Emaar · Dubai Hills Estate
Parkwood at Dubai Hills Estate Construction Updates
The Certified Build Record for Two Towers Beside Hillside Park
Parkwood recorded 15% construction progress at its 07 May 2026 RERA inspection, the reading where enabling and piling give way to structure on plot 5414.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Parkwood at Dubai Hills Estate at a Glance
Parkwood is a 487-residence Emaar development on plot 5414 in Dubai Hills Estate, registered with the Dubai Land Department on 22 January 2025 and started on site on 02 May 2025. Its first year of building produced a certified 15%, and that modest figure is an accurate reflection of where the work went: below ground, into piling and foundations spread beneath a built-up area of 51,835.10 sq m. The DLD-registered anchors behind the reading are set out below.
3488
Active
02 May 2025
487 residential units
51,835.10 sq m
31 January 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Parkwood at Dubai Hills Estate Construction Update Timeline
This record currently holds one dated certified reading: 15% on 07 May 2026, logged while enabling, piling, foundation and structure works were all running together on plot 5414. The register also carries an earlier inspection of 5.83% with no published date, so it is noted here in prose rather than plotted as a dated point on the track below, which would imply a precision the source does not give. Every new reading is added as it publishes, with the full site report linked from its own row.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 15% | 07 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Parkwood at Dubai Hills Estate Has Been Built
One dated reading supports one honest velocity: the whole-build average since the site opened. The schedule-implied rate beneath it is arithmetic from the registered completion date, not recorded inspection data:
- 02 May 2025 to 07 May 2026: site start to the first dated reading, 0% to 15%About 1.2 points per month
- 07 May 2026 to 31 January 2029: schedule-implied rate for the 85 points still to runAbout 2.6 points per month
A whole-build average of 1.2 points per month is not a warning sign at this depth of a build. Substructure absorbs money and programme time without moving a percentage: a single basement, ground, podium and first floor slab has to carry both towers before either can climb, so the certified figure stays low while the most expensive risk on the project is being retired. The register also shows the reading rose 9.17 points from an earlier 5.83% inspection, but that inspection carries no published date, so no rate can be calculated across the interval. What matters for anyone holding a Parkwood unit is the second figure: keeping the 31 January 2029 registered date means running at roughly twice the pace achieved so far. That step up is normal once vertical structure replaces excavation, and the next dated inspection is the first real test of whether it has happened.
Get the Next Inspection Figure First
Tell me you are tracking Parkwood at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Parkwood at Dubai Hills Estate
A certified percentage only means something against what it is building toward. The full project guide covers what the 15% is working to deliver:

Parkwood at Dubai Hills Estate: Vida Interiors Beside Hillside Park
Parkwood at Dubai Hills Estate sets apartments and a row of townhouses onto Hillside Park, with interiors under the Vida label.
View the Parkwood at Dubai Hills Estate Project GuideConsidering an Early-Stage Entry?
Entering at 15% means carrying the construction period in exchange for the longest installment runway the plan offers. Availability shifts between inspection cycles, so ask me what is open before the next certified reading resets the picture.
Ask About Remaining Availability on WhatsAppStage Record
Parkwood at Dubai Hills Estate Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is tied to the window it actually occupies in Parkwood's own record, which at this point means one dated inspection and a registered completion date to run toward.
Site Activation and Enabling Works
Construction formally started on 02 May 2025, four months after project 3488 was registered with the DLD, with enabling works opening plot 5414 for the substructure.
Piling and Foundations
The register's earlier certified reading of 5.83% falls in this stage. Its inspection date is not published, so this page does not place it on the dated timeline.
Substructure and First Structure Works
The 07 May 2026 inspection recorded enabling, piling, foundation and structure works progressing together across the shared basement, ground, podium and first floor levels.
Superstructure, Facade and MEP
The stage that has to absorb most of the remaining 85 points: Tower A to 20 floors plus roof, Tower B to 19 floors plus roof, then enclosure and services.
