Ocean Cove by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of a landscaped courtyard lawn with trees pathways and residential buildings in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina

Ocean Cove at Rashid Yachts & Marina Construction Updates

One Certified Reading, Two Buildings, and the Road to August 2028

Ocean Cove reached 17.93% construction at its 14 April 2026 RERA inspection, the earliest dated reading on record for Emaar's two waterfront buildings at Mina Rashid.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

17.93%Construction Progress
14 April 2026Latest RERA Inspection
233 ResidencesTotal Units
Project 3173DLD Registration

Construction Snapshot

Ocean Cove at Rashid Yachts & Marina at a Glance

Ocean Cove is Emaar's 233-residence development on plot 500 at Madinat Dubai Almelaheyah, carried on the Dubai Land Department register as project 3173 and held there under MINA RASHID PROPERTIES L.L.C, developer number 1275. Registration closed on 12 July 2024, construction started on 28 October 2024, and the register's latest certified reading is the 17.93% logged on 14 April 2026. What makes this record read differently from a tower project is its shape: the 233 units are split between a G+9 building of 154 units and a G+7 building of 79 units, so every percentage below is the combined output of two structures rather than one rising core.

DLD Project Number

3173

Project Status

Active

Construction Start

28 October 2024

Total Units

233 Residences

Total Built-Up Area

24,164.94 sq m

Registered Completion Date

31 August 2028

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Ocean Cove at Rashid Yachts & Marina Construction Update Timeline

This record holds one dated reading so far: 17.93% construction progress, certified at the inspection of 14 April 2026 and carried on the register for project 3173. The same monitoring file reports the preceding inspection at 9.57% without publishing its date, so the 8.36-point gain between the two readings is on record while the interval it covers is not. The track below is therefore plotted from a single certified point, and the table row links the full April 2026 update behind it.

Inspection MonthConstruction ProgressInspection DateFull Update
April 202617.93%14 April 2026View the April 2026 update

Pace Analysis

How Fast Ocean Cove at Rashid Yachts & Marina Has Been Built

A single percentage says where a project stands; the intervals around it say how it is moving. Ocean Cove's record supports three measurements, two looking back and one looking forward:

  • Oct 2024 to Apr 2026: construction start to the certified 17.93% readingAbout 1.0 point per month
  • Preceding undated inspection to Apr 2026: structural phase, 9.57% to 17.93%A recorded gain of 8.36 points
  • Apr 2026 to the registered completion date of 31 August 2028About 2.9 points per month required

Two of those three figures are history and one is a test. The 1.0 point per month averaged since the 28 October 2024 start is the profile a two-building project takes while the work is still below and barely above ground, and the April monitoring notes confirm it: enabling works, piling and foundations are signed off as completed, and those are the months that consume time without moving a percentage far. The 8.36-point step up to 17.93% is the first evidence of that changing, because those points were earned by structure, internal works and MEP running in parallel rather than by groundworks. The forward figure is the one to hold on to. Reaching 100% by the registered date of 31 August 2028 asks for roughly 2.9 points a month from the April reading onward, close to three times the pace of the first year and a half. That step up is normal for a build entering its structural climb, and it is also the benchmark every future inspection on this page should be read against: for an end user it is the difference between an August 2028 handover and a later one, and for an investor it is the cleanest single test of whether Emaar is holding the schedule it registered.

Get the Next Inspection Figure First

Tell me you are tracking Ocean Cove at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Ocean Cove at Rashid Yachts & Marina at Mina Rashid

A build percentage only means something next to what is being delivered. The project guide covers the residences this record is tracking toward:

Ocean Cove at Rashid Yachts & Marina by Emaar aerial view of landscaped courtyard with swimming pool residential buildings and pathways in Dubai - Presented by Tohid Fetrat

Ocean Cove at Rashid Yachts & Marina, Around a Courtyard Pool

Ocean Cove at Rashid Yachts & Marina places 233 Emaar apartments in two low buildings around a landscaped courtyard.

View the Ocean Cove at Rashid Yachts & Marina Project Guide

Considering an Early-Stage Entry?

Availability at Ocean Cove shifts as the build clears each certified checkpoint. If the record on this page is what brought you here, ask me which layouts are still open before the next inspection is recorded.

Ask About Remaining Availability on WhatsApp

Stage Record

Ocean Cove at Rashid Yachts & Marina Build Stages, Mapped to the Inspections

Each stage below is tied to the window it occupies in Ocean Cove's own record, using the dates on the DLD file for project 3173 and the construction-completion checkpoints written into the launch payment schedule, so you can see what the project has cleared and what certifies the next move.

From 28 Oct 2024

Site Activation and Enabling Works

Construction started on 28 October 2024 on plot 500 at Madinat Dubai Almelaheyah. The April 2026 monitoring notes list enabling works as completed.

Closed out before Apr 2026

Piling and Foundations

Both buildings' loads were taken into the ground before the first dated reading: piling and foundation works are recorded as completed at the 14 April 2026 inspection.

