Emaar · Dubai Hills Estate
Palace Residences Hillside B Construction Updates
One Tower, Five Townhouses and a Register Record That Starts at Zero
Palace Residences Hillside B logged 0% on the DLD register at its 9 December 2025 inspection, a baseline for the Dubai Hills Estate tower and five townhouses.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Residences Hillside B at a Glance
Palace Residences Hillside B is Emaar's 287-residence Palace branded project in Dubai Hills Estate, listed with the Dubai Land Department as project 4280 and made up of one residential tower of basement, ground, podium and 18 floors plus five G+1 townhouses. Its whole record so far is one line, a 0% register reading dated 9 December 2025, and the register sets the other anchors around it: registration on 15 December 2025, a registered construction start of 3 February 2026 and a registered completion date of 31 October 2029. Because that reading predates the registered start, the cards below describe a building measured from zero rather than picked up part way through its build.
4280
Active
3 February 2026
287 residences
26,999.40 sq m
31 October 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Residences Hillside B Construction Update Timeline
The Palace Residences Hillside B record holds a single inspection: 9 December 2025, when the DLD register logged 0% and the RERA report noted that no construction activity had started at site, with its progress status shown as N/A. There is no spread between readings to describe yet, so the track below carries one dot at its left edge, and the table has one row linking the December 2025 update, where that inspection is set out in full. Each later reading will be added here with its own date.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| December 2025 | 0% | 9 December 2025 | View the December 2025 update |
Pace Analysis
How Fast Palace Residences Hillside B Has Been Built
A pace needs two dated readings, and the Palace Residences Hillside B record has one. What can be stated today is the baseline itself and the arithmetic between it and the registered completion date:
- 9 Dec 2025: baseline reading, 0% on the DLD register, no earlier inspection to compareNo measured pace yet
- 9 Dec 2025 to 31 Oct 2029: 100 points over 1,422 days to the registered completion date, arithmetic, not a forecastAbout 2.11 points per 30-day month
Treat the 2.11 figure as a straight line drawn from the December 2025 zero to the 31 October 2029 registered completion date, not as a schedule: it assumes the tower's basement, podium and 18 floors and the five townhouses all advance at one even rate, which no build does. Its value arrives with the second reading. Once a later inspection is dated, the points gained since 9 December 2025 divided by the days elapsed give this project's first measured pace, and setting that figure beside 2.11 shows whether the record is running above or below the even line toward a Q4 2029 handover. For an investor, that comparison is the first delivery signal this record can produce; for an end user, it is the first measure of how the wait is being used. Until it exists, a single 0% entry supports no claim of delay or of early delivery.
Get the Next Inspection Figure First
Tell me you are tracking Palace Residences Hillside B and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Residences Hillside B at Dubai Hills Estate
A baseline reading means little until you know what it is the baseline of. The project guide sets out the homes this record is tracking toward:

Palace Residences Hillside B: A Palace Tower Plus Five Townhouses
Palace Residences Hillside B is Emaar's Palace-branded tower of 18 floors over a podium plus five townhouses, 287 residences in all.
View the Palace Residences Hillside B Project GuideConsidering a Pre-Construction Entry?
EOI registration for Palace Residences Hillside B is open, with deposits of AED 50K ≈ USD 14K for a 1 bedroom, AED 75K ≈ USD 20K for a 2 bedroom, AED 100K ≈ USD 27K for a 3 bedroom and AED 150K ≈ USD 41K for a townhouse, while its construction record opens at 0% on 9 December 2025. The deposit is refunded only if Emaar does not accept the offer, and is forfeited if an accepted offer is not signed and paid on time, so if this page is what brought you here, ask me for current availability first; the choice of floors and layouts narrows as each release is taken up.
Ask About Remaining Availability on WhatsAppStage Record
Palace Residences Hillside B Build Stages, Mapped to the Inspections
Only the first stage below carries an inspection date, because the 9 December 2025 baseline is the one reading on file; the other four are placed against the register's 3 February 2026 construction start and 31 October 2029 completion date, and each will take its window from the readings that record it.
Baseline Inspection and Registration
The 9 December 2025 inspection found no construction activity at site and set the 0% reading; project 4280 was registered on 15 December 2025.
Site Activation and Basement
The register dates the construction start to 3 February 2026; the first reading after the 0% baseline will show how far enabling works and the basement have moved.
Podium and 18-Floor Tower Structure
Ground, podium and the 18 floors of the single tower rise in this stage; its window will be set by the inspections that record them.
