SeaPoint at Emaar Beachfront Construction Updates
The Verified Inspection Record for Plot 3649 on the Emaar Beachfront Island
SeaPoint at Emaar Beachfront reached 36.78% construction at its 24 June 2026 RERA inspection, the climb so far carrying two towers above their shared island podium.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
SeaPoint at Emaar Beachfront at a Glance
SeaPoint at Emaar Beachfront is Emaar Properties' 674-residence development on plot 3649 at Dubai Harbour, registered with the Dubai Land Department as project 2633. Two years and nine months separate its 12 September 2023 construction start from the 36.78% recorded at the June 2026 inspection, and the figures below are the registered anchors behind that record. Its registered description, a basement, a ground floor and eight podium levels carrying towers of 57 and 42 storeys, is the reason one percentage here has to cover two vertical programmes of very different height.
2633
Active
12 September 2023
674 residential units
84,733.14 sq m
April 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
SeaPoint at Emaar Beachfront Construction Update Timeline
The register carries two readings for project 2633. The current one, 36.78%, was recorded at the inspection of 24 June 2026; the reading before it stands at 25.15% and is published without a date, so it appears on the track below at its percentage only and is not tabulated as a dated row. The 11.63 point spread between the two is the whole of the published movement so far, and the table links the full monthly update behind the June 2026 figure.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 36.78% | 24 June 2026 | View the June 2026 update |
Pace Analysis
How Fast SeaPoint at Emaar Beachfront Has Been Built
Reading the pace behind a percentage tells buyers more than the percentage itself. For SeaPoint the register supplies one fully dated interval and one measured step whose interval is not published, so the record carries exactly one true velocity:
- 12 Sep 2023 to 24 Jun 2026: site start to superstructure, 0% to 36.78%About 1.1 points per month
- Previous register reading to the June 2026 inspection: 25.15% to 36.78%Up 11.63 points, interval undated
An average of about 1.1 points per month across thirty three months is the signature of a build whose early spend goes downward and sideways rather than upward. On a plot this tight to the water the enabling, piling, foundation and substructure packages are all certified complete in the June 2026 report, and none of that work moves a percentage the way a floor plate does. The 11.63 point step to the 36.78% recorded in June 2026 is the first reading taken with both towers in vertical production above the shared eight level podium, which is the point where a curve of this shape normally steepens. For an investor the useful test at the next two inspections is whether the rate climbs clear of that 1.1 point average; for an end user counting toward April 2028, it is whether the 57 storey tower keeps pace with the 42 storey one, because a single handover date covers both.
Get the Next Inspection Figure First
Tell me you are tracking SeaPoint at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About SeaPoint at Emaar Beachfront
A percentage is only worth following if you know what it is building. The project guide covers the 674 residences behind the 36.78% recorded on 24 June 2026:

SeaPoint at Emaar Beachfront: Penthouses and a Private Beach
SeaPoint at Emaar Beachfront holds 674 Emaar homes, apartments to six bedroom penthouses, with a private beach and ninth floor deck.
View the SeaPoint at Emaar Beachfront Project GuideConsidering an Entry at This Stage?
Availability at SeaPoint keeps shifting as the towers rise above the podium. If the record on this page is what brought you here, ask me for current availability before the remaining waterfront residences narrow further.
Ask About Remaining Availability on WhatsAppStage Record
SeaPoint at Emaar Beachfront Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is anchored to the window it actually occupied in SeaPoint's own record, so you can see where the 36.78% recorded on 24 June 2026 sits in the build.
Registration and Site Activation
Project 2633 entered the Dubai Land Department register on 16 April 2023, with First Abu Dhabi Bank named as the project's trust account bank. Construction on plot 3649 was recorded as starting five months later.
Enabling, Piling and Substructure
Enabling works, piling, foundations and the full substructure below the podium. All four packages were recorded as complete by the 24 June 2026 inspection.
Superstructure and External Envelope
Vertical production running on both towers at once, 57 storeys on one and 42 on the other off a single podium base. This is the phase the 24 June 2026 reading was taken in.
MEP and Internal Finishing
MEP and internal finish works were already recorded as progressing in June 2026, but the bulk of both sits between the 36.78% reading and the 80% payment milestone.
Commissioning and Handover
Systems commissioning, the amenities platform and podium roof garden, and final approvals ahead of the April 2028 handover that the payment plan's closing instalment is tied to.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on SeaPoint at Emaar Beachfront's own record.
Buyer Position
Tracking Your Position at SeaPoint at Emaar Beachfront
This page is one of four project resources that together cover a SeaPoint at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

