Solaya Construction Updates
A Register Record Opening at Zero on the Jumeirah 1 Beachfront
Solaya by Meraas read 0% on the DLD register on 8 June 2026, a first baseline for two low-rise beachfront buildings on the Jumeirah 1 coast.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Solaya at a Glance
Solaya by Meraas is the Meraas release of Solaya 5 and Solaya 7, two low-rise buildings holding 55 residences on the Port De La Mer beachfront in Jumeirah 1, with handover estimated for Q2 2029. The Dubai Land Department registered it as project 4123 on 28 November 2025, and the record so far rests on a single dated reading: 0% on 8 June 2026. What sets this record apart is its order of events: the register entered 31 March 2026 as the construction start, yet the inspection 69 days later found demolition works still ongoing on the plot, so the register's start date comes before any building work on site.
4123
Active
31 March 2026
55 residential units
24,485.07 sq m
30 September 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Solaya Construction Update Timeline
The Solaya by Meraas record holds one dated entry so far: 0% on the DLD register on 8 June 2026, from an inspection that found demolition works ongoing and no construction activities started on Solaya 5 or Solaya 7. The register also lists a previous inspection at 0% with no date attached, so it is noted here rather than drawn as a dot or a row. The single dot on the track marks the June 2026 reading, and the table row opens its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 0% | 8 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Solaya Has Been Built
A measured pace needs two dated readings, and Solaya by Meraas has one. What the record supports today is a baseline, the gap from the registered start, and two pieces of arithmetic toward the completion dates:
- 8 June 2026: DLD register reading, the only dated figure on record0%
- Registered start, 31 March 2026, to the June 2026 reading69 days
- Arithmetic, not a forecast: 100 points over 1,210 days to the 30 September 2029 registered completion dateAbout 2.48 points per 30-day month
- Arithmetic, not a forecast: 100 points over 1,118 days to the end of Q2 2029, the estimated handoverAbout 2.68 points per 30-day month
No figure here measures how quickly Solaya 5 and Solaya 7 are being built, because on 8 June 2026 neither had left the ground: the inspection recorded demolition in progress. The two rates are simply the average climb the remaining 100 points would need to reach each date, set down now so that later readings have a yardstick, not a projection of when either building will finish. The first reading taken after construction activities begin will be the first entry on this page that can carry a measured pace. For an end user, that is the number that starts to test the Q2 2029 estimate; for an investor, it is the first evidence of how quickly work on this beachfront plot gets moving once demolition is cleared.
Get the Next Inspection Figure First
Tell me you are tracking Solaya and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Solaya at Port De La Mer
A 0% reading says little until you know what the two buildings will hold. The full project guide covers the residences this record is tracking toward:

Solaya by Meraas: Two Beachfront Buildings at Port De La Mer
Solaya by Meraas covers two low-rise beachfront buildings at Port De La Mer, with 55 residences around a Beach Park.
View the Solaya Project GuideConsidering a Pre-Construction Entry?
Availability at Solaya by Meraas is listed as Available. If the record on this page is what brought you here, ask me what is open across Solaya 5 and Solaya 7 before the first construction reading is published.
Ask About Remaining Availability on WhatsAppStage Record
Solaya Build Stages, Mapped to the Inspections
Only the first two stages below carry dates in the Solaya by Meraas record; the other three are listed in the order the 8 June 2026 inspection leaves ahead of the site, and each will gain its inspection window as readings arrive.
Registration and Registered Start
Project 4123 entered the DLD register as Solaya (5,7) on 28 November 2025, and the register dated the start of construction for both buildings 31 March 2026.
Site Clearance and Demolition
The 8 June 2026 inspection found demolition works ongoing and no construction activities started, with the DLD register reading 0% on that date.
Basement and Foundations
Both configurations on the inspection report begin with a basement level, so below-ground works are the first stage a later reading can show.
Structure of Solaya 5 and Solaya 7
The frames rise to B+G+R+7 for Solaya 5 and B+G+R+8 for Solaya 7, the second building carrying one more upper floor.
Finishing, Beachfront Landscaping, and Handover
Not yet recorded. The estimated handover is Q2 2029; the DLD register dates registered completion one quarter later, at 30 September 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Solaya's own record.
Buyer Position
Tracking Your Position at Solaya
This page is one of four project resources that together cover a Solaya purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Solaya Construction Updates
This page: the dated DLD register record for Solaya 5 and 7, from 0% to handover.