Enclosure, Fit-Out and the Five Townhouses
The tower is closed in and fitted out while the five G+1 townhouses and the surrounding grounds take shape; no reading has reached this stage yet.
Finishing, Commissioning and Handover
Final works toward the 31 October 2029 registered completion date and the Q4 2029 handover, when the register would read 100%.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Residences Hillside B's own record.
Buyer Position
Tracking Your Position at Palace Residences Hillside B
This page is one of four project resources that together cover a Palace Residences Hillside B purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Residences Hillside B Construction Updates
This page: the register record for Palace Residences Hillside B, opening at 0% in December 2025.

Palace Residences Hillside B Golden Visa: The Line Through the 1 Bedroom
Emaar's Palace Residences Hillside B qualifies from the 2 bedroom; a 1 bedroom only at the threshold or above.
Read the Palace Residences Hillside B Golden Visa Guide
Palace Residences Hillside B Escrow: The Second Hillside Account
Palace Residences Hillside B escrows 287 units at First Abu Dhabi Bank, DLD project 4280, 0% certified December 2025.
Verify the Palace Residences Hillside B Escrow AccountApproaching Handover
Between 0% and Handover: What Palace Residences Hillside B Buyers Should Do Now
With the register at 0% on 9 December 2025 and the tower's 18 floors and five townhouses still ahead, nothing a Palace Residences Hillside B buyer can inspect is physical yet; protection at this stage sits in where the money goes and what the paperwork says. Launch-stage terms are fixed when a reservation turns into a purchase, so the three steps below belong before the first transfer beyond the EOI, not after it.
First, set your payments against Emaar's 80/20 plan for Palace Residences Hillside B: 10% plus the 4% DLD registration fee on booking, with the EOI deposit applied towards that 10% on signing, then 70% during construction and the final 20% on completion at the Q4 2029 handover. Every plan payment after the EOI belongs in the First Abu Dhabi Bank trust account registered for project 4280, while the 4% fee is paid to the Dubai Land Department; the Palace Residences Hillside B escrow account guide shows how to match the bank and project number on Dubai REST.
Second, if residency is part of the plan, settle the unit type before committing, since 1 bedroom prices of AED 1.96M ≈ USD 534K to AED 2.19M ≈ USD 596K straddle the AED 2M ≈ USD 545K threshold and only units priced at or above it qualify on their own; the Palace Residences Hillside B Golden Visa page sets out which tiers qualify.
Third, follow each new register reading against the zero point; the Palace Residences Hillside B December 2025 construction update holds the inspection behind that starting figure, and later months join the timeline above as they are recorded.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A record that starts before site works reads differently once you see what already stands around the plot. These three pages set Palace Residences Hillside B in its market, community and developer context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Residences Hillside B Construction Updates Frequently Asked Questions
Palace Residences Hillside B is an Active project on the Dubai Land Department register, number 4280, and its only reading so far is 0%, recorded at the inspection of 9 December 2025, when no construction activity had started at site. The register dates the construction start to 3 February 2026; the full record is in the inspection timeline above.
One. The Palace Residences Hillside B record consists of the 9 December 2025 inspection, logged at 0% on the DLD register, with the RERA report of that date showing progress status N/A. With no earlier reading there is no point change to report; the inspection detail is in the Palace Residences Hillside B December 2025 update.
The DLD register dates the Palace Residences Hillside B construction start to 3 February 2026. The first tracked reading, 0% on 9 December 2025, is dated before that start and serves as the baseline, so the next reading on record will be the first taken after the registered start date.
The registered completion date for project 4280 is 31 October 2029, which falls inside the Q4 2029 handover quarter for Palace Residences Hillside B, so the two do not conflict and the registered date has not lapsed. Registered dates can be revised between inspections; the last reading, 0% on 9 December 2025, carries no revision, and this page's record is updated when one is recorded.
Palace Residences Hillside B holds 287 residences in one residential tower of basement, ground, podium and 18 floors plus five G+1 townhouses, the configuration described in the RERA inspection report of 9 December 2025. Hillside B's own typical floor plans show the tower as ground, podium and levels 1 to 18, with five two-level townhouses numbered TH01 to TH05. The residence types and sizes are covered on the Palace Residences Hillside B project guide.
Covering 100 percentage points in the 1,422 days between the 9 December 2025 reading of 0% and the 31 October 2029 registered completion date works out to about 2.11 points per 30-day month. That figure is arithmetic, not a forecast: with one reading on record there is no measured pace yet, and the pace analysis sets the first measured rate against it once a second reading exists.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Residences Hillside B construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.