DAMAC Properties · DAMAC Riverside
Marine 2 at DAMAC Riverside Views Construction Updates
From Substructure to Q2 2028: The Register Record of a 358-Residence Building
Marine 2 at DAMAC Riverside Views recorded 12.02% at the 16 July 2026 inspection, an early reading setting the substructure-stage baseline for its Q2 2028 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Marine 2 at DAMAC Riverside Views at a Glance
Marine 2 is a single apartment building of 358 residences that DAMAC Properties is developing in DAMAC Riverside Views, the apartment district of DAMAC Riverside in Dubai Investment Park 2, and the Dubai Land Department tracks it under its own project number, 3373. Its record is still short: registration on 19 November 2024, a construction start on 29 January 2025, and one dated reading of 12.02% on 16 July 2026. Because the DLD's inspection report describes one ground-plus-three-podium-plus-14-floor residential building with a roof level, every figure on this page measures one structure, not an averaged multi-building phase.
3373
Active
29 January 2025
358 residences (G+3P+14+R building)
31,387.16 sq m
31 May 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Marine 2 at DAMAC Riverside Views Construction Update Timeline
One dated inspection anchors the Marine 2 record so far: 12.02% on 16 July 2026, which the register shows next to a previous reading of 6.02% that it does not date. Around those readings sit the registration on 19 November 2024, the construction start 71 days later on 29 January 2025, and, ahead, the registered completion date of 31 May 2028. The track places both readings on the way to 100%; the table row links the full July 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 12.02% | 16 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Marine 2 at DAMAC Riverside Views Has Been Built
Marine 2 has a single dated inspection, so no pace can yet be measured between two readings. What the register dates do allow is whole-build arithmetic, set out below and labelled as arithmetic, not a forecast:
- 29 Jan 2025 to 16 Jul 2026: average since the registered start, 0% to 12.02% over 533 days (arithmetic, not a forecast)About 0.68 points per month
- 16 Jul 2026 to 31 May 2028: rate implied by the registered completion date, 87.98 points over 685 days (arithmetic, not a forecast)About 3.85 points per month
- 6.02% (undated) to 12.02% (16 Jul 2026): the register gives no date for the earlier readingNo measured pace
With one dated reading, the Marine 2 record has a starting slope rather than a curve. The 12.02% of 16 July 2026 arrived 533 days after the registered start, at a point where that inspection found foundation and substructure work well advanced and the superstructure only beginning, so the first average mostly reflects groundwork for a G+3P+14+R frame. The higher figure tied to 31 May 2028 exists because the three podium levels, the 14 floors above them, the roof and the finishes all sit inside the 87.98 points still to be recorded. Neither number is a verdict: the registered date is DAMAC's filing with the DLD, and the first measured pace for this building will come when the next dated inspection is set against 16 July 2026. For an end user that pairing shows how quickly the floors begin to climb; for an investor it is the first hard evidence of how the distance to Q2 2028 is being covered.
Get the Next Inspection Figure First
Tell me you are tracking Marine 2 at DAMAC Riverside Views and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Marine 2 at DAMAC Riverside Views at DAMAC Riverside
The 12.02% reading of 16 July 2026 only means something next to what is being delivered. The project guide sets out the apartments and the community that Marine 2 buyers are tracking toward on this page:

Marine 2 at DAMAC Riverside Views: Apartments in the Apartment District
Marine 2 at DAMAC Riverside Views is a DAMAC Properties building of 358 one and two bedroom apartments in DAMAC Riverside.
View the Marine 2 at DAMAC Riverside Views Project GuideConsidering an Early-Stage Entry?
Which Marine 2 apartments are open changes as buyers commit through the construction cycles, and this page publishes no stock figure. If the record here is what brought you, ask me which 1 Bedroom and 2 Bedroom Apartments are available today.
Ask About Remaining Availability on WhatsAppStage Record
Marine 2 at DAMAC Riverside Views Build Stages, Mapped to the Inspections
Each stage below is pinned to Marine 2's own register dates rather than a textbook sequence: two stages have dated evidence so far, a third was only beginning on 16 July 2026, and the last two lie inside the 87.98 points still ahead of the building.
Registration and Construction Start
Project 3373 entered the DLD register on 19 November 2024, and the register records construction starting 71 days later, on 29 January 2025.
Enabling Works, Foundations and Substructure
At the 16 July 2026 inspection enabling works were complete, foundation and substructure work was well advanced and mobilisation was still under way, with the register at 12.02%.
Podium Levels and 14-Floor Superstructure
The same inspection recorded the superstructure at an early stage; the three podium levels and 14 floors of the G+3P+14+R frame are what the next dated readings will capture.
Block Work, Envelope and Building Services
Block work plus the interior and exterior finishes listed in the DLD project description all fall within the 87.98 points left after the 16 July 2026 reading.
Finishing, Completion and Handover
Final finishes and the handover of 358 residences, expected in Q2 2028, against the registered completion date of 31 May 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Marine 2 at DAMAC Riverside Views's own record.
Buyer Position
Tracking Your Position at Marine 2 at DAMAC Riverside Views
This page is one of four project resources that together cover a Marine 2 at DAMAC Riverside Views purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Marine 2 at DAMAC Riverside Views Construction Updates
This page: the dated DLD record for Marine 2, from its January 2025 start toward handover.

