DAMAC Properties · DAMAC Riverside
Sage at DAMAC Riverside Construction Updates
The Dated Build Record of 550 Townhouses in Dubai Investment Park 2
Sage at DAMAC Riverside reached 13.26% on the DLD register at its 26 August 2026 inspection, opening the dated record of 550 townhouses with foundations under way.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Sage at DAMAC Riverside at a Glance
Sage at DAMAC Riverside is DAMAC Properties' cluster of 550 G+1+R townhouses in DAMAC Riverside, Dubai Investment Park 2, carried on the DLD register under its own project number, 3171. The register reading of 13.26% recorded on 26 August 2026 came 701 days after the 24 September 2024 construction start, and because the cluster is a spread of low-rise homes on one site rather than a single building, the inspection note of that date placed foundation and substructure works at several different points of progress across the plot.
3171
Active
24 September 2024
550 townhouses, G+1+R
1,347.67 sq m
31 December 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Sage at DAMAC Riverside Construction Update Timeline
The Sage record so far is short and exact: DLD registration on 16 July 2024, a construction start on 24 September 2024, and one dated inspection, 13.26% on 26 August 2026. The register also carries an earlier 7.63% reading with no date attached, so it appears on the track below as a dot with no month and has no table row of its own. Ahead sit DAMAC's expected handover in Q4 2027 and the registered completion date of 31 December 2027, and the one table row below links the full August 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 13.26% | 26 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Sage at DAMAC Riverside Has Been Built
With one dated reading on the Sage record, no inspection-to-inspection pace exists yet. What can be stated is arithmetic on the register's own dates, shown per 30-day month and not as a forecast:
- 24 Sep 2024 to 26 Aug 2026: registered start to the latest reading, 0% to 13.26% in 701 daysAbout 0.57 points per month, whole-build average
- 26 Aug 2026 to 31 Dec 2027: 13.26% to 100% by the registered completion date, 86.74 points in 492 daysAbout 5.29 points per month if that date holds
- Previous reading of 7.63%: shown in the register without a dateNo measured pace
Set side by side, the two figures describe different spans rather than a single curve. The 0.57 average spreads 13.26 points across all 701 days since the registered start, a span that, by the August 2026 note, still included ongoing mobilisation and advanced enabling and infrastructure works across a 550-home site; the 5.29 figure is simply what the remaining 86.74 points would need per 30-day month for the registered date of 31 December 2027 to hold. Neither is a forecast, and the registered date is DAMAC's filing with the DLD, not a promise. The first measured pace will come from the next dated reading: for an end user planning around a Q4 2027 move, that is the figure to watch, and for an investor modelling the 25% due on handover, it is the first evidence of how quickly the townhouse frames rise once foundations give way to superstructure.
Get the Next Inspection Figure First
Tell me you are tracking Sage at DAMAC Riverside and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Sage at DAMAC Riverside
A 13.26% reading on 26 August 2026 means little without the homes it measures. The full project guide sets out what the Sage record is building toward:

Sage at DAMAC Riverside: Middle and End Unit Townhouses
Sage at DAMAC Riverside is a DAMAC Properties cluster of 550 townhouses, 4 bedroom middle units and 5 bedroom end units.
View the Sage at DAMAC Riverside Project GuideConsidering an Early-Stage Entry?
At 13.26% on the 26 August 2026 register reading, Sage is being sold while its foundations and substructure are under way, and the townhouses on offer are set by DAMAC Properties release by release. If the record on this page is what brought you here, ask me what is available today and how the payment plan applies to a unit bought now.
Ask About Remaining Availability on WhatsAppStage Record
Sage at DAMAC Riverside Build Stages, Mapped to the Inspections
Each stage below is pinned to the register dates and the single dated reading in the Sage record, so the current position comes from the record rather than a generic build sequence: one stage closed, one under way at 13.26% on 26 August 2026, and three still ahead of the Q4 2027 handover.
Registration and Construction Start
The DLD registered Sage as project 3171 on 16 July 2024, and the register records construction starting on 24 September 2024, 70 days later; no dated reading falls in this window.
Enabling Works, Foundations and Substructure
At the 26 August 2026 inspection the register read 13.26%, with site infrastructure and enabling works well advanced and foundation and substructure works at varying stages across the 550-townhouse plot.
Townhouse Superstructure
Superstructure works on the G+1+R townhouses were logged at an early stage in August 2026; the next dated readings will show how quickly this phase moves the percentage.
Blockwork Envelope, MEP and Internal Works
External envelope, MEP and internal works were each at an early stage on 26 August 2026, the bridge between the concrete structure and the finishes the register describes.
Finishes and Handover
Internal and external finishes close the build toward DAMAC's expected Q4 2027 handover and the 31 December 2027 registered completion, when the final 25% falls due on handover, at completion.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sage at DAMAC Riverside's own record.
Buyer Position
Tracking Your Position at Sage at DAMAC Riverside
This page is one of four project resources that together cover a Sage at DAMAC Riverside purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sage at DAMAC Riverside Construction Updates
This page: the DLD register record for Sage, from the 24 September 2024 start to handover.

