Palm Beach Tower 1 Construction Updates

The Dated Register Record of Nakheel's Tower at the Palm Gateway

Palm Beach Tower 1 recorded 82.83% in the DLD register on 12 August 2026; what remains at the Palm Gateway is interior, MEP, envelope and external work.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

82.83%Construction Progress
12 August 2026Latest RERA Inspection
278 Residential UnitsTotal Units
Project 2406DLD Registration

Construction Snapshot

Palm Beach Tower 1 at a Glance

Palm Beach Tower 1 is Nakheel's single tower of 278 residential units on plot 2059 at the Palm Gateway, entered in the Dubai Land Department register as project 2406 on 22 June 2022, with construction dated from 1 December 2022. What sets this record apart is where it begins: the first dated register reading, 80.7% on 19 May 2026, came after the frame was already listed as complete, so the history below covers the closing interior and envelope packages of a finished structure rather than a tower rising floor by floor. Handover is scheduled for Q4 2026, the quarter of the 31 December 2026 registered completion date.

DLD Project Number

2406

Project Status

Active

Construction Start

1 December 2022

Total Units

278 Residential Units

Total Built-Up Area

222,797.14 sq m

Registered Completion Date

31 December 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Palm Beach Tower 1 Construction Update Timeline

Two register readings on this record carry a date: 80.7% at the 19 May 2026 inspection and 82.83% at the 12 August 2026 inspection, 85 days apart and 2.13 points apart. A third figure, 77.01%, sits on the May register screen as the previous inspection with no date beside it, so it appears on the track below as an unlabelled dot and has no row in the table. Each row links the monthly update written for that inspection.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202682.83%12 August 2026View the August 2026 update
May 202680.7%19 May 2026

Pace Analysis

How Fast Palm Beach Tower 1 Has Been Built

Only one interval on the Palm Beach Tower 1 record has a date at both ends, so the measured pace rests on a single dated pair, worked on a 30-day month:

  • 19 May 2026 to 12 Aug 2026: interiors, MEP and envelope, 80.7% to 82.83%About 0.75 points per month

One interval cannot draw a curve, so the useful comparison is with the build as a whole: 82.83 points in 1,350 days, counted from the 1 December 2022 start to the 12 August 2026 reading, or about 1.84 points per month. The 85-day figure sits well under that average, and the two inspection reports say where the remaining percentage lives: the frame was listed as complete by May, and by August the report had moved internal works to an advanced stage and added external works to envelope, MEP and finishes. The 3.69 point step from the undated 77.01% to 80.7% is left out of the arithmetic because it has no start date. At the latest reading, 17.17 points and 141 days stood between the register and its 31 December 2026 registered completion date; both are recorded quantities, not a forecast, and no delivery conclusion is drawn from them here. End users planning a Q4 2026 move into this Palm Gateway tower should read the next dated reading against that schedule; investors should watch whether a second interval confirms, lifts or slows the 0.75 figure.

Get the Next Inspection Figure First

Tell me you are tracking Palm Beach Tower 1 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Palm Beach Tower 1 at Palm Jumeirah Dubai

A register percentage measures progress toward a particular building, and at 82.83% on 12 August 2026 that building is in its closing packages. The project guide sets out what Tower 1 buyers are receiving:

Palm Beach Tower 1 at Palm Jumeirah by Nakheel aerial view of the residential towers and waterfront surroundings in Dubai Presented by Tohid Fetrat

Palm Beach Tower 1, Part of Nakheel's Palm Beach Towers

Palm Beach Tower 1 is a Nakheel tower at the Palm Gateway of Palm Jumeirah, with 278 apartments and duplex penthouses.

View the Palm Beach Tower 1 Project Guide

Considering a Near-Handover Entry?

With handover scheduled for Q4 2026, availability at Palm Beach Tower 1 shifts from one register cycle to the next as remaining units are taken. If this record is what brought you here, ask me what is available now before the choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Palm Beach Tower 1 Build Stages, Mapped to the Inspections

Palm Beach Tower 1 enters this record late: by the first dated inspection on 19 May 2026 its foundations and frame were already listed as complete, so the first three stages below are dated only by the register and that May report, and just one stage has two dated readings inside it.

