DAMAC Properties · DAMAC Riverside
Lush at DAMAC Riverside Construction Updates
The Dated Register Record for 744 Townhouses in Dubai Investment Park 2
Lush at DAMAC Riverside reached 41.69% at the 26 August 2026 DLD register reading, with townhouse frames well advanced and finishes ahead of a Q4 2027 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Lush at DAMAC Riverside at a Glance
Lush at DAMAC Riverside is DAMAC Properties' townhouse project of 744 residential units in DAMAC Riverside, Dubai Investment Park 2, entered on the Dubai Land Department register as project 3169 on 17 July 2024. Construction started on 24 September 2024 against a registered completion date of 31 December 2027, a registered build window of about 39 months that closes inside DAMAC's Q4 2027 handover quarter. The cards below are the register anchors that frame the 41.69% recorded on 26 August 2026, when the rows of 4 and 5 bedroom homes had their frames well advanced and their finishes at an early stage.
3169
Active
24 September 2024
744 residential units
129,960.74 sq m
31 December 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Lush at DAMAC Riverside Construction Update Timeline
The Lush record holds two register readings so far: a previous inspection at 25.76%, which the register shows without a date, and 41.69% on 26 August 2026. Both sit after the 17 July 2024 registration and the 24 September 2024 construction start, with the 31 December 2027 registered completion still ahead. The track below places the two readings on the way to 100%, and the dated reading links to its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 41.69% | 26 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Lush at DAMAC Riverside Has Been Built
With one dated register reading, the Lush record supports arithmetic rather than a phase-by-phase pace. Two figures frame it, both as arithmetic and not a forecast:
- 24 Sep 2024 to 26 Aug 2026: construction start to the latest reading, 41.69 points over about 23 monthsAbout 1.81 points per month, average to date
- 26 Aug 2026 to 31 Dec 2027: 58.31 points remaining to the registered completion date, about 16 monthsAbout 3.61 points per month needed
Because the register shows the earlier 25.76% reading without a date, the Lush curve cannot yet be split into measured phases; the only rate available runs from the 24 September 2024 start to the 26 August 2026 reading. Set against the second figure, a faster average than to date would be needed to reach 100% by the registered completion date of 31 December 2027. Finishing stages can move differently from structural stages, and on rows of G+1+R townhouses the envelope and finishes are spread across many low-rise homes rather than stacked floor by floor. For an end user planning a Q4 2027 move and an investor timing an exit, the next dated reading is the one that turns this average into a measured rate, so buyers confirm the schedule with DAMAC and watch the next register readings.
Get the Next Inspection Figure First
Tell me you are tracking Lush at DAMAC Riverside and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Lush at DAMAC Riverside
A register percentage reads differently once you know what is being built. The full project guide covers the townhouses this record is tracking toward handover:

Lush at DAMAC Riverside: 744 Townhouses With Parking for Two Cars
Lush at DAMAC Riverside is a DAMAC Properties project of 744 four and five bedroom townhouses inside the DAMAC Riverside community.
View the Lush at DAMAC Riverside Project GuideConsidering an Under-Construction Purchase?
Availability at Lush changes between inspection cycles. If the record on this page is what brought you here, ask me what is currently offered and how the payment plan applies at this stage of the build.
Ask About Remaining Availability on WhatsAppStage Record
Lush at DAMAC Riverside Build Stages, Mapped to the Inspections
Each stage below is pinned to the Lush register dates and to what the 26 August 2026 inspection notes say about it, so the record shows which work on the 744 townhouses is logged as largely done at 41.69% and which is only opening up.
Registration and Site Start
Project 3169 entered the DLD register on 17 July 2024, and construction on the townhouse site started on 24 September 2024.
Enabling Works and Foundations
Logged as substantially completed at the 26 August 2026 inspection, with site mobilisation still noted as ongoing that day.
Substructure and Superstructure
Progressing at advanced stages at 41.69%, up from the register's previous reading of 25.76%, which carries no date.
MEP, Infrastructure and Envelope
Internal works, infrastructure and MEP stood at different stages on 26 August 2026, while the external envelope had only begun.
Finishes, External Works and Handover
Finishes and external works were at early stages in August 2026; registered completion is 31 December 2027, handover Q4 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Lush at DAMAC Riverside's own record.
Buyer Position
Tracking Your Position at Lush at DAMAC Riverside
This page is one of four project resources that together cover a Lush at DAMAC Riverside purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Lush at DAMAC Riverside Construction Updates
This page: the dated DLD register record for Lush, from its September 2024 start to handover.

