Emaar · Dubai Hills Estate
Palace Residences at Dubai Hills Estate Construction Updates
The Verified Build Record Beside Dubai Hills Park
Palace Residences recorded 50.72% construction at its 16 June 2026 RERA inspection, and the climb from February shows envelope and services now setting the pace.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Residences at Dubai Hills Estate at a Glance
Palace Residences is Emaar's 962-residence development on plot 3395 in Dubai Hills Estate, three mid-rise buildings of G+21, G+22, and G+23 storeys standing over one shared podium. Twenty-six months separate the 30 March 2024 construction start from the 50.72% recorded on 16 June 2026, and the figures below are the DLD-registered anchors behind that record. What makes this record read differently from most mid-build projects is its setting: the mall, park, hospital, and golf course around plot 3395 have been trading for years, so only the buildings are unfinished.
2884
Active
30 March 2024
962 residential units
94,252.08 sq m
Q3 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Residences at Dubai Hills Estate Construction Update Timeline
Two certified readings carry this record so far: 36.8% on 12 February 2026 and 50.72% on 16 June 2026, four months and 13.92 points apart. The first of those is also the point where the register crossed a third of the build, and the second is where it crossed half. Each dot on the track below marks one of those inspections, and each table row links the full monthly update behind it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 50.72% | 16 June 2026 | View the June 2026 update |
| February 2026 | 36.8% | 12 February 2026 | View the February 2026 update |
Pace Analysis
How Fast Palace Residences at Dubai Hills Estate Has Been Built
This record holds two dated readings and a registered start date, which is enough to set the long build-up phase against the four months since February:
- Mar 2024 to Feb 2026: enabling, piling, foundations, and frame to 36.8%About 1.6 points per month
- Feb 2026 to Jun 2026: envelope, MEP, and finishes join the frame, 36.8% to 50.72%About 3.4 points per month
More than doubling is the expected shape here rather than a surprise. The first stretch carried everything below ground across a plot serving three buildings, work that consumes months while moving a certified percentage very little, and the register reflected that with an average near 1.6 points. Once the frames repeated and the June notes started listing external envelope, MEP, internal works, and internal finishes alongside superstructure, four packages began contributing to the same reading at once. For a buyer with milestone-linked installments, that matters directly: 9.28 points separate the June figure from the 60% threshold, which at the observed 3.4 points per month is a matter of months rather than years, though the wording of an individual agreement governs what actually triggers a payment. For an investor reading delivery risk, a project past half with 49.28 points left and a handover expected in Q3 2028 is carrying schedule margin rather than racing the calendar.
Get the Next Inspection Figure First
Tell me you are tracking Palace Residences at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Residences at Dubai Hills Estate
The build percentage only means something next to what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Palace Residences at Dubai Hills Estate: Three Mid-Rise Branded Towers
Palace Residences at Dubai Hills Estate brings the Palace name to three mid-rise towers, with access to Dubai Hills Park.
View the Palace Residences at Dubai Hills Estate Project GuideConsidering an Entry Past the Halfway Mark?
Availability at Palace Residences keeps shifting as the certified percentage rises and released inventory sells through. If the record on this page is what brought you here, ask me for current availability before the remaining choice narrows further.
Ask About Remaining Availability on WhatsAppStage Record
Palace Residences at Dubai Hills Estate Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it actually occupied in this project's record, so you can see when Palace Residences passed through it and which packages the inspection notes placed there.
Site Activation and Enabling Works
From the 30 March 2024 construction start: enabling and piling across plot 3395, the phase that consumes months of site time while a certified percentage moves slowly.
Foundations and Substructure
Below ground work under all three buildings and the shared podium, listed as closed out alongside enabling and piling in the 16 June 2026 inspection notes.
Superstructure Across Three Buildings
The 12 February 2026 inspection caught the project at 36.8%, with the frames of the G+21, G+22, and G+23 buildings rising over the shared podium level.
Envelope, MEP, and Internal Finishes
External envelope, MEP, internal works, and internal finishes joined superstructure between the two readings, carrying the register to 50.72% on 16 June 2026.
