Emaar · Dubai Hills Estate
Hillsedge at Dubai Hills Estate Construction Updates
The Verified Build Record Rising Beside Hillside Park
Hillsedge recorded 25.55% construction at its 06 June 2026 RERA inspection, the point where enabling works close out and both Dubai Hills Estate towers start climbing.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Hillsedge at Dubai Hills Estate at a Glance
Hillsedge is Emaar's 406-apartment release on plot 5412 inside Dubai Hills Estate, built as Tower A at nineteen floors, Tower B at eighteen, and a low rise Park Apartments block over one shared podium. Thirteen months separate the 02 May 2025 construction start from the 25.55% recorded in June 2026, and the figures below are the DLD-registered anchors behind that reading. Because three structures share a single podium, the certified percentage summarises three frames sitting at three different stages rather than one tower climbing on its own.
3411
Active
02 May 2025
406 residential units
34,915.67 sq m
31 January 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Hillsedge at Dubai Hills Estate Construction Update Timeline
This record is deliberately short: one inspection date has been published for Hillsedge so far, 06 June 2026, when the register recorded 25.55%. That same report carries a previous reading of 14.84%, a gap of 10.71 points, but no inspection date is published against the earlier figure, so it is noted here in prose and kept out of the dated track and table below. Every new cycle adds one dot and one row.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 25.55% | 06 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Hillsedge at Dubai Hills Estate Has Been Built
With one dated reading on file, the honest pace question at Hillsedge is not phase velocity but whether the build is keeping up with its own registered schedule. Three figures answer it:
- May 2025 to Jun 2026: whole build average from construction start to 25.55%About 1.9 points per month
- Previous reading to 06 Jun 2026: 14.84% to 25.55%, no date published against the earlier figure10.71 points gained
- Jun 2026 to the registered date of 31 Jan 2029: 74.45 points still to certifyAbout 2.3 points per month implied
Read together, those three lines say the site is running close to what its own registered date demands, with the average since groundbreaking about four tenths of a point per month below the rate the remaining distance implies. At this stage that gap is arithmetic rather than a warning: the first thirteen months absorbed enabling works, piling, and foundations, where a great deal of site effort converts into very few certified points, and superstructure is the phase where the percentage usually starts moving faster than the trench work before it. The figure worth watching is not 25.55% but the next reading, because the June cycle was the first with enabling works closed out, which makes the following inspection the first clean measure of how quickly the frames themselves rise. For anyone on the construction linked payment plan that reading matters twice over, since the 30 percent threshold sits only 4.45 points above the June record.
Get the Next Inspection Figure First
Tell me you are tracking Hillsedge at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Hillsedge at Dubai Hills Estate
A certified percentage only means something next to what it is building. The project guide covers the 406 apartments this record is tracking toward:

Hillsedge at Dubai Hills Estate: Two Towers and a Park Block
Hillsedge at Dubai Hills Estate places 406 apartments across two towers and a Park Apartments block around Hillside Park.
View the Hillsedge at Dubai Hills Estate Project GuideConsidering an Entry at 25.55%?
Released inventory at Hillsedge shifts between inspection cycles, and entering while the frames are still rising leaves most of the payment runway ahead of you. If this record is what brought you here, ask me what is currently available before the next release moves.
Ask About Remaining Availability on WhatsAppStage Record
Hillsedge at Dubai Hills Estate Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it actually occupied in the Hillsedge register, so you can see where the 25.55% reading falls in the build.
Registration Before Mobilisation
DLD registration for project 3411 was recorded on 29 November 2024, five months before any work began on plot 5412, which is why the payment plan opens with instalments dated rather than milestone triggered.
Site Activation and Enabling Works
Construction started on 02 May 2025. By the June 2026 report, enabling works across the plot were recorded complete, with piling and substructure carrying almost all of the certified progress from this window.
Foundations Advanced, Frames Climbing
The 06 June 2026 inspection recorded 25.55%: substructure, piling, and foundation works at advanced stages, with superstructure frames standing at differing heights across Tower A, Tower B, and the Park Apartments block.
Facade, Internal Works, and MEP
Internal works and MEP installation were logged at an early stage in June 2026 and scale up once the concrete structure closes. This is the window carrying the 30 and 50 percent payment thresholds.
