Sunset Bay 5 by Imtiaz in Island A, Dubai Islands construction updates cover image featuring two architectural project renderings of the residential tower and ground-level entrance in Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Island A, Dubai Islands

Sunset Bay 5 Construction Updates

Tracking a Single G+2P+8+R Building on Island A, Reading by Reading

Sunset Bay 5 reached 44.53% in the DLD register on 5 October 2026, nearing halfway within sixteen months of breaking ground on Island A in June 2025.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

44.53%Construction Progress
5 October 2026Latest RERA Inspection
62 residencesTotal Units
Project 3811DLD Registration

Construction Snapshot

Sunset Bay 5 at a Glance

Sunset Bay 5 by Imtiaz is one G+2P+8+R residential building holding 62 residences on Island A at Dubai Islands, entered in the Dubai Land Department register as project 3811. The register gives a construction start of 15 June 2025, a registration date of 4 July 2025 and a registered completion date of 15 October 2027. Between those anchors the record so far holds just two readings: 44.53% dated 5 October 2026, and an earlier 32.62% that the register shows without a date. That short, partly undated history is the baseline every later Sunset Bay 5 reading on this page will be measured against.

DLD Project Number

3811

Project Status

Active

Construction Start

15 June 2025

Total Units

62 residences

Total Built-Up Area

7,466.17 sq m

Registered Completion Date

15 October 2027 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Sunset Bay 5 Construction Update Timeline

The Sunset Bay 5 record opens with a pair of register readings, and only one of them is dated. The 44.53% of 5 October 2026 is the single row in the table below and links its full October 2026 update. The previous reading of 32.62% sits on the track as an undated marker, because the register prints it without a date; the two figures are 11.91 points apart, but without the earlier date that gap cannot be turned into a monthly rate. From the next dated reading onward, each one adds a dot to the track and a row to the table.

Inspection MonthConstruction ProgressInspection DateFull Update
October 202644.53%5 October 2026View the October 2026 update

Pace Analysis

How Fast Sunset Bay 5 Has Been Built

With only one dated reading, Sunset Bay 5 has no inspection-to-inspection pace to measure yet. The register's own anchors still support two figures, set out below as arithmetic, not a forecast:

  • 15 Jun 2025 to 5 Oct 2026: whole-build average since the registered start, 0% to 44.53% over 477 daysAbout 2.80 points per month
  • 5 Oct 2026 to 15 Oct 2027: average needed from 44.53% to 100% by the registered completion date, 375 daysAbout 4.44 points per month

The two numbers describe different stretches of the same building. The 2.80 average covers about sixteen months that took the plot from enabling works through piling and foundations to a structure the RERA report of 5 October 2026 places at an advanced stage. The 4.44 figure is what the remaining 55.47 points would need to average across the 375 days to 15 October 2027, a faster rate than the record shows so far. That difference is arithmetic, not a verdict: the same report already has MEP, internal works, the external envelope and internal finishes progressing alongside the frame, and handover remains scheduled for Q4 2027. For an end user, the figure to watch is the next dated reading, which gives Sunset Bay 5 its first measured pace; for an investor, it is whether the readings that follow track toward the 4.44 line.

Get the Next Inspection Figure First

Tell me you are tracking Sunset Bay 5 and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Sunset Bay 5 at Island A

The register percentage is measuring progress toward a specific product: furnished apartments stacked above two podium parking levels and topped by a rooftop pool deck. The full project guide covers it:

Sunset Bay 5 by Imtiaz in Island A, Dubai Islands front elevation of a modern tiered residential tower with balconies, palms and landscaped entrance in Dubai - Presented by Tohid Fetrat

Sunset Bay 5, a G+2P+8+R Building on Dubai Islands

Sunset Bay 5 is an Imtiaz building of 62 fully furnished apartments with one to three bedrooms on Island A.

View the Sunset Bay 5 Project Guide

Considering a Mid-Construction Entry?

Limited units are available at Sunset Bay 5, and availability keeps shifting as the building moves toward its Q4 2027 handover. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Sunset Bay 5 Build Stages, Mapped to the Inspections

Each stage below is tied to what the Sunset Bay 5 record actually shows, from the 15 June 2025 start to the RERA report and 44.53% register reading of 5 October 2026, rather than to a generic building sequence.

From the 15 Jun 2025 start

Enabling Works on the Island A Plot

Site set-up and enabling works from the registered 15 June 2025 start, listed as completed in the RERA report of 5 October 2026.

Jun 2025 to Oct 2026 record

Piling and Foundations

Piling and foundation works beneath the single building, both recorded as completed by the 5 October 2026 report; the register does not date when each finished.

Current Phase44.53% on 5 Oct 2026

Podium and Residential Frame

Structure works for the ground, two podium parking levels, eight residential floors and roof, at an advanced stage per the RERA report of 5 October 2026.

Running in parallel, Oct 2026 record

MEP, Envelope and Internal Works

Already progressing alongside the frame in the same 5 October 2026 report: MEP services, internal works, the external envelope and internal finishes.

Through the Q4 2027 handover

Furnishing, Rooftop and Delivery

Furnishing all 62 apartments, completing the rooftop pool deck and podium clubhouse, and final works ahead of the registered completion date of 15 October 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sunset Bay 5's own record.

