RAW District by Imtiaz architectural visualization for the June 2026 construction update in Downtown Jebel Ali Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Downtown Jebel Ali · Construction Update

RAW District by Imtiaz Construction Update - June 2026

June 2026 DLD Record Shows RAW District by Imtiaz at 0% Ahead of Its Scheduled 15 October 2026 Construction Start

No construction activity had started when RERA inspected RAW District on 09 June 2026; the DLD register reads 0% ahead of the scheduled 15 October 2026 start.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Progress
09 June 2026Inspection Date
Q1 2029Expected Handover
4500DLD Project Number

Verified DLD Register Data

RAW District by Imtiaz Construction Snapshot

A first reading of 0%, with no earlier figure to compare against, places RAW District by Imtiaz at the opening of the enabling and foundations band, where the record is about registration and payment protection rather than visible site progress.

Project Name

RAW District by Imtiaz

Project Number

4500

Project Status

Active

Construction Progress

0%

Inspection Date

09 June 2026

Construction Start

15 October 2026

Total Units

670 units

Total Built Area

35,391.30 sq m

Expected Completion

15 December 2029

Data source: RERA inspection conducted on 09 June 2026 for DLD project 4500, whose report records that no construction activities had started; the 0% figure is the reading shown in the Dubai Land Department project register. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

RAW District by Imtiaz Construction Progress Summary

The June 2026 cycle sets the baseline for everything that follows: the RERA inspection on 09 June 2026 found that no construction activities had started, and the DLD register, which records the project as registered on 16 June 2026, shows 0%. Every later RAW District reading will be measured from this starting point.

Completed
  • First RERA site inspection, conducted on 09 June 2026
  • DLD project registration as project 4500, dated 16 June 2026
  • Trust account bank on record: First Abu Dhabi Bank P.J.S.C.
Position at 0%
  • No construction activity recorded at the 09 June 2026 inspection
  • Pre-start period ahead of the scheduled 15 October 2026 construction start
  • Sales under the developer's dated plans, next instalment 15 October 2026
Ahead of Handover
  • Enabling and foundation works after the scheduled start
  • Superstructure of the G+5P+15+Roof residential building described in the inspection report
  • Residential towers, retail podium and office building shown in the developer's plans
  • Handover anticipated in Q1 2029, with a registered completion date of 15 December 2029
Next inspectionRecorded in the DLD project register after the next RERA site visit; the first reading after the 15 October 2026 scheduled start is the one that shows whether works began on time.
Completion targetHandover anticipated in Q1 2029 by the developer; the DLD register carries a later registered completion date of 15 December 2029.
Remaining distance100 percentage points separate the 09 June 2026 reading from completion.

Payment Timing at 0%

What 0% Progress Means for RAW District Buyers

Both Imtiaz payment plans for RAW District set instalments by calendar date rather than by construction milestone, so a 0% reading does not pause them: the second instalment, 5% of the price, is scheduled for 15 October 2026, the same date the register gives for the construction start. At this stage, four actions matter most.

Before the 15 October 2026 Instalment

Verify the escrow account

Every payment, the booking amount included, should go only to the DLD regulated escrow account registered for project 4500 at First Abu Dhabi Bank P.J.S.C. RAW District by Imtiaz escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before You Sign

Read your SPA against the dated plan

Check whether your sale and purchase agreement follows the developer's dated schedule, 50/50 or the 60/40 option with 40% paid over three years after handover, and how it treats the Q1 2029 handover against the 15 December 2029 registered completion date. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood is the DLD's interim register for off plan sales, and on a project that has not started construction it is the buyer's main registered proof of purchase. Confirm it is issued in your name against project 4500 once the booking payment and the 4% DLD registration fee are settled.

Every Cycle

Watch for the first working reading

The first inspection after the scheduled start will show whether enabling works began on time. The RAW District by Imtiaz construction updates hub records each reading as it lands.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before construction starts trades certainty for runway: nothing is built yet and handover is anticipated in Q1 2029, but the plan spreads most of the price across dated instalments and completion. Every payment goes to the DLD-registered escrow account for project 4500, released against RERA-inspected construction progress.

Entering Now at 0%
  • 20% plus the 4% DLD registration fee and admin fee on booking
  • Six 5% instalments dated 15 October 2026 to 1 September 2028 on the 50/50 plan
  • 50% due on completion, anticipated in Q1 2029
Typical Near-Completion Entry
  • Structure already inspected and visible on site
  • A shorter wait, with most of the price due within months
  • Choice narrowed to the units still unsold
AED 649K ≈ USD 176.7KStarting Price
50/50 Plan50% Due on Completion
Q1 2029Expected Handover
Ask What Is Available at RAW District

Limited units available per the project page as of this update; availability shifts between cycles.