Sage at DAMAC Riverside Golden Visa From the 4 Bedroom Townhouse
Sage at DAMAC Riverside, DAMAC Properties' townhouse cluster in Dubai Investment Park 2, qualifies from its 4 bedroom townhouse upward.
Read the Sage at DAMAC Riverside Golden Visa Guide
Sage Escrow Account: Plot 1211 and First Abu Dhabi Bank
Sage at DAMAC Riverside, DLD project 3171, escrows 550 townhouses with First Abu Dhabi Bank, certified 13.26% in August 2026.
Verify the Sage at DAMAC Riverside Escrow AccountApproaching Handover
Between 13.26% and Handover: What Sage at DAMAC Riverside Buyers Should Do Now
At this reading the Sage townhouses are still below their superstructure, and most of the cluster's construction record is yet to be written. That makes this window about protecting payments and planning ahead rather than inspecting finished homes, and each step below is easiest to settle before the next instalment in your SPA schedule falls due, not after it.
First, ahead of every one of the 24 construction instalments, confirm the receiving account and the register details on the Sage at DAMAC Riverside escrow account page, so every transfer goes into the First Abu Dhabi Bank trust account for project 3171.
Second, if residency is part of the plan, read the Sage at DAMAC Riverside Golden Visa guide early, since for an off-plan townhouse it is the Oqood value, not the list price, that the eligibility check reads.
Third, follow the record rather than the renderings: the next dated reading after 26 August 2026 will join the inspection timeline above and give Sage its first measured pace, and the Sage August 2026 inspection report sets the baseline it will be compared with.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Riverside Structure
A cluster record reads differently once you see what surrounds it. These three pages place the Sage build inside its market, its master community and its developer:

DAMAC Riverside Properties for Sale
Explore DAMAC Riverside properties for sale, featuring modern apartments, spacious townhouses, luxury villas, flexible payment plans and amenities.
See DAMAC Riverside Properties for Sale
DAMAC Riverside Community Overview
Read the DAMAC Riverside guide: 4 and 5 bedroom townhouses with lagoons and green spaces in the Dubai South growth corridor.
Explore the DAMAC Riverside Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Sage at DAMAC Riverside Construction Updates Frequently Asked Questions
Sage at DAMAC Riverside is an active project on the Dubai Land Department register, number 3171, in early-stage construction: it read 13.26% at the inspection of 26 August 2026, when the RERA progress report listed the main contract as progressing. Foundations and substructure were under way on that date, and the dated record is set out in the inspection timeline above.
The 26 August 2026 inspection recorded Sage at 13.26% on the DLD register, 5.63 points above a previous reading of 7.63% that the register does not date. Because that earlier reading has no date, the gain cannot be turned into a monthly rate; the inspection itself is covered in the Sage at DAMAC Riverside August 2026 construction update.
The Sage at DAMAC Riverside record holds four register dates: DLD registration on 16 July 2024, construction start on 24 September 2024, the 13.26% reading of 26 August 2026 and a registered completion date of 31 December 2027. Registration came 70 days before the start, and DAMAC's expected handover in Q4 2027 frames the far end of the record.
As arithmetic, not a forecast: 13.26 points across the 701 days from the registered start on 24 September 2024 to the 26 August 2026 reading average about 0.57 points per 30-day month at Sage at DAMAC Riverside. Reaching 100% by the registered completion date of 31 December 2027 would take the remaining 86.74 points in 492 days, about 5.29 points per 30-day month. The two figures describe different spans and carry no verdict on timing; the pace analysis above sets them side by side.
Q4 2027 is DAMAC's expected handover for Sage at DAMAC Riverside, and 31 December 2027 is the registered completion date in the DLD record for project 3171, as listed at the 26 August 2026 reading. The registered date falls inside the Q4 2027 window, so the two agree; the registered date records what DAMAC filed with the DLD rather than a commitment, the handover itself is confirmed by DAMAC as works complete, and this page's record is updated as each new inspection is recorded.
Sage at DAMAC Riverside comprises 550 townhouses, which the RERA progress report of 26 August 2026 describes as G+1+R units of concrete and blockwork construction, finished inside and out. G+1+R is register shorthand for a ground floor, a first floor and a roof level, so the 13.26% reading is one figure for 550 low-rise homes rather than for the floors of a single building.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sage at DAMAC Riverside construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.