Buyer Position

Tracking Your Position at Sunset Bay 5

This page is one of four project resources that together cover a Sunset Bay 5 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sunset Bay 5 by Imtiaz in Island A, Dubai Islands construction updates cover image featuring two architectural project renderings of the residential tower and ground-level entrance in Dubai - Presented by Tohid Fetrat
You Are Here

Sunset Bay 5 Construction Updates

This page: every dated DLD register reading for project 3811, from June 2025 to handover.

Sunset Bay 5 by Imtiaz in Island A, Dubai Islands Golden Visa card graphic over an aerial rendering of a rooftop swimming pool and surrounding buildings in Dubai - Presented by Tohid Fetrat

Sunset Bay 5 by Imtiaz Golden Visa: Even the Entry Apartment

Sunset Bay 5, Imtiaz's 62 apartments on Island A, starts every unit type above AED 2M, even the entry 1 bedroom.

Read the Sunset Bay 5 Golden Visa Guide
Sunset Bay 5 by Imtiaz in Island A, Dubai Islands escrow account concept graphic with shield and padlock symbols above a rooftop infinity pool in Dubai - Presented by Tohid Fetrat

Sunset Bay 5 Escrow: 62 Units, One First Abu Dhabi Bank Account

Imtiaz registered Sunset Bay 5 as DLD project 3811, 62 units held at First Abu Dhabi Bank, 44.53% certified October 2026.

Verify the Sunset Bay 5 Escrow Account

Approaching Handover

Between 44.53% and Handover: What Sunset Bay 5 Buyers Should Do Now

Payments at Sunset Bay 5 follow fixed dates in the 60/40 schedule, so no percentage on this page triggers an instalment by itself. When the register posted 44.53% on 5 October 2026, four instalments totalling 40% of the price had fallen due, and the 15 October 2026 instalment took that total to 50% ten days later. What remains is 10% dated 15 May 2027 and 40% on completion, so the useful window for the checks below is the months before May 2027, not the week a payment notice arrives.

First, before the 15 May 2027 transfer, confirm that the receiving account is the DLD-registered trust account for project 3811 at First Abu Dhabi Bank; the Sunset Bay 5 escrow account guide shows how to check it against the official record.

Second, if residency is part of your plan, read the Sunset Bay 5 Golden Visa eligibility guide now, while the building is still off plan; all three apartment types start above the AED 2M threshold at current prices.

Third, keep the product itself in view as the record moves: the Sunset Bay 5 by Imtiaz project guide holds the layouts, the furnishing specification and the full 60/40 schedule your remaining payments follow.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island A Structure

Sunset Bay 5 is one building on one Island A plot. These three pages place its construction record in the context of the island market, the community taking shape around it and the developer accountable for delivering it:

Aerial masterplan view of Island A properties for sale with waterfront residences, marinas, green spaces, and connected roadways in Dubai. Presented by Tohid Fetrat

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses

Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.

See Island A Properties for Sale
Aerial masterplan view highlighting Island A at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island A Community Overview

Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.

Explore the Island A Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Sunset Bay 5 Construction Updates Frequently Asked Questions

Sunset Bay 5 by Imtiaz is an active DLD-registered project (number 3811) at 44.53% in the register as of 5 October 2026, roughly sixteen months after its 15 June 2025 start and with handover scheduled for Q4 2027. The RERA report of the same date places the structure at an advanced stage. Every reading is laid out in the inspection timeline above.

Progress at Sunset Bay 5 is recorded as a percentage in the Dubai Land Department project register for project 3811, posted after RERA site inspections; the latest figure is 44.53% as of 5 October 2026. The RERA progress monitoring report of that date lists the works under way but carries no percentage figure, and the register's earlier 32.62% reading carries no date, so this page dates and charts only the 5 October 2026 figure.

The DLD register lists 15 October 2027 as the registered completion date for Sunset Bay 5, and that date falls inside the Q4 2027 handover quarter, so the two do not conflict. The registered date is the completion anchor held in the DLD register for project 3811, separate from the developer's handover schedule; it had not passed when the 44.53% reading of 5 October 2026 was posted, and this page's record is updated as later readings appear.

Sunset Bay 5 has 62 residences in one building configured as G+2P+8+R: a ground floor, two podium parking levels, eight residential floors and a roof level. At the 44.53% register reading of 5 October 2026, structure works on that frame were at an advanced stage; the Sunset Bay 5 apartment layouts are set out on the project page.

Sunset Bay 5 has averaged about 2.80 percentage points per month since its 15 June 2025 start, reaching 44.53% on 5 October 2026 after 477 days (arithmetic on a 30-day month, not a forecast). No measured pace between inspections exists yet, because the previous register reading of 32.62% is undated; the full working is in the pace analysis above.

From 44.53% on 5 October 2026, Sunset Bay 5 has 55.47 points left, which works out to about 4.44 points per month over the 375 days to its registered completion date of 15 October 2027. That figure is arithmetic, not a forecast or a delay signal: later phases run services, envelope and finishes side by side, and handover remains scheduled for Q4 2027.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sunset Bay 5 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status