Lush at DAMAC Riverside Golden Visa: 4 and 5 Bedroom Townhouses Qualify
Lush at DAMAC Riverside, a DAMAC Properties townhouse project in Dubai Investment Park 2, qualifies at both bedroom types.
Read the Lush at DAMAC Riverside Golden Visa Guide
Lush at DAMAC Riverside Escrow Account at Emirates NBD
Lush at DAMAC Riverside, DLD project 3169, escrows 744 residential units with Emirates NBD and read 41.69% certified in August 2026.
Verify the Lush at DAMAC Riverside Escrow AccountApproaching Handover
Between 41.69% and Handover: What Lush at DAMAC Riverside Buyers Should Do Now
At 41.69%, with the townhouse frames well advanced and finishes still at an early stage, Lush sits in the part of the build where the 55% construction-period share of DAMAC's published plan is paid, as scheduled in each buyer's SPA. Those payments fall due before the Q4 2027 handover rather than at it, so the three checks below belong before each instalment, not after.
First, check that every construction-stage payment goes to the Emirates NBD escrow account registered for project 3169; the Lush at DAMAC Riverside escrow account page shows how to confirm it before you transfer.
Second, if residency matters to your purchase, work through the Lush at DAMAC Riverside Golden Visa guide: the 4 bedroom entry price of AED 2.28M ≈ USD 619K already sits above the AED 2M ≈ USD 545K property threshold, and the guide explains how timing works for an under-construction purchase.
Third, follow the register as it moves: the Lush August 2026 inspection notes set the baseline, and the next dated reading is the first that will let this page measure a real pace between two inspections.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Riverside Structure
A build record reads best beside what surrounds it. These three pages place the Lush register record in its community, its resale market and its developer context:

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Lush at DAMAC Riverside Construction Updates Frequently Asked Questions
Lush at DAMAC Riverside, project 3169 on the Dubai Land Department register, is active and under construction, with 41.69% recorded at the 26 August 2026 inspection. That day's RERA report gives the main contract as progressing, the townhouse substructure and superstructure at advanced stages, and finishes at early stages. The full dated record is in the Lush inspection timeline above.
Two readings appear on the register for Lush at DAMAC Riverside: a previous inspection at 25.76%, shown without a date, and the current 41.69% recorded on 26 August 2026. Only the August reading is dated, so it forms the single row of the timeline table, and its site notes are set out in the Lush August 2026 construction update.
Lush at DAMAC Riverside has averaged about 1.81 percentage points per month between its 24 September 2024 construction start and the 41.69% reading of 26 August 2026. As arithmetic, not a forecast, reaching 100% by the 31 December 2027 registered completion date would take about 3.61 points per month over the remaining 58.31 points, a faster average than to date; finishing stages can move differently from structural stages. The working is in the Lush pace analysis above.
DAMAC schedules handover of Lush at DAMAC Riverside for Q4 2027, and the DLD register for project 3169 carries 31 December 2027 as its registered completion date, the last day of that quarter. The two dates agree as of the 26 August 2026 reading of 41.69%; a registered date can be revised on the register, and this page records any change when a newer reading is published.
The DLD register lists 744 residential units for Lush at DAMAC Riverside, project 3169, offered as 4 Bedroom Townhouses from AED 2.28M ≈ USD 619K and 5 Bedroom Townhouses at AED 3.80M ≈ USD 1.03M. That count stood on the register at the 26 August 2026 reading, when construction was recorded at 41.69%.
The RERA inspection report of 26 August 2026 describes Lush at DAMAC Riverside as G+1+R townhouses, shorthand for a ground floor, one upper floor and a roof level, built with a concrete structure and blockwork and finished inside and out. On that date, with progress at 41.69%, the structure stood at advanced stages while the external envelope and finishes were at early stages.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Lush at DAMAC Riverside construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.