Amenity Deck, Park, and Certification
The Level 01 amenity deck, the four Hillside Park zones above the podium, and the closing inspection cycles cover the final stretch to the registered completion date of 31 January 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Hillsedge at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Hillsedge at Dubai Hills Estate
This page is one of four project resources that together cover a Hillsedge at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Hillsedge at Dubai Hills Estate Construction Updates
This page: the verified inspection record for Hillsedge, from the 02 May 2025 start toward handover.

Hillsedge at Dubai Hills Estate Golden Visa: One Tier In, One Below
Of the two tiers at Emaar's Hillsedge at Dubai Hills Estate, only the 2 bedroom qualifies; the 1 bedroom starts below.
Read the Hillsedge at Dubai Hills Estate Golden Visa Guide
Hillsedge at Dubai Hills Estate: The Escrow Every Payment Must Reach
Hillsedge at Dubai Hills Estate pays First Abu Dhabi Bank escrow as DLD project 3411, 406 units, 25.55% certified June 2026.
Verify the Hillsedge at Dubai Hills Estate Escrow AccountApproaching Handover
Between 25.55% and Handover: What Hillsedge at Dubai Hills Estate Buyers Should Do Now
Below thirty percent the useful work for a buyer is not watching the towers but keeping the paperwork and the payment triggers aligned with what the register certifies. The published Hillsedge plan attaches instalments to 30, 50, 70, 90, and 100 percent construction completion, and the June 2026 reading sits 4.45 points under the first of them, which puts these three steps in this cycle rather than the next one.
First, confirm that your construction linked instalments release into the project's registered escrow account; the Hillsedge escrow account page sets out what to check against the DLD record for project 3411 before any transfer leaves your side.
Second, read your own sale and purchase agreement against those five certified thresholds, because some instalments are date driven and others are milestone driven, and only the register decides when a milestone one becomes payable.
Third, if residency forms part of the plan, settle eligibility early through the Hillsedge Golden Visa eligibility guide, since the qualifying route differs before and after the title deed is issued at handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
Hillsedge is one plot inside a masterplan that has been handing over since 2018, which is unusual company for a project sitting at 25.55%. These three pages set the reading in that context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Hillsedge at Dubai Hills Estate Construction Updates Frequently Asked Questions
Hillsedge stands at 25.55% construction progress, recorded at the RERA inspection of 06 June 2026 against DLD project 3411, which remains active in the register. The reading and its track sit in the inspection timeline above.
The 06 June 2026 inspection recorded 25.55%, a rise of 10.71 points from the previous reading of 14.84% carried in the same report. Enabling works were logged complete, substructure and foundations at advanced stages, and superstructure frames climbing on both towers. The full site report is in the June 2026 Hillsedge construction update.
The DLD-registered completion date for project 3411 is 31 January 2029, placing handover in the first quarter of 2029. From 25.55% on 06 June 2026, 74.45 percentage points remain across roughly thirty one months, and registered completion dates can be revised between inspection cycles.
DLD registration records 406 residential units within a total built-up area of 34,915.67 sq m: 204 one bedroom apartments and 202 two bedroom apartments, distributed between Tower A at nineteen floors, Tower B at eighteen, and the low rise Park Apartments block.
Construction started on site on 02 May 2025, five months after DLD project registration on 29 November 2024. The first published dated reading came thirteen months later, at 25.55% on 06 June 2026.
Across the whole build the pace averages about 1.9 percentage points per month, from the 02 May 2025 start to 25.55% on 06 June 2026. The 10.71 point gain from the earlier 14.84% reading cannot be converted into a monthly rate, because no inspection date is published against that earlier figure. Holding the registered date of 31 January 2029 implies about 2.3 points per month from here, as set out in the pace analysis above.
The 06 June 2026 report records enabling works complete, piling, substructure, and foundation works at advanced stages, superstructure frames rising at differing heights on Tower A and Tower B, and internal and MEP installation at an early stage. The shared podium is built as one basement, ground, podium level, and roof.
Hillsedge occupies plot 5412 in the Hadaeq Sheikh Mohammed Bin Rashid area, a central position within Dubai Hills Estate where its two towers and the Park Apartments block wrap the four zones of Hillside Park above one shared podium. Layouts and the masterplan position are covered in the Hillsedge project guide at Dubai Hills Estate.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Hillsedge at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.