SeaPoint at Emaar Beachfront Construction Updates
This page: the verified inspection record for SeaPoint at Emaar Beachfront, groundbreaking to April 2028.

SeaPoint at Emaar Beachfront Golden Visa: All Six Tiers
All six tiers at SeaPoint at Emaar Beachfront, from 1 bedroom apartment to 6 bedroom penthouse, clear the threshold.
Read the SeaPoint at Emaar Beachfront Golden Visa Guide
SeaPoint at Emaar Beachfront Escrow: Emaar's First Abu Dhabi Bank Account
SeaPoint at Emaar Beachfront holds 674 units' payments at First Abu Dhabi Bank, DLD project 2633, certified 36.78% June 2026.
Verify the SeaPoint at Emaar Beachfront Escrow AccountApproaching Handover
Between 36.78% and Handover: What SeaPoint at Emaar Beachfront Buyers Should Do Now
At 36.78% on 24 June 2026 the live question on this project is not handover but milestones. The SeaPoint payment plan releases instalments against certified construction completion, with 10% falling due at 40%, 10% at 60%, 10% at 80% and the closing 10% at 100%, so the figure on this page is what puts your next call for payment in motion. The 40% threshold is the one immediately above the June 2026 reading, and calls for payment on milestone plans arrive with a short window to settle, so the three steps below belong now rather than when the notice lands.
First, map your remaining instalments against the certified thresholds rather than the calendar months printed beside them; the SeaPoint escrow account page sets out how the First Abu Dhabi Bank escrow account releases funds against verified progress.
Second, follow the record instead of the marketing: the SeaPoint June 2026 inspection record carries the full site report behind the 36.78% figure, and every new reading is added to the timeline above.
Third, if your purchase may qualify for residency, settle eligibility now rather than at handover through the SeaPoint Golden Visa guide, since starting the check this early leaves room to correct documentation long before the title deed is issued.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar Beachfront Structure
A build record is only half the picture; the other half is what stands around it. These three pages put SeaPoint's progress in its community, market, and developer context:

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
SeaPoint at Emaar Beachfront Construction Updates Frequently Asked Questions
SeaPoint at Emaar Beachfront is an active DLD-registered project (number 2633) in its superstructure and envelope phase, recorded at 36.78% at the inspection of 24 June 2026. The full record is in the inspection timeline above.
The 24 June 2026 inspection recorded 36.78% construction progress, up 11.63 points from the previous register reading of 25.15%. The site report behind that figure is published in the June 2026 SeaPoint construction update.
Across the thirty three months from the 12 September 2023 construction start to the 24 June 2026 inspection, SeaPoint averaged about 1.1 percentage points per month to reach 36.78%. The register publishes the earlier 25.15% reading without a date, so the 11.63 point step between the two readings cannot be converted into a monthly rate. The full breakdown is in the pace analysis above.
Handover at SeaPoint at Emaar Beachfront is expected in April 2028, the month the final 10% instalment of the payment plan is tied to. At 36.78% on 24 June 2026 the project was still in its superstructure phase, and this page is updated each time a new inspection figure is recorded against project 2633.
Dubai Land Department registration records show 674 residential units, covering one, two, three and four bedroom apartments plus four and six bedroom penthouses, across a total built-up area of 84,733.14 sq m split between towers of 57 and 42 storeys.
Construction started on 12 September 2023, five months after project 2633 was registered with the Dubai Land Department on 16 April 2023. By the 24 June 2026 inspection the enabling, piling, foundation and substructure packages were all recorded as complete.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the SeaPoint at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.