Current PhaseApr 2026 at 17.93%

Structure, Internal Works and MEP

The 14 April 2026 file records structure works, internal works and MEP progressing together across the G+9 building of 154 units and the G+7 building of 79 units.

20% to 60% completion checkpoints

Enclosure, Facade and Fit-Out

The launch payment schedule sets certified checkpoints at 20%, 40% and 60% construction completion, the three readings that will mark this project's climb from structure to enclosed, fitted buildings.

Toward 100% by 31 Aug 2028

Finishing, Commissioning and Handover

Apartment finishing, systems commissioning and courtyard landscaping close the remaining 82.07 points to the registered completion date of 31 August 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ocean Cove at Rashid Yachts & Marina's own record.

Buyer Position

Tracking Your Position at Ocean Cove at Rashid Yachts & Marina

This page is one of four project resources that together cover a Ocean Cove at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ocean Cove by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of a landscaped courtyard lawn with trees pathways and residential buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Ocean Cove at Rashid Yachts & Marina Construction Updates

This page: the certified inspection record for Ocean Cove, from the October 2024 start to handover.

Ocean Cove by Emaar Properties in Rashid Yachts & Marina Golden Visa concept with a Golden Visa card above a landscaped lawn and residential buildings in Dubai - Presented by Tohid Fetrat

Ocean Cove at Rashid Yachts & Marina Golden Visa in Two Blocks

Ocean Cove at Rashid Yachts & Marina, 233 Emaar residences in two blocks, qualifies at 2 and 3 bedrooms, not 1.

Read the Ocean Cove at Rashid Yachts & Marina Golden Visa Guide
Ocean Cove by Emaar Properties in Rashid Yachts & Marina escrow account protection concept with shield and padlock icons above a landscaped residential courtyard and private terrace in Dubai - Presented by Tohid Fetrat

Ocean Cove at Rashid Yachts & Marina: The Escrow Record

Ocean Cove at Rashid Yachts & Marina is DLD project 3173: Abu Dhabi Commercial Bank escrow, 17.93% certified April 2026.

Verify the Ocean Cove at Rashid Yachts & Marina Escrow Account

Approaching Handover

Between 17.93% and Handover: What Ocean Cove at Rashid Yachts & Marina Buyers Should Do Now

In this band the visible work is vertical structure rather than finishes, so the obligations that matter to a buyer are financial rather than physical. Ocean Cove launched on an 80/20 schedule of nine instalments whose later payments are written against certified construction percentages, which makes a recorded inspection the trigger rather than the news. The next construction-completion checkpoint on that schedule sits at 20%, and the reading certified on 14 April 2026 is 17.93%, so it is points away rather than years. The three steps below belong in that window.

First, confirm how your instalments are released. The Ocean Cove escrow account page sets out the project 3173 trust account at Abu Dhabi Commercial Bank and why a certified percentage, rather than a request, is what moves money out of it.

Second, hold the launch schedule against the record on this page. Its later instalments were written against 20%, 40%, 60% and 100% construction completion, so each new inspection tells you which checkpoint has actually been cleared; the Ocean Cove at Rashid Yachts & Marina project guide carries the full schedule.

Third, if residency is part of the plan, settle eligibility now rather than near handover, because the qualifying route depends on purchase value and on when the title is issued. The Golden Visa eligibility guide for Ocean Cove covers both.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

A build record is one half of the picture; the other half is what is rising around it. These three pages place the 17.93% recorded at Ocean Cove on 14 April 2026 in its market, community, and developer context:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Ocean Cove at Rashid Yachts & Marina Construction Updates Frequently Asked Questions

Ocean Cove is an active DLD-registered project, number 3173, recorded at 17.93% construction progress at the inspection of 14 April 2026, with its RERA progress status listed as Main Contract - Progressing. The full record is in the inspection timeline above.

The 14 April 2026 inspection certified 17.93% construction progress, an 8.36-point gain on the 9.57% carried from the preceding inspection. Against that reading, the monitoring notes place enabling works, piling and foundations in the completed column, and structure, internal works and MEP in the progressing column. The site report is published in the Ocean Cove April 2026 construction update.

Ocean Cove is in its structural stage. At the 17.93% reading of 14 April 2026 the groundworks stages were closed out, and structure, internal works and MEP were running in parallel across a G+9 building of 154 units and a G+7 building of 79 units. Each stage is mapped to its window in the stage record above.

Construction started on 28 October 2024, following project registration on 12 July 2024. From that start to the 14 April 2026 reading of 17.93%, the record averages about 1.0 percentage point per month, the expected profile for a period dominated by enabling works, piling and foundations.

Ocean Cove comprises 233 residences in two buildings: Building 1 at G+9+Roof with 154 units, and Building 2 at G+7+Roof with 79 units, on plot 500 at Madinat Dubai Almelaheyah. The apartments are one, two and three bedroom layouts.

The DLD-registered completion date for project 3173 is 31 August 2028, and that date has not lapsed. From the 17.93% certified on 14 April 2026, closing the remaining 82.07 points by then implies an average of about 2.9 percentage points per month, and this page's record is updated as each inspection is recorded.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ocean Cove at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.