Fit-Out, Commissioning and Completion
Interior fit-out across the 487 residences, amenity and podium landscaping, then commissioning and building completion procedures before the registered date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Parkwood at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Parkwood at Dubai Hills Estate
This page is one of four project resources that together cover a Parkwood at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Parkwood at Dubai Hills Estate Construction Updates
This page: the verified inspection record for Parkwood, from the May 2025 site start toward handover.

Parkwood at Dubai Hills Estate Golden Visa: Three of Four Tiers
Parkwood at Dubai Hills Estate, Emaar's 487 residences, qualifies at 2 and 3 bedroom apartments and the 3 bedroom townhouse.
Read the Parkwood at Dubai Hills Estate Golden Visa Guide
Parkwood at Dubai Hills Estate: The Escrow for 487 Homes
Parkwood at Dubai Hills Estate is DLD project 3488, 487 units in First Abu Dhabi Bank escrow, 15% certified May 2026.
Verify the Parkwood at Dubai Hills Estate Escrow AccountApproaching Handover
Between 15% and Handover: What Parkwood at Dubai Hills Estate Buyers Should Do Now
At this depth of a build the buyer's job is not watching the towers rise; it is making sure the paperwork behind each installment is correct while there is still time to fix it. The Emaar schedule ties the fourth installment to 30% certified completion rather than to a printed date, so the distance between today's 15% and that threshold is the window in which the three steps below happen.
First, confirm where your money lands before it moves; the Parkwood escrow account verification page shows the DLD-regulated trust account recorded for project 3488 with First Abu Dhabi Bank.
Second, read your installment schedule against certified percentages rather than the indicative dates printed beside them, because a milestone-linked plan follows the inspection record on this page, not the calendar.
Third, if residency is part of why you bought, settle eligibility now through the Parkwood Golden Visa eligibility guide, while there are years rather than weeks before the title deed is issued.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record is only half the picture; the other half is the community the site sits inside. These three pages put Parkwood's 15% in its masterplan, community, and developer context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Parkwood at Dubai Hills Estate Construction Updates Frequently Asked Questions
Parkwood is an active DLD-registered project (number 3488) in its substructure and early structure phase, recorded at 15% at the RERA inspection of 07 May 2026. The full record is in the inspection timeline above.
The 07 May 2026 inspection recorded 15% construction progress, up 9.17 points from an earlier certified reading of 5.83%, with enabling, piling, foundation and structure works all noted as progressing. The full site report is in the May 2026 construction update.
The DLD-registered completion date for project 3488 is 31 January 2029, which leaves 85 percentage points to run from the 15% recorded on 07 May 2026. The DLD can revise a registered date at any point in a build, and this page's record moves with each published reading.
Parkwood comprises 487 residences across one, two and three bedroom apartments plus three bedroom townhouses, built over a total built-up area of 51,835.10 sq m recorded for project 3488. The scheme is arranged as Tower A of 20 floors plus roof and Tower B of 19 floors plus roof.
Across the twelve months between the 02 May 2025 site start and the 07 May 2026 inspection, Parkwood averaged about 1.2 percentage points per month to reach 15%. Holding the registered completion date of 31 January 2029 implies roughly 2.6 points per month for the remaining 85 points, a schedule-implied figure rather than a recorded one. The working is in the pace analysis above.
Project 3488 was registered with the Dubai Land Department on 22 January 2025 and construction start was recorded on 02 May 2025, roughly three and a half months later. The first dated certified reading on this page is the 15% logged on 07 May 2026.
At the 07 May 2026 inspection the recorded works were enabling, piling, foundation and structure, running together across plot 5414. Both towers share a single basement, ground, podium and first floor structure, so the majority of the 15% represents substructure rather than visible tower floors.
Parkwood occupies plot 5414 in Hadaeq Sheikh Mohammed Bin Rashid, the Dubai Hills Estate master plan, beside Hillside Park. Unlike the towers themselves, the surrounding infrastructure was finished long before this plot broke ground, so what separates today from 2029 is build progress rather than any wait for amenities.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Parkwood at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.