Riwa at Madinat Jumeirah Living by Meraas in Madinat Jumeirah Living construction updates cover image featuring a project rendering of residential buildings overlooking landscaped lawns and flowering trees in Dubai - Presented by Tohid Fetrat

Meraas · Madinat Jumeirah Living

Riwa at Madinat Jumeirah Living Construction Updates

The Register Record for Three Buildings Between Al Wasl and Jumeirah Beach Roads

Riwa reached 12.52% in the DLD register on 20 July 2026, the first dated reading in a record that will follow three Meraas buildings to handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

12.52%Construction Progress
20 July 2026Latest RERA Inspection
244 residential unitsTotal Units
Project 3021DLD Registration

Construction Snapshot

Riwa at Madinat Jumeirah Living at a Glance

Riwa is the Meraas addition of 244 residences to Madinat Jumeirah Living, entered in the DLD register as project 3021 on 04 April 2024, with construction recorded as starting on 05 September 2024. Its record is still short: a single dated reading of 12.52% on 20 July 2026, preceded by an undated register reading of 6.49%. Because Riwa is three separate buildings of basement, ground, ten floors and roof rather than one tower, every percentage below blends the progress of three structures rising side by side at the inland end of the community.

DLD Project Number

3021

Project Status

Active

Construction Start

05 September 2024

Total Units

244 residential units

Total Built-Up Area

28,401.71 sq m

Registered Completion Date

Q3 2027 (developer handover)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Riwa at Madinat Jumeirah Living Construction Update Timeline

Two register readings make up Riwa's record so far: a previous inspection figure of 6.49% that the DLD register lists without a date, and 12.52% at the inspection of 20 July 2026, 6.03 points higher. The undated figure appears only as a dot on the track below; the July 2026 reading is the one table row, linked to its full monthly update with the RERA site findings for the three buildings.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202612.52%20 July 2026View the July 2026 update

Pace Analysis

How Fast Riwa at Madinat Jumeirah Living Has Been Built

With one dated reading and an undated one before it, Riwa's record cannot yet show a measured pace between two inspections. What it does support is arithmetic from the registered construction start, set against the Q3 2027 estimate:

  • 05 Sep 2024 to 20 Jul 2026: construction start to the latest reading, 0% to 12.52% over 683 daysAbout 0.55 points per month
  • 20 Jul 2026 to 30 Sep 2027: the remaining 87.48 points over 437 days to the end of Q3 2027About 6.01 points per month needed

Both rates use a 30-day month, and both are arithmetic, not a forecast. Set side by side, they show that the work left at Riwa would need a markedly faster monthly rate than the average logged since September 2024 if the Q3 2027 estimate is to hold. The 20 July 2026 RERA report adds the context that matters here: structure and MEP works were already running together with foundations across the three buildings, so the readings after July 2026 are the ones that will show which way the gap moves. For an end user timing a move, that makes Q3 2027 a date to confirm with Meraas rather than assume; for an investor reading delivery consistency, the next two or three register figures are the evidence to wait for.

Get the Next Inspection Figure First

Tell me you are tracking Riwa at Madinat Jumeirah Living and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Riwa at Madinat Jumeirah Living

A 12.52% reading only means something next to what is being built. The project guide covers the homes this record is tracking toward:

Riwa at Madinat Jumeirah Living by Meraas in Madinat Jumeirah Living project rendering of modern residential buildings with balconies, roadside landscaping and palm trees in Dubai - Presented by Tohid Fetrat

Riwa at Madinat Jumeirah Living, Beside the Sports Park

Riwa at Madinat Jumeirah Living is a Meraas project of 244 units in three buildings, apartments plus four bedroom penthouses.

View the Riwa at Madinat Jumeirah Living Project Guide

Considering an Early-Stage Entry?

Buying at Riwa now means committing while most of the three buildings are still to be recorded. Availability shifts as the build moves forward, so if the record on this page is what brought you here, ask me which layouts are still open before you decide.

Ask About Remaining Availability on WhatsApp

Stage Record

Riwa at Madinat Jumeirah Living Build Stages, Mapped to the Inspections

Each stage below is pinned to what Riwa's own record shows, from the April 2024 registration to the single dated reading of 20 July 2026; the stages still ahead are marked as unrecorded rather than given dates the record does not contain.

Apr 2024 to Sep 2024

Registration and Site Start

Riwa entered the DLD register as project 3021 on 04 April 2024; the register then records construction starting on 05 September 2024, the date every rate on this page is measured from.

Current PhaseSep 2024 onward, 12.52% at last reading

Enabling Works and Foundations

The RERA report of 20 July 2026 found enabling and foundation works still progressing beneath the three buildings, each with a basement level, as the register read 12.52%.

Under way by Jul 2026

Structure to Roof Across Three Buildings

Structural and MEP works were already progressing at the July 2026 inspection, rising toward ground, ten floors and roof: Building 1 with 86 units, Buildings 2 and 3 with 79 each.

Not yet recorded

Facades, Interiors, and Landscaped Grounds

Still ahead in the record: the facades, apartment interiors, pool, gym and landscaped gardens planned for Riwa, which later register readings will capture as they progress.

Toward Q3 2027 (estimated)

Finishing, Commissioning, and Handover

The closing stretch of the 87.48 points that remained after 20 July 2026, ending at handover, which Meraas estimates for Q3 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Riwa at Madinat Jumeirah Living's own record.