Jun 2022 to Dec 2022

Registration and Site Start

Entered in the DLD register as project 2406 on 22 June 2022 for plot 2059, with construction dated from 1 December 2022.

From Dec 2022, complete by May 2026

Enabling and Foundation Works

Site enabling and the tower's foundations, with no dated reading during them; the 19 May 2026 report already shows both finished.

Complete by 19 May 2026

Frame from Basement to Roof

The B+G+11P+37+LR+R structure, 11 podium levels and 37 floors, listed as completed at the 19 May 2026 inspection; no dated reading caught it mid-rise.

Current PhaseMay 2026 to Aug 2026, 80.7% to 82.83%

Interiors, MEP, Envelope and External Works

80.7% on 19 May 2026 and 82.83% on 12 August 2026, when internal works reached an advanced stage and external works joined MEP, finishes and envelope.

After Aug 2026, toward Q4 2026

Completion and Handover

The 17.17 points left after the 12 August 2026 reading, closing on the 31 December 2026 registered completion date and the Q4 2026 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palm Beach Tower 1's own record.

Buyer Position

Tracking Your Position at Palm Beach Tower 1

This page is one of four project resources that together cover a Palm Beach Tower 1 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palm Beach Tower 1 at Palm Jumeirah by Nakheel Construction Updates aerial view showing project development and beachfront location in Dubai Presented by Tohid Fetrat
You Are Here

Palm Beach Tower 1 Construction Updates

This page: each dated DLD register reading for Palm Beach Tower 1 through to handover.

Palm Beach Tower 1 at Palm Jumeirah by Nakheel Golden Visa eligibility illustration with luxury tower architecture in Dubai Presented by Tohid Fetrat

Palm Beach Tower 1 Golden Visa at the Palm Gateway

Nakheel's Palm Beach Tower 1, 278 units at the Palm Gateway, qualifies at every tier from 1 bedroom to duplex penthouse.

Read the Palm Beach Tower 1 Golden Visa Guide
Palm Beach Tower 1 at Palm Jumeirah by Nakheel Escrow Account security illustration with tower architecture shield protection and lock symbol in Dubai Presented by Tohid Fetrat

Palm Beach Tower 1 Escrow: Nakheel's Palm Jumeirah Account at Mashreq

Nakheel's Palm Beach Tower 1 on Palm Jumeirah escrows 285 units at Mashreq, DLD project 2406, 82.83% certified in August 2026.

Verify the Palm Beach Tower 1 Escrow Account
Why Snagging Matters at This Stage of Palm Beach Tower 1 featuring the illuminated waterfront towers and panoramic coastal skyline at night in Dubai Presented by Tohid Fetrat

Palm Beach Tower 1 Snagging at the Palm Gateway

Palm Beach Tower 1 is a Nakheel tower of 278 residential units where the trunk of Palm Jumeirah meets the mainland.

Book Palm Beach Tower 1 Snagging

Approaching Handover

Between 82.83% and Handover: What Palm Beach Tower 1 Buyers Should Do Now

At the 12 August 2026 reading, 17.17 points separated Palm Beach Tower 1 from 100%, and the work that closes them sits in the interiors, the services and the outer skin rather than in the frame, which both inspection reports already list as complete. A handover notice usually allows only a short period before the appointment itself, which is why the three steps below belong in these final months, not after the notice lands.

First, have an independent snagging team document defects in your apartment or duplex penthouse, internal stairs, balustrades and terraces included, before you accept it; the Palm Beach Tower 1 snagging page covers when to schedule it and what is checked.

Second, set each remaining installment against recorded progress on the Palm Beach Tower 1 escrow account page, where Mashreq Bank PSC is named as the trust bank for project 2406, so final payments follow the register rather than a request.

