Madinat Al Mataar
Greenridge at Emaar South recorded 35.6% construction on 17 June 2026, with superstructure now rising across townhouse clusters that broke ground in January 2025.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Greenridge at Emaar South at a Glance
Greenridge is Emaar's 520-home townhouse community on plot 6713 in Madinat Al Mataar, held by the Dubai Land Department as project 3283. Roughly sixteen and a half months separate its 30 January 2025 construction start from the 35.6% recorded in June 2026, and the register entries below are the anchors behind that reading. Because this site spreads sideways instead of upward, its percentage is the sum of many clusters moving on separate sequences, not one frame climbing floor by floor.
3283
Active
30 January 2025
520 townhouses
127,197.41 sq m
Q4 2028 (31 December 2028)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Greenridge at Emaar South Construction Update Timeline
One dated inspection anchors this record so far: 17 June 2026 at 35.6%. The register holds an earlier figure of 26.38% as well, 9.22 points lower, but no inspection date is attached to it. That reading therefore gets no dot on the track and no row in the table below, because pairing it with an invented date would manufacture a pace Greenridge has not yet demonstrated. Everything plotted here is tied to a date the record actually contains.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 35.6% | 17 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Greenridge at Emaar South Has Been Built
With a single dated reading on file, pace here is a derived figure rather than a measured one. Both lines below state exactly what they are:
- 30 Jan 2025 start to 17 Jun 2026 inspection: 0% to 35.6% across about 16.6 monthsAbout 2.2 points per month, derived
- Undated 26.38% register figure to 35.6% on 17 Jun 20269.22 points, interval not on record
Two point two points per month is an average rather than a velocity, and averages flatten the phases underneath them. That single line covers mobilisation, an enabling and foundation period, and the first superstructure, three stages that never move at the same rate. What the June 2026 cycle actually describes is a plot running four packages at once, with groundworks close to finished while frames, envelope, and services advance unevenly from cluster to cluster. That parallelism is why a 520-townhouse community tends to record its progress in steps rather than a smooth ramp. It also means the second dated inspection will matter more than the first: it will produce the first figure on this page that measures Greenridge against its own recent output instead of against its start date. For anyone on the construction-linked plan, the certification at 40 percent is the next event the register will settle.
Get the Next Inspection Figure First
Tell me you are tracking Greenridge at Emaar South and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Greenridge at Emaar South at Emaar South Dubai
A percentage only means something next to what it is building. The project guide covers what this record is tracking toward:

Greenridge at Emaar South: Grace and Pearl Townhouse Clusters
Greenridge at Emaar South is a 520 home Emaar townhouse community of four unit clusters around linear parks and open lawns.
View the Greenridge at Emaar South Project GuideBuying Into a Build Already Under Way?
A certified 35.6% means a share of the construction risk sits behind the figure on this page rather than ahead of it, and the remainder arrives as dated readings you can follow. Greenridge availability moves between inspections, so ask me what is on the list today before planning around it.
Ask About Remaining Availability on WhatsAppStage Record
Greenridge at Emaar South Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it occupied in Greenridge's own register entries rather than to a generic construction sequence, so you can see where the 17 June 2026 reading actually sits.
Registration and Site Mobilisation
Project 3283 entered the DLD register on 17 September 2024, with the trust account opened at Mashreq Bank PSC before any work started on plot 6713.
Enabling, Foundation, and Substructure
Construction began on 30 January 2025. Fifteen months later the register still carried groundworks as an open item, which is what batching 520 homes across a large plot looks like on paper.
Superstructure Across the Clusters
G+1 frames rising across the townhouse clusters. This is the package carrying most of the movement in the 35.6% figure and the one to watch before the 40 percent trigger.
Envelope, Internal Works, and MEP
Started but uneven between clusters at this reading. As frames top out, these packages take over the percentage and drive the run toward the 60 and 80 percent triggers.
Infrastructure, Certification, and Handover
Plot-wide roads, landscaping, and the community centre closing out, followed by completion certification. The register currently places that endpoint at 31 December 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Greenridge at Emaar South's own record.
Buyer Position
Tracking Your Position at Greenridge at Emaar South
This page is one of four project resources that together cover a Greenridge at Emaar South purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Greenridge at Emaar South Construction Updates
This page: every dated RERA reading for Greenridge, from the 30 January 2025 start onward.

