Emaar · Dubai Creek Harbour
Palace Residences Creek Blue Construction Updates
The Certified Inspection Record for a Creek-Facing Palace Tower
Palace Residences Creek Blue recorded 20.52% construction at its 09 June 2026 RERA inspection, the first certified reading published for this Creek-facing Emaar tower.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Residences Creek Blue at a Glance
Palace Residences Creek Blue is Emaar's 512-residence Palace branded tower on plot 278 in Al Khairan First, the Creek Beach side of Dubai Creek Harbour. Twenty-two months separate the 01 August 2024 construction start from the 20.52% recorded at the 09 June 2026 inspection, and the figures below are the DLD-registered anchors behind that reading. Because the register describes the building as 1B+G+2P+50F+Roof, almost every point still to be certified here is vertical work on a fifty floor tower rather than ground works, which is what makes a single-reading record worth following closely.
3147
Active
01 August 2024
512 residential units
49,745.60 sq m
31 March 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Residences Creek Blue Construction Update Timeline
One certified inspection stands in this record so far: 09 June 2026 at 20.52%, up 3.78 points on the 16.74% held as the previous reading against project 3147. The register publishes that earlier percentage without its date, so the track below carries it as a position rather than a month, and the table row links the full update behind the June 2026 figure. Each new inspection is added here as it is entered against the project.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 20.52% | 09 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Palace Residences Creek Blue Has Been Built
With one certified reading on the board, the useful pace question is not how the curve bends but what the first 20.52% cost in time. Two spans can be measured from the record as it stands:
- Aug 2024 to Jun 2026: enabling, piling and early structure, 0% to 20.52%About 0.9 points per month
- Previous reading to 09 Jun 2026: superstructure cycle, 16.74% to 20.52%A gain of 3.78 points
Twenty-two months of registered construction time sit behind the 20.52% certified on 09 June 2026, which averages out at roughly nine tenths of a point per month. That average is not the tower's cruising speed. On a building registered as 1B+G+2P+50F+Roof the opening stretch is dominated by work that consumes months and certifies slowly: excavation, piling and the podium levels underneath the first residential floor, all of which the June 2026 notes confirm are now closed out or in hand. The 3.78 points added in the cycle ending on that inspection is the more informative number, because it was earned once vertical structure started moving, and it cannot yet be turned into a rate because the register publishes the 16.74% reading without a date. For an investor pricing the runway to the 40% construction completion instalment, and for an end user counting cycles toward a Q1 2029 handover, the figure that matters next is whether the following reading holds that superstructure step or beats it.
Get the Next Inspection Figure First
Tell me you are tracking Palace Residences Creek Blue and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Residences Creek Blue at Dubai Creek Harbour
A certified percentage is only half a decision; the other half is what the 512 residences behind it actually are. The project guide carries the layouts, prices and payment structure this record is tracking toward:

Palace Residences Creek Blue Project Guide
Layouts and sizes across 512 Palace branded one, two and three bedroom residences, the amenity podium, the Creek Beach plot position, and the milestone payment plan that runs to 2029.
View the Palace Residences Creek Blue Project GuideConsidering an Entry While the Structure Rises?
Entry here starts from AED 1.87M ≈ USD 509K, with most of the price still spread across instalments tied to certified construction milestones through to 2029. Availability shifts between inspection cycles, so ask me what sits on the current developer list before the Creek-facing stacks thin out.
Ask About Remaining Availability on WhatsAppStage Record
Palace Residences Creek Blue Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to what the DLD record and the 09 June 2026 inspection notes actually confirm for this tower. With one published reading, the windows are set by the 01 August 2024 construction start, the 20.52% certified in June 2026, and the milestone markers written into the payment plan, so the work already behind the project stays visibly separate from the work the percentage still has to pay for.
Site Activation and Enabling Works
The DLD record opens this build on 01 August 2024 on plot 278 in Al Khairan First, the period when the site was activated for the enabling package ahead of piling.
Piling and Substructure
The 09 June 2026 inspection notes record enabling works and piling as completed, so the substructure carrying a fifty floor tower was already behind the project when the 20.52% figure was certified.