Third, if your purchase may support residency, settle eligibility through the Palm Beach Tower 1 Golden Visa guide before handover, since title deed timing shapes the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Palm Jumeirah Dubai Structure

A register record describes one building; the island around it decides what that building is worth on completion. These three pages place the Palm Beach Tower 1 record in its market, community and developer context:

Palm Jumeirah Properties for Sale featuring luxury waterfront residences, beachfront homes, iconic palm-shaped island views, premium real estate opportunities, and Dubai skyline panoramas on Palm Jumeirah. Presented by Tohid Fetrat

Palm Jumeirah Dubai Properties for Sale

Browse beachfront apartments, penthouses, sky mansions and signature villas for sale across Palm Jumeirah.

See Palm Jumeirah Dubai Properties for Sale
Aerial view of Palm Jumeirah in Dubai, iconic waterfront development by Nakheel at sunset

Palm Jumeirah Dubai Community Overview

Read the Palm Jumeirah guide: Nakheel's island of signature villas, branded residences, private beaches and five-star resorts.

Explore the Palm Jumeirah Dubai Community
Aerial masterplan view of Palm Jebel Ali by Nakheel showing the palm shaped island and the Dubai waterfront skyline at sunset Presented by Tohid Fetrat

Nakheel: The Master Developer of Dubai's Island Living and Reclaimed Coastline

Founded in 2003, Nakheel created Palm Jumeirah and Dubai Islands, adding over 300 kilometers of coastline and building complete waterfront communities.

View the Nakheel Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Palm Beach Tower 1 Construction Updates Frequently Asked Questions

Palm Beach Tower 1 is an active DLD-registered project, number 2406, which the Dubai Land Department project register put at 82.83% on 12 August 2026. The RERA report of that visit records the enabling, foundation and structure packages as finished and places internal works at an advanced stage; handover is scheduled for Q4 2026. The dated record sits in the inspection timeline above.

Two: 80.7% at the inspection of 19 May 2026 and 82.83% at the inspection of 12 August 2026, both from the Dubai Land Department project register for project 2406. The August reading is 2.13 points above the May one, and each has its own monthly page: the Palm Beach Tower 1 May 2026 construction update and the Palm Beach Tower 1 August 2026 construction update.

Palm Beach Tower 1 is listed in the Dubai REST app as project 2406 under its register name, Palm Beach Towers -1, with status Active. The project details give the registered date (22-06-2022), the construction start (01-12-2022) and the registered completion date (31-12-2026). The inspection panel shows one inspection date at a time with two figures, Current Progress and Previous Inspection, which for 12-08-2026 read 82.83% and 80.7%; each panel date matches the date of the RERA inspection report for the same visit.

The RERA inspection reports for Palm Beach Tower 1 dated 19 May 2026 and 12 August 2026 carry a progress status indicator, Main Contract - Progressing, with written inspection notes and site photographs, but no percentage figure. The percentage for each date is taken from the Dubai Land Department project register instead, which is why this page attributes 80.7% (19 May 2026) and 82.83% (12 August 2026) to the register. The notes remain the source for what was on site, such as internal works at an advanced stage in August.

As a dot on the track and nothing more. The 77.01% figure is shown as the previous inspection when the register displays its 19 May 2026 entry, and no date accompanies it, so it has no row in the timeline table, yields no monthly pace and dates no stage. The only measured pace on the Palm Beach Tower 1 record comes from the dated pair of 80.7% on 19 May 2026 and 82.83% on 12 August 2026, roughly 0.75 points per 30-day month; the full working is in the pace analysis above.

They show Palm Beach Tower 1 at 82.83% in the register on 12 August 2026, with 17.17 points still to record and 141 days to the 31 December 2026 registered completion date, while handover is scheduled for Q4 2026. They do not set a handover date of their own: each reading measures progress on its inspection day, and neither the readings nor the pace between them forecasts when keys are released. Nakheel confirms handover as final inspections complete, and this page's record is updated when later readings are recorded.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palm Beach Tower 1 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status