Greenridge at Emaar South Golden Visa: 520 Townhouses, All Qualifying
Greenridge at Emaar South is a 520 townhouse freehold community where the 3 and 4 bedroom typologies each qualify individually.
Read the Greenridge at Emaar South Golden Visa Guide
Greenridge at Emaar South Escrow Account, Banked with Mashreq
Mashreq banks escrow for Greenridge at Emaar South, DLD project 3283, where 520 units stood 35.6% certified in June 2026.
Verify the Greenridge at Emaar South Escrow AccountApproaching Handover
Between 35.6% and Handover: What Greenridge at Emaar South Buyers Should Do Now
At this reading the next thing the record decides is money rather than keys. The registered Greenridge plan releases instalments against certified completion at 20, 40, 60, and 80 percent, which puts the 20 percent point behind the June 2026 figure and leaves 40 percent as the next call. Milestone calls tend to arrive with little warning once an inspection clears, which makes the three checks below jobs for now rather than for the notice period.
First, confirm where your next transfer is going. The Greenridge escrow account page carries the Mashreq Bank PSC trust account recorded against project 3283, and a two-minute check against the DLD record belongs before the payment, not after it.
Second, read your own sale and purchase agreement against the 35.6% now certified. The binding schedule lives in that document rather than on this page, and knowing what your specific clauses trigger, and how long they give you, is far easier before the next certified figure lands than after.
Third, if the purchase may support residency, settle eligibility early using the Greenridge Golden Visa guide, since an off-plan position runs on the Oqood interim registration until a title deed exists at handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar South Dubai Structure
Percentages describe the plot. What surrounds it decides how the finished home lives. Three pages carry that wider context:

Emaar South Dubai Properties for Sale
Browse apartments, townhouses and villas for sale in Emaar South, with prices, payment plans and availability.
See Emaar South Dubai Properties for Sale
Emaar South Dubai Community Overview
Read the Emaar South guide: a golf community of apartments, townhouses and villas beside Al Maktoum International Airport.
Explore the Emaar South Dubai Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Greenridge at Emaar South Construction Updates Frequently Asked Questions
Project 3283 holds active status in the DLD register and stood at 35.6% when RERA inspected the site on 17 June 2026. At that reading the clusters carried structure, envelope, and services work at the same time rather than in sequence. Every dated figure is set out in the inspection timeline above.
The 17 June 2026 inspection recorded 35.6%, which is 9.22 points above the earlier register figure of 26.38%. No inspection date is attached to that earlier figure, so the record cannot say how long those 9.22 points took to add. The site report for the cycle is published as the June 2026 construction update.
The DLD record carries a completion window of Q4 2028, dated 31 December 2028. Subtracting the June 2026 reading from a certified 100% leaves 64.4 points to add before that point is reached. Registered windows are forecasts held in the register, not guarantees, and they shift in both directions as work proceeds; this page follows whichever figure the next inspection produces.
DLD registration holds 520 units under project 3283, divided evenly into 260 three-bedroom and 260 four-bedroom freehold G+1 townhouses. The registered total built-up area is 127,197.41 sq m, spread horizontally across plot 6713 rather than stacked into a tower.
Registration with the Dubai Land Department was completed on 17 September 2024 and construction began on 30 January 2025. Roughly sixteen and a half months later, the 17 June 2026 inspection produced the first dated percentage on this page at 35.6%.
Averaged from the 30 January 2025 start to 35.6% on 17 June 2026, progress works out at about 2.2 percentage points per month. That number is derived across the whole period, not measured between two inspections, because only one dated reading currently exists in the register. The calculation is shown in the pace analysis above.
By the 17 June 2026 cycle the certified position was four packages running at once: groundworks and substructure close to finished, G+1 frames going up across the clusters, and envelope, internal, and services work started but uneven from cluster to cluster. Plot-wide infrastructure was recorded as under way rather than complete.
Plot 6713 sits within Madinat Al Mataar, on the airport side of Emaar South. The district around it remains under construction, so the golf course, parks, and Expo City links will look considerably different by the Q4 2028 window than they do at this reading. Format and masterplan position are covered in the Greenridge at Emaar South townhouse project guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Greenridge at Emaar South construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.