Solaya by Meraas Golden Visa: Two Low-Rise Beachfront Buildings
Meraas's Solaya holds 55 freehold residences at Port De La Mer in Jumeirah 1, and all five residence types qualify individually.
Read the Solaya Golden Visa Guide
Solaya by Meraas: The Port De La Mer Escrow Account
Meraas's Solaya is DLD project 4123, 55 units in Commercial Bank of Dubai escrow, 0% certified June 2026.
Verify the Solaya Escrow AccountApproaching Handover
Between 0% and Handover: What Solaya Buyers Should Do Now
At the 0% reading of 8 June 2026 there is no structure to inspect at Solaya 5 or Solaya 7, which moves the buyer's attention from the site to the paperwork and the payment trail. Meraas dates its instalments by calendar rather than by construction stage, so the next due date arrives whether or not the register has moved, and the three steps below belong before it, not after.
First, confirm that every instalment is going to the account registered for project 4123; the Solaya by Meraas escrow account page sets out how to check it against the DLD record before any transfer.
Second, if residency is part of your plan, settle eligibility early through the Solaya by Meraas Golden Visa eligibility guide, since the paperwork available before handover differs from what the title deed later provides.
Third, follow the register from this baseline: the first reading after construction activities begin is the one that starts to test the Q2 2029 estimate, and it will be added to the inspection timeline with its own monthly update.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Port De La Mer Structure
Solaya 5 and Solaya 7 are two buildings on a longer stretch of the Jumeirah 1 coastline. These three pages put a 0% baseline in its market, shoreline, and developer context:

Port de La Mer: Beachfront Apartments in Solaya and Solaya 8
Port de La Mer is the Meraas beachfront community in Jumeirah 1, with apartments for sale in Solaya and Solaya 8.
See Port De La Mer Properties for Sale
Port de La Mer: A Mediterranean-Inspired Marina Island by Meraas in Jumeirah
Port de La Mer has 24 low-rise freehold buildings around a marina, with private beach access and promenade dining.
Explore the Port De La Mer Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Solaya Construction Updates Frequently Asked Questions
Solaya by Meraas read 0% on the DLD project register on 8 June 2026, under active project 4123, which the register names Solaya (5,7). The inspection that day logged demolition works as ongoing, with no construction activity begun on either building, which places the project at its pre-construction baseline. The full record is in the inspection timeline above.
One dated reading is on record for Solaya by Meraas: 0% on the DLD register on 8 June 2026. An earlier 0% sits in the register's previous inspection slot without any date, so no point change can be calculated between the two; the dated reading is covered in the Solaya by Meraas June 2026 construction update.
Handover at Solaya by Meraas is estimated for Q2 2029, while the registered completion date for project 4123 on the DLD register falls one quarter later, on 30 September 2029. Neither date had passed when the 0% reading of 8 June 2026 was taken, and this page's record is updated as each new reading is recorded.
Solaya by Meraas comprises 55 residences in two buildings, which the RERA inspection report of 8 June 2026 lists as Solaya 5: B+G+R+7 and Solaya 7: B+G+R+8. Both configurations sit on the same DLD project, 4123, and share the single 0% register reading of that date.
Solaya by Meraas carries 31 March 2026 as its registered construction start, about four months after project 4123 was registered on 28 November 2025. The first dated reading, 0% on 8 June 2026, followed 69 days after that registered start, at an inspection that still found demolition works ongoing.
Progress at Solaya by Meraas is taken from the Dubai Land Department project register for project 4123, which shows a percentage against each dated inspection; the RERA report of 8 June 2026 lists its own Progress Status as N/A, so the 0% on this page is the register figure. Each new reading joins the timeline with its own monthly update, and the general method is set out on the Dubai Construction Updates hub.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Solaya construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.