Marina Views recorded 7.09% construction progress at its 5 May 2026 RERA inspection, an early reading that fixes the start line for three towers beside the marina.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Marina Views at Rashid Yachts & Marina at a Glance
Marina Views is a 545-residence development on plot 504 at Madinat Dubai Almelaheyah, registered with the Dubai Land Department as project 3172 and built as three buildings carrying twenty two, twenty and nineteen residential floors above podium level. Just over sixteen months separate the 18 December 2024 construction start from the 7.09% certified on 5 May 2026, and the anchors below are the registered figures behind that reading. One detail only the registration carries: the register counts 554 units for this project, the 545 residences plus nine retail units on the ground floor, which is why a search of the public record returns a number the sales material never uses.
3172
Active
18 December 2024
545 residences
60,164.73 sq m
31 December 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Marina Views at Rashid Yachts & Marina Construction Update Timeline
Two readings sit in this record so far. The Dubai Land Department dashboard carries a previous inspection at 6.3% and the certified reading of 7.09% taken on 5 May 2026, a movement of 0.79 points, and only the 5 May figure carries a published date, so the earlier dot on the track below is plotted without a month label rather than given one it does not have. The narrowness of that spread is the record telling the truth about the stage: at 7.09% the value being certified is still below ground, in piling and foundations, not in visible floors. The table links the full monthly update behind the current reading.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 7.09% | 5 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Marina Views at Rashid Yachts & Marina Has Been Built
On a record this young the useful comparison is not between two inspections but between what has been certified since the diggers arrived and what the registered programme still has to deliver. Three measurements frame the Marina Views pace:
- Dec 2024 to May 2026: enabling, piling and foundations, groundbreaking to 7.09%About 0.4 points per month
- Previous recorded reading to 5 May 2026: 6.3% to 7.09%Plus 0.79 points certified
- May 2026 to 31 December 2028: 92.91 points left to certifyAbout 2.9 points per month implied
The shape here is the flat opening of a substructure programme, not a stall. Marina Views has been on site for just over sixteen months and has certified 7.09% of its value, because piling rigs and foundation pours convert a great deal of money and programme time into very few percentage points; the curve stays close to the axis until floor plates for Tower 1, Tower 2 and Tower 3 start rising, and from that reading onward the same monthly effort registers in points rather than fractions. The 0.79 points between the previous reading and 5 May 2026 belong to that part of the curve and should be read as such. For an end user, the practical meaning is that 31 December 2028 still has a normal amount of runway in front of it at roughly 2.9 points a month; for an investor, the reading worth waiting for is the first one that breaks out of fractions, because that is the inspection which confirms the substructure is behind this project rather than in front of it.
Get the Next Inspection Figure First
Tell me you are tracking Marina Views at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Marina Views at Rashid Yachts & Marina at Mina Rashid
A percentage only means something next to what it is building. The project guide sets out the residences, the amenity platform and the marina position that the 7.09% is working toward:

Marina Views at Rashid Yachts & Marina, Three Towers at the Water
Marina Views at Rashid Yachts & Marina spreads 545 Emaar apartments over three towers, with nine ground floor shops.
View the Marina Views at Rashid Yachts & Marina Project GuideConsidering an Early-Stage Entry?
Availability at Marina Views shifts as the build moves from foundations toward structure. If the record on this page is what brought you here, ask me what is released right now rather than assuming the launch position still stands.
Ask About Remaining Availability on WhatsAppStage Record
Marina Views at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is tied to the window it occupies in this project's own record, using the 18 December 2024 start, the 7.09% certified on 5 May 2026, and the construction-completion markers written into the launch payment schedule.
Site Activation and Mobilisation
From the 18 December 2024 construction start: site establishment and contractor mobilisation on plot 504 at Madinat Dubai Almelaheyah, before certified progress had begun to accumulate.
Enabling Works, Piling and Foundations
The 5 May 2026 inspection found mobilisation still ongoing, enabling works at an advanced stage, and piling and foundation work progressing, with the contract logged as Main Contract - Progressing.
Superstructure Across Three Towers
Cores and floor plates for Tower 1 at twenty residential levels, Tower 2 at twenty two and Tower 3 at nineteen: the phase in which certified progress stops moving in fractions of a point.