Envelope Closure, Podium, and Completion
Frames finished and facades sealed on each of the three buildings, then the podium deck, pool, and planting completed ahead of the completion certificate and Q3 2028 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Residences at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Palace Residences at Dubai Hills Estate
This page is one of four project resources that together cover a Palace Residences at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Residences at Dubai Hills Estate Construction Updates
This page: the verified inspection record for Palace Residences, from the 2024 groundbreaking toward handover.

Palace Residences at Dubai Hills Estate Golden Visa: The Line Runs Through
Palace Residences at Dubai Hills Estate is set across three Emaar towers; 2 bedroom, 3 bedroom and townhouse releases each qualify.
Read the Palace Residences at Dubai Hills Estate Golden Visa Guide
Palace Residences at Dubai Hills Estate: Mashreq-Held Escrow for 962 Homes
Mashreq holds escrow for Palace Residences at Dubai Hills Estate, DLD project 2884 of 962 units, certified 50.72% in June 2026.
Verify the Palace Residences at Dubai Hills Estate Escrow AccountApproaching Handover
Between 50.72% and Handover: What Palace Residences at Dubai Hills Estate Buyers Should Do Now
Here the installment schedule keys off certified percentages as much as off dated months, so a new reading reaches a buyer's paperwork before it reaches the site itself. The quiet stretch between inspection cycles, rather than the week a demand notice lands, is when the three checks below are worth making.
First, map your own installment schedule onto the certified record: the 20% and 40% triggers sit behind the 16 June 2026 reading, and 60% is 9.28 points ahead, so the wording of your agreement is worth reading before that figure is reached rather than after.
Second, confirm that every remaining payment lands in the escrow account the Dubai Land Department holds for project 2884, identified in the June inspection report as a Mashreq Bank PSC account; the Palace Residences escrow account page covers the verification and what each release is tied to.
Third, if the purchase may support residency, settle eligibility now rather than at handover through the Palace Residences Golden Visa guide, since an off plan purchase and a completed title deed follow different application paths.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record is only half the picture; the other half is the district it lands in. These three pages put the Palace Residences reading into its community and developer context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Residences at Dubai Hills Estate Construction Updates Frequently Asked Questions
Palace Residences is an active DLD-registered project (number 2884) recorded at 50.72% at the RERA inspection of 16 June 2026, with superstructure work continuing while the envelope, MEP, and internal finishing packages run alongside it. The full record is in the inspection timeline above.
The 16 June 2026 inspection recorded 50.72%, up 13.92 points from the 36.8% reading of 12 February 2026, and it is the first certified figure for project 2884 to sit above the 50% line. The site report behind it is the Palace Residences June 2026 construction update.
From the 30 March 2024 construction start to the February 2026 reading, the record averaged about 1.6 percentage points per month. Between 12 February and 16 June 2026 it ran at about 3.4 points per month as envelope, MEP, and finishing packages joined the frame. The breakdown is in the pace analysis above.
Handover is expected in Q3 2028. At the inspection of 16 June 2026, 49.28 percentage points still separated the project from construction completion, and the published schedule places the 60%, 80%, and 100% milestones between the two. This page's record is updated when each new inspection is recorded.
DLD registration records show 962 residential units, a mix of 1, 2, and 3 bedroom apartments with 3 bedroom townhouses, across a total built-up area of 94,252.08 sq m. Those units sit in three buildings registered at G+21, G+22, and G+23 storeys over one shared podium.
Construction started on 30 March 2024, following project registration with the Dubai Land Department on 28 December 2023. The first tracked inspection, dated 12 February 2026, recorded 36.8%; that reading is documented in the Palace Residences February 2026 construction update.
Three. The DLD project description registers them at G+21, G+22, and G+23 storeys over a shared podium of one basement, ground, and podium level, with the townhouses at podium level. Layouts and the wider case are in the Palace Residences at Dubai Hills Estate project guide.
The development occupies plot 3395 in the Hadaeq Sheikh Mohammed Bin Rashid district, fronting Dubai Hills Park with Dubai Hills Mall a short distance away. The shops, park, hospital, and golf course nearby were open before this plot broke ground, so the wait to Q3 2028 applies to three buildings rather than to a district.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Residences at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.