Marine 2 Golden Visa: Each Apartment Type Below the AED 2M Threshold
Marine 2 at DAMAC Riverside Views, a DAMAC Properties building, has no apartment type reaching the AED 2M threshold.
Read the Marine 2 at DAMAC Riverside Views Golden Visa Guide
Marine 2 Escrow: DLD Project 3373 at First Abu Dhabi Bank
Marine 2 at DAMAC Riverside Views escrows its 358 units at First Abu Dhabi Bank and read 12.02% in July 2026.
Verify the Marine 2 at DAMAC Riverside Views Escrow AccountApproaching Handover
Between 12.02% and Handover: What Marine 2 at DAMAC Riverside Views Buyers Should Do Now
At 12.02% on 16 July 2026, the next visible change at Marine 2 is the superstructure: the podium levels and 14 floors that the July inspection found only just beginning. With 87.98 points still to be recorded before the registered completion date of 31 May 2028, the three checks below belong at the start of a purchase and at every payment date, not in the weeks before handover.
First, before any deposit leaves your account, confirm that payments go to the First Abu Dhabi Bank trust account registered to project 3373; the Marine 2 escrow account page explains how to match it against the DLD record.
Second, if residency matters to your plans, read the Marine 2 Golden Visa page before choosing between the 1 Bedroom and 2 Bedroom Apartments, since neither reaches the AED 2M ≈ USD 545K property threshold on its own at its listed price.
Third, follow each dated reading as it is published; the Marine 2 July 2026 construction update holds the full record of the 16 July 2026 inspection, and the next one will give this building its first measured pace.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Riverside Structure
Marine 2 is one building inside a far larger DAMAC Riverside plan, so its 12.02% reading of 16 July 2026 reads best beside the community and the developer around it:

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Marine 2 at DAMAC Riverside Views Construction Updates Frequently Asked Questions
Marine 2 at DAMAC Riverside Views is an active DLD-registered project, number 3373, in early-stage construction: the register recorded 12.02% on 16 July 2026, with the main contract listed as progressing and foundations and substructure well advanced. That reading was 109 days old when this page was built, so a newer inspection may already be listed in the DLD register.
Marine 2 was registered with the DLD on 19 November 2024 and started construction on 29 January 2025, 71 days later. Its first dated reading, 12.02% on 16 July 2026, came 533 days after the start and sits 6.00 points above the register's previous figure of 6.02%, which carries no date. The full sequence is laid out in the inspection timeline above.
Q2 2028 is the expected handover for Marine 2, and 31 May 2028 is the completion date DAMAC registered with the DLD for project 3373; the registered date falls inside Q2 2028, so the two agree. Both lie in the future, 685 days after the 16 July 2026 reading for the registered date, and this page's record is updated whenever a new inspection is recorded.
Marine 2 will hold 358 residences, listed as 1 Bedroom and 2 Bedroom Apartments, in a single G+3P+14+R building: a ground floor, three podium levels, 14 floors above them and a roof level, as described in the DLD inspection report of 16 July 2026. The DLD register lists the same 358 units for project 3373.
No pace can be measured yet at Marine 2, because 12.02% on 16 July 2026 is its only dated reading. What can be set out is arithmetic: 533 days separate the 29 January 2025 start from that reading, while 87.98 points remain over the 685 days to the registered completion date of 31 May 2028. The per-month figures for both spans are in the pace analysis above, labelled as arithmetic rather than a forecast.
Each new DLD inspection of project 3373 becomes a dated row and a dot on this page, added to the 16 July 2026 reading of 12.02%, and each gets its own monthly update page. The July 2026 page was the first; the full record for that inspection is in the July 2026 inspection record for Marine 2.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Marine 2 at DAMAC Riverside Views construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.