Superstructure Above the Podium
Structure works were progressing at site on 09 June 2026 with main contract mobilization ongoing, lifting a building registered as 1B+G+2P+50F+Roof up through its podium levels.
Vertical Structure to the Next Milestone
The developer schedule places its fifth instalment at 40% construction completion, and on this tower it is the floor by floor structure package that carries the certified percentage there.
Envelope, Fit-Out and Handover
Facade, building services and interior fit out across 512 residences carry the remaining 79.48 points to the 31 March 2029 completion date registered with the DLD.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Residences Creek Blue's own record.
Buyer Position
Tracking Your Position at Palace Residences Creek Blue
This page is one of four project resources that together cover a Palace Residences Creek Blue purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Residences Creek Blue Construction Updates
This page: every certified RERA reading for project 3147, kept in one record until handover.

Palace Residences Creek Blue Golden Visa
See which unit tiers at Palace Residences Creek Blue clear the Golden Visa residency threshold.
Read the Palace Residences Creek Blue Golden Visa Guide
Palace Residences Creek Blue Escrow Account
Check the project 3147 trust account at Abu Dhabi Commercial Bank before each milestone instalment.
Verify the Palace Residences Creek Blue Escrow AccountApproaching Handover
Between 20.52% and Handover: What Palace Residences Creek Blue Buyers Should Do Now
At 20.52% the money still ahead of you is larger than the money behind you, which makes this the window where verification matters more than anticipation. Instalments on this project are pegged to certified construction percentages rather than to the calendar dates printed beside them, so it is the next reading, not the plan, that decides when your money is called, and the three steps below belong in the cycle you are in now.
First, confirm that every instalment routes only to the DLD-registered escrow account for project 3147; the Palace Residences Creek Blue escrow account page covers the trust account held with Abu Dhabi Commercial Bank and how releases follow certified progress.
Second, read each new figure against your own schedule rather than the marketing timeline; the Palace Residences Creek Blue June 2026 construction update sets out what the 20.52% reading covers and which instalment marker it clears.
Third, if your tier may qualify for residency, settle eligibility early through the Palace Residences Creek Blue Golden Visa page, since the application path is far easier to plan before the title deed timeline begins.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
A certified percentage tells you how far one tower has come. These three pages set the June 2026 reading against the district around the plot, the developer delivering it, and the stock competing with it:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour Community Overview
Read the Dubai Creek Harbour guide: Emaar's 5.5 km² waterfront masterplan with Creek Beach, marina living, parks and skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties Developer Profile
Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Residences Creek Blue Construction Updates Frequently Asked Questions
Palace Residences Creek Blue is an active DLD-registered project, number 3147, recorded at 20.52% construction progress at the RERA inspection of 09 June 2026. Every published cycle is kept in the inspection timeline on this page.
The 09 June 2026 inspection recorded 20.52%, a gain of 3.78 points on the 16.74% carried as the previous reading in the DLD register for project 3147. That visit logged enabling works and piling as completed and structure works progressing at site, and the whole visit is written up in the full June 2026 inspection report for Palace Residences Creek Blue.
The DLD register carries 31 March 2029 as the registered completion date for project 3147, a date that had not lapsed at the 09 June 2026 inspection, with 79.48 percentage points still to be certified between that reading and 100%. Handover is published as Q1 2029 on the project guide, and this record is republished each time a new inspection percentage is entered against the project.
DLD registration records show 512 residential units across one, two and three bedroom layouts, with a total built-up area of 49,745.60 sq m in a building registered as 1B+G+2P+50F+Roof: one basement level, ground, two podium levels, fifty floors and a roof.
Construction start is registered as 01 August 2024, roughly twenty-two months before the first certified reading published here, the 20.52% recorded on 09 June 2026. Averaged across enabling, piling and early structure that is about 0.9 percentage points per month, and the span is broken down in the pace analysis above.
At the 09 June 2026 inspection, enabling works and piling were recorded complete and structure works were progressing at site with main contract mobilization still ongoing. Everything certified so far is substructure and early vertical structure; facade, building services and interior fit out across the 512 residences sit ahead of the 20.52% reading.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Residences Creek Blue construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.