About the Development

RAW District by Imtiaz Project Details

RAW District by Imtiaz in Downtown Jebel Ali evening exterior view featuring residential towers, office building, metro station, and landscaped surroundings in Dubai Presented by Tohid Fetrat
Downtown Jebel Ali · Imtiaz Developments

Registered as DLD project 4500 and read at 0% on 09 June 2026, RAW District by Imtiaz is a pre-construction mixed-use district of fully furnished apartments, offices and retail on Sheikh Zayed Road. The development counts 670 units in total. Starting prices: AED 649K ≈ USD 176.7K.

For buyers entering at this stage, the trade off is the longest wait in the build cycle against the lightest early outlay, with handover anticipated in Q1 2029 and the register's completion date set at 15 December 2029.

RAW District by Imtiaz Project Guide

Site Context This Cycle

Explore RAW District by Imtiaz Location on Dubai Map

RAW District fronts Sheikh Zayed Road and has a direct connection to the adjacent metro, and that frontage will shape how the build opens: after the scheduled 15 October 2026 start, the first works to look for in later readings are enabling and site access packages along the highway edge, none of which had begun at the 09 June 2026 inspection.

Downtown Jebel Ali is a growth district rather than a finished one, with Palm Jebel Ali and Expo City each about 10 minutes away and Al Maktoum International Airport about 25 by the developer's figures, so buyers here are pricing the district's growth alongside the building's own progress toward the Q1 2029 handover. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view RAW District by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in RAW District by Imtiaz Before Construction Begins

Before the first foundation is laid, the buyer's questions are about payment protection and residency eligibility rather than progress. Each resource below is matched to where RAW District stands in June 2026.

RAW District by Imtiaz architectural visualization for construction updates in Downtown Jebel Ali Dubai - Presented by Tohid Fetrat
You Are Here

RAW District by Imtiaz Construction Updates

This page: the June 2026 DLD reading for RAW District, the first entry before construction starts.

RAW District by Imtiaz highlighting UAE Golden Visa eligibility for qualifying Dubai property investors - Presented by Tohid Fetrat

RAW District Golden Visa: Seven Tiers Against the AED 2M Line

Only retail spaces at Imtiaz's RAW District sit above AED 2M; no apartment or office tier clears it alone.

Read RAW District by Imtiaz Golden Visa Guide
RAW District by Imtiaz highlighting the Dubai escrow account system protecting off-plan property buyer payments - Presented by Tohid Fetrat

RAW District Escrow: Imtiaz in Downtown Jebel Ali

Imtiaz Developments' RAW District is DLD project 4500, 672 units escrowed at First Abu Dhabi Bank, 0% certified June 2026.

Verify RAW District by Imtiaz Escrow Account

Update Timeline

Other RAW District by Imtiaz Construction Updates

This June 2026 report opens the RAW District inspection history; each later reading joins the hub as the project moves from its scheduled start toward handover.

All RAW District by Imtiaz Construction Updates

FAQs

RAW District by Imtiaz Construction Progress in June 2026: Frequently Asked Questions

The Dubai Land Department project register shows RAW District by Imtiaz, project 4500, at 0% following the RERA inspection of 09 June 2026. The inspection report notes that no construction activities had started at the time of the visit and lists the progress status as N/A. This is the first reading on record, so there is no earlier figure to measure a change against.

Nothing in the June 2026 record points to slippage: a 0% reading on 09 June 2026 is consistent with a construction start that the DLD register schedules for 15 October 2026. The developer anticipates handover in Q1 2029, while the register carries a later registered completion date of 15 December 2029, and either date can be revised between inspection cycles. How schedule changes are followed across the build is covered on the RAW District by Imtiaz construction updates hub.

The RERA inspection took place on 09 June 2026, about four months before the construction start date of 15 October 2026 shown in the DLD register. At that visit the inspector found that no construction activities had started, and the register holds the project at 0%. At this point the figure reflects the pre-start timetable, not a site where work has stopped.

The record shows a RERA inspection on 09 June 2026 and a DLD registration date of 16 June 2026, both as entered in the register. It schedules construction to start on 15 October 2026 and gives a registered completion date of 15 December 2029. The developer's own anticipated handover is Q1 2029.

Not under the developer's published plans. Both Imtiaz payment plans for RAW District set their instalments by calendar date rather than by construction milestone, and each schedules a 5% instalment on 15 October 2026 after the 20% booking payment. Your sale and purchase agreement fixes the dates that apply to your unit, and every instalment is paid into the project's DLD-registered escrow account at First Abu Dhabi Bank P.J.S.C.

The RERA inspection report of 09 June 2026 describes the project as a G+5P+15+Roof residential building and records that no construction activities had started on site. The developer's factsheet places residential towers, a retail and F&B podium and a separate office building within the same district, none of which had been started at the time of that visit.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for RAW District correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts