Emaar Properties · Rashid Yachts & Marina
Pier Point 1 at Rashid Yachts & Marina Construction Updates
Tracking Two Towers From Piling to Handover Beside the Marina Berths
Pier Point 1 recorded 8.27% construction progress at its 14 May 2026 RERA inspection, and the first readings establish a piling stage programme on plot 512.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Pier Point 1 at Rashid Yachts & Marina at a Glance
Pier Point 1 is Emaar's 122 home release on plot 512 of Rashid Yachts & Marina, registered with the Dubai Land Department as project 3304 on 23 September 2024 and under construction since 22 February 2025. The 8.27% certified on 14 May 2026 covers the first fourteen and a half months of that programme, and it is the entire published record: this is the first tower in the marina tracked here from its piling stage rather than picked up once the frame was already up, so the figures below are the registration anchors a buyer has to read the site through.
3304
Active
22 February 2025
122 residential units
12,894.42 sq m
31 October 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Pier Point 1 at Rashid Yachts & Marina Construction Update Timeline
Two readings sit on the record for project 3304 and only one of them is dated: 6.12% is carried as the previous figure inside the report, then 8.27% was certified at the inspection of 14 May 2026, a gain of 2.15 points. The track below plots both, the single table row links the full May 2026 report, and each further cycle joins it here as RERA records it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 8.27% | 14 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Pier Point 1 at Rashid Yachts & Marina Has Been Built
On a record this young the useful arithmetic runs in two directions: what the plot has averaged since the February 2025 start, and what it has to average from here to meet the date on the registration.
- Feb 2025 to May 2026: mobilization, enabling and piling, 0% to 8.27%About 0.6 points per month
- May 2026 to Oct 2028: the 91.73 points left to certify before handoverAbout 3.1 points per month needed
Only two readings exist, and because the earlier 6.12% is carried inside the 14 May 2026 report without a date of its own, the 2.15 point step between them cannot honestly be given a monthly rate. What can be measured is the whole stretch from 22 February 2025, and 0.6 points per month across it is the signature of groundworks: piling consumes programme time while registering very little certified progress, which is why an 8.27% reading fourteen and a half months in says nothing negative about the schedule. The curve should steepen sharply once the substructure gives way to the registered ground plus one podium, nine floor and roof frame, because floor plates convert into percentage points far faster than piles do. For an investor the number to hold onto is the 3.1 points per month the remaining 91.73 points imply against 31 October 2028; for a buyer already committed, that same figure is the yardstick for judging each new reading as it lands.
Get the Next Inspection Figure First
Tell me you are tracking Pier Point 1 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Pier Point 1 at Rashid Yachts & Marina at Mina Rashid
A percentage is only useful next to what it is building toward. At the 8.27% recorded on 14 May 2026 the case for Pier Point 1 sits in the registration and the layouts rather than on the plot, and the project guide holds both:

Pier Point 1 at Rashid Yachts & Marina, by the Superyacht Berths
Pier Point 1 at Rashid Yachts & Marina holds 122 Emaar residences in two towers on a landscaped podium.
View the Pier Point 1 at Rashid Yachts & Marina Project GuideConsidering an Entry at the Piling Stage?
Availability at Pier Point 1 shifts between inspection cycles, and entering this early buys the longest instalment runway against a handover registered for 31 October 2028. If the record on this page is what brought you here, ask what is still released before the next cycle changes it.
Ask About Remaining Availability on WhatsAppStage Record
Pier Point 1 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Each stage below is pinned to where it actually sits in the Pier Point 1 record rather than to a generic construction sequence. Only the first two carry a certified reading behind them, the 8.27% of 14 May 2026, with 91.73 points of the programme still ahead of the third.
Site Mobilization on Plot 512
From the 22 February 2025 construction start: site compound, access and setting out on plot 512 in Madinat Dubai Almelaheyah, work the May 2026 brief still lists among the activity on site.
Enabling Works and Piling
The 14 May 2026 inspection recorded mobilization, enabling and piling under way and carried the main contract as progressing, certifying 8.27% against the 6.12% held as the previous reading.
Substructure and Superstructure
Pile caps and basement, then the registered ground plus one podium, nine floor and roof frame across both towers and the podium between them. This is where certified progress climbs fastest.
Facade, Fit Out and Podium Landscaping
Enclosing both towers, fitting out the 122 residences, and building the pool deck, gardens and retail frontage that give the scheme its marina outlook.
Completion Procedures and Handover
The closing RERA inspection cycles, completion procedures and the handover window that both the registration and Emaar Properties place from October 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Pier Point 1 at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Pier Point 1 at Rashid Yachts & Marina
This page is one of four project resources that together cover a Pier Point 1 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Pier Point 1 at Rashid Yachts & Marina Construction Updates
This page: every recorded inspection reading for Pier Point 1, from the February 2025 groundbreaking onward.

Pier Point 1 at Rashid Yachts & Marina Golden Visa: 122 Homes
Three of four types at Pier Point 1 at Rashid Yachts & Marina, Emaar's waterfront release, qualify on a single purchase.
Read the Pier Point 1 at Rashid Yachts & Marina Golden Visa Guide
Pier Point 1 at Rashid Yachts & Marina: First Tower Escrow
Pier Point 1 at Rashid Yachts & Marina, DLD project 3304: First Abu Dhabi Bank escrow, 8.27% certified May 2026.
Verify the Pier Point 1 at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 8.27% and Handover: What Pier Point 1 at Rashid Yachts & Marina Buyers Should Do Now
The distance between 8.27% and a building anyone can inspect is closed by substructure work, so this is the window for checking the paperwork rather than the progress. The instalments in the launch schedule of record run on their own dates rather than on inspection readings, with the next of them placed in November 2026, which puts the three checks below before that date instead of after it.
First, confirm that every instalment still ahead of you is routed to the DLD registered trust account for project 3304 at First Abu Dhabi Bank P.J.S.C.; the Pier Point 1 escrow account page sets out the account and how certified progress releases money from it.
Second, read the record cycle by cycle rather than only its latest number, starting with the Pier Point 1 May 2026 construction update, which carries the inspection brief behind the 8.27% figure in full.
Third, if residency is part of the plan, settle eligibility now rather than at handover through the Pier Point 1 Golden Visa eligibility guide, because the AED 2 million threshold is decided by the tier you buy, not by the date you complete.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
Two readings on one plot say little standing alone. These three pages set the Pier Point 1 record against the towers released beside it, the marina being finished around it, and the developer carrying the programme:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Pier Point 1 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Pier Point 1 is an active DLD registered project, number 3304, in its enabling and piling stage, with certified progress recorded at 8.27% at the inspection of 14 May 2026 and the main contract carried as progressing at that date. The full record is in the inspection timeline above.
Two. The 14 May 2026 inspection certified 8.27%, a rise of 2.15 points on the 6.12% the same report carries as the previous figure, and that earlier reading holds no separate date of its own in the DLD record. Every later cycle is added to this page as it is recorded.
Across the fourteen and a half months between the 22 February 2025 construction start and the 14 May 2026 inspection, certified progress averaged about 0.6 percentage points per month, which is the arithmetic of mobilization, enabling and piling rather than of a stalled site. Closing the remaining 91.73 points by the registered date of 31 October 2028 implies about 3.1 points per month from here. The working is set out in the pace analysis above.
The completion date registered with the Dubai Land Department for project 3304 is 31 October 2028, and Emaar Properties markets handover as October 2028. That date had not been reached at the 14 May 2026 inspection, which leaves just under thirty months and 91.73 percentage points between the latest reading and the registered target, and this page is updated as each new inspection is recorded.
A total of 122. The DLD registration describes the scheme as a residential development of ground plus one podium, nine floors and roof, delivered as one to three bedroom apartments with a short run of three bedroom townhouses across two towers over a single landscaped podium. Layouts and the full specification are in the Pier Point 1 at Rashid Yachts & Marina project guide.
Construction started on 22 February 2025, five months after project 3304 was registered with the Dubai Land Department on 23 September 2024. The first reading published on this site is the 8.27% certified on 14 May 2026, reported in full in the Pier Point 1 May 2026 construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Pier Point 1 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.