Facade, Amenity Platform and Retail Level
Enclosure of the three towers, the landscaped amenity platform above the podium, and the nine ground-floor retail units that the DLD registration records alongside the 545 residences.
Finishing, Commissioning and Handover
Apartment finishing, systems commissioning and final approvals across 545 residences, closing the 92.91 points that still separated Marina Views from completion at the May 2026 reading.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Marina Views at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Marina Views at Rashid Yachts & Marina
This page is one of four project resources that together cover a Marina Views at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marina Views at Rashid Yachts & Marina Construction Updates
This page: the certified inspection record for Marina Views, from 18 December 2024 groundbreaking to handover.

Marina Views at Rashid Yachts & Marina Golden Visa, 545 Residences
Three of four typologies at Marina Views at Rashid Yachts & Marina qualify individually; the 1 bedroom does not reach it.
Read the Marina Views at Rashid Yachts & Marina Golden Visa Guide
Marina Views at Rashid Yachts & Marina: A 554-Unit Escrow
Marina Views at Rashid Yachts & Marina takes 554 units into Emirates NBD escrow, DLD project 3172, 7.09% certified May 2026.
Verify the Marina Views at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 7.09% and Handover: What Marina Views at Rashid Yachts & Marina Buyers Should Do Now
At 7.09% the work being certified is below ground, which makes the decisions in front of a Marina Views buyer administrative rather than physical. The launch payment schedule of record ties its later instalments to construction-completion markers of 20%, 40%, 60% and 100%, so the distance between today's reading and those markers is precisely the window in which to get verification habits and paperwork in order. Certified readings arrive on the inspector's timetable rather than on notice, so each of the three steps below is worth completing before the next inspection is recorded, not after it.
First, confirm which certified milestone each remaining instalment is tied to. The Marina Views escrow account page sets out the Emirates NBD trust account holding funds for project 3172 and how releases follow verified progress rather than requests.
Second, if residency is part of the plan, settle eligibility now rather than at title stage. The Marina Views Golden Visa guide covers which purchase positions qualify and what the off-plan route asks for.
Third, follow the record itself. The Marina Views construction update for May 2026 carries the inspection detail behind the 7.09% figure, and every later certified reading is added to the timeline above as it is recorded.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
One project's inspection record only reads properly against the marina it sits in. These three pages place the 7.09% reading in its market, community and developer context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Marina Views at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Marina Views is an active Dubai Land Department project, number 3172, recorded at 7.09% construction progress at the RERA inspection of 5 May 2026, with progress status logged as Main Contract - Progressing. At that inspection mobilisation was ongoing, enabling works had reached an advanced stage, and piling and foundation work was progressing. The full reading history is in the inspection record above.
The 5 May 2026 inspection certified 7.09% construction progress, 0.79 points above the 6.3% carried as the previous recorded reading on the Dubai Land Department dashboard. Four photographs taken by the RERA inspector form part of that report as record evidence. The site detail behind the figure is set out in the full May 2026 inspection report for Marina Views.
Between the 18 December 2024 construction start and the 5 May 2026 inspection, Marina Views accumulated 7.09 percentage points across just over sixteen months, an average of about 0.4 points per month. That rate is characteristic of a substructure programme, where piling and foundations absorb time and cost while certifying very little percentage. Closing the remaining 92.91 points by the registered date of 31 December 2028 implies about 2.9 points per month. The month by month arithmetic is set out in the pace analysis above.
Construction officially started on 18 December 2024, just over five months after the project was registered with the Dubai Land Department on 4 July 2024. The earliest reading published on this site is the 7.09% certified on 5 May 2026; the 6.3% held on the dashboard as the previous inspection carries no published date, so it is plotted on the track above without one.
The registered completion date recorded with the Dubai Land Department for project 3172 is 31 December 2028, which agrees with the December 2028 handover given for the development. That date has not lapsed, and at 7.09% certified on 5 May 2026 roughly thirty two months of the registered programme remained. This page is updated as each further inspection is certified.
Marina Views comprises 545 residences across three buildings: Tower 1 with 179 units over twenty residential floors, Tower 2 with 193 units over twenty two, and Tower 3 with 173 units over nineteen. The Dubai Land Department register counts 554 units for the project in total, being those 545 residences plus nine retail units on the ground floor.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marina Views at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.