Buyer Position

Tracking Your Position at Riwa at Madinat Jumeirah Living

This page is one of four project resources that together cover a Riwa at Madinat Jumeirah Living purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Riwa at Madinat Jumeirah Living by Meraas in Madinat Jumeirah Living construction updates cover image featuring a project rendering of residential buildings overlooking landscaped lawns and flowering trees in Dubai - Presented by Tohid Fetrat
You Are Here

Riwa at Madinat Jumeirah Living Construction Updates

This page: every dated DLD register reading for Riwa project 3021, from construction start to handover.

Riwa at Madinat Jumeirah Living by Meraas in Madinat Jumeirah Living Golden Visa concept graphic featuring a gold card beside rendered residential buildings, palm trees and planted surroundings in Dubai - Presented by Tohid Fetrat

Riwa at Madinat Jumeirah Living Golden Visa: Four Unit Types

Riwa at Madinat Jumeirah Living, Meraas's 244-residence development, qualifies at every type, 1 bedroom to 4 bedroom penthouse.

Read the Riwa at Madinat Jumeirah Living Golden Visa Guide
Riwa at Madinat Jumeirah Living by Meraas in Madinat Jumeirah Living escrow account concept graphic featuring a visible shield and padlock above a rendered residential building exterior and landscaped street in Dubai - Presented by Tohid Fetrat

Riwa at Madinat Jumeirah Living: The Escrow Account on Record

Riwa at Madinat Jumeirah Living escrows 244 units at First Abu Dhabi Bank under DLD project 3021, 12.52% certified July 2026.

Verify the Riwa at Madinat Jumeirah Living Escrow Account

Approaching Handover

Between 12.52% and Handover: What Riwa at Madinat Jumeirah Living Buyers Should Do Now

At 12.52% on 20 July 2026, most of Riwa's three buildings are still to be recorded, so the useful work for a buyer now is protecting payments and keeping the record in view, not preparing for keys. Every dated instalment on the developer's launch schedule before handover has already fallen due, which makes the schedule in your sale and purchase agreement the one that counts, so the three checks below belong before your next payment, not after the next reading.

First, match every payment against the account named on the Riwa escrow account page, so money toward the price goes only into the First Abu Dhabi Bank account registered to project 3021.

Second, if residency is part of the plan, settle eligibility early through the Riwa Golden Visa guide, since the timing of your payments and title deed shapes the application path.

Third, follow the register readings as they land: the Riwa July 2026 construction update sets the 12.52% baseline, and every later reading joins the inspection timeline on this page.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Madinat Jumeirah Living Structure

A build record reads better with its surroundings. These three pages place Riwa's 12.52% reading of 20 July 2026 in the context of the community market, the masterplan, and the developer building it:

Aerial view of Madinat Jumeirah Living properties for sale in Dubai showing residential buildings, landscaped surroundings and the Burj Al Arab nearby, Presented by Tohid Fetrat

Madinat Jumeirah Living: MJL Nourelle Residences Opposite Burj Al Arab

Madinat Jumeirah Living, a freehold Meraas apartment community in Umm Suqeim 3, lists MJL Nourelle residences on a 20/55/25 payment plan.

See Madinat Jumeirah Living Properties for Sale
Aerial masterplan view of Madinat Jumeirah Living community in Dubai showing residential buildings, landscaped areas and the Burj Al Arab nearby, Presented by Tohid Fetrat

Madinat Jumeirah Living: Low-Rise Freehold Apartments Opposite Burj Al Arab

Madinat Jumeirah Living has low-rise apartments in Umm Suqeim, an air-conditioned footbridge to the Souk and Burj Al Arab views.

Explore the Madinat Jumeirah Living Community
Meraas developer Dubai – luxury residential towers including Atélis, Jumeirah Residences, The Edit, Verve City Walk, and Bluewaters Bay

Meraas: Lifestyle Destinations From City Walk to Port de La Mer

Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.

View the Meraas Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Riwa at Madinat Jumeirah Living Construction Updates Frequently Asked Questions

Riwa, DLD project 3021, is an active project in its enabling and foundations stage, read at 12.52% in the DLD register on 20 July 2026. The RERA progress report for that inspection lists the status as Main Contract, Progressing, with structure and MEP works already running alongside the groundwork. The stage-by-stage view is in the stage record above.

Two. The register shows a previous inspection reading of 6.49%, which carries no date, and 12.52% at the inspection of 20 July 2026, a difference of 6.03 points. Only the dated reading has a row in the timeline; the RERA findings for that inspection are in the Riwa construction update for July 2026.

Q3 2027 is the handover estimate Meraas gives for Riwa. The register record for project 3021 does not show a completion date, so this page works from the developer estimate and sets it against the 12.52% register reading of 20 July 2026; the record here is updated as each new reading is published.

Riwa's 244 residential units sit in three buildings, each planned as basement, ground, ten floors and roof (B+G+10+R): Building 1 holds 86 units and Buildings 2 and 3 hold 79 each, according to the RERA progress report of 20 July 2026. The mix covers 1, 2 and 3 bedroom apartments and 4 bedroom penthouses.

Averaged from the 05 September 2024 construction start, the 12.52% recorded on 20 July 2026 works out to about 0.55 points per 30-day month over 683 days. Completing the remaining 87.48 points by 30 September 2027, the final day of the Q3 2027 estimate, would take about 6.01 points per 30-day month. Both figures are arithmetic, not a forecast; the undated 6.49% reading cannot yield a measured pace between inspections, and the workings sit in the pace analysis above.

The DLD register records Riwa's construction start as 05 September 2024, after the project was registered on 04 April 2024. The first dated reading on this page's record followed on 20 July 2026, at 12.52%.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Riwa at Madinat Jumeirah Living construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status