Sunset Bay Grand by Imtiaz in Dubai Islands construction updates cover image featuring a project rendering of the residential building with layered balconies landscaped podium and surrounding streets in Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Dubai Islands

Sunset Bay Grand Construction Updates

The Dated Register Record of One Island A Building, From the Foundations Up

Sunset Bay Grand recorded 16.29% in the DLD register on 17 August 2026, an early reading for its Island A building, with foundations complete and structure rising.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

16.29%Construction Progress
17 August 2026Latest RERA Inspection
98 residential unitsTotal Units
Project 3868DLD Registration

Construction Snapshot

Sunset Bay Grand at a Glance

Sunset Bay Grand is the 98-home Imtiaz Developments address on Island A, Dubai Islands, registered with the Dubai Land Department as project 3868 on 30 September 2025 and started 15 days later, on 15 October 2025. Ten months into the build, the register read 16.29% on 17 August 2026, with handover expected in Q4 2027. Because the whole project is one building of ground, two podium levels, 10 residential floors and a roof level, every point on this record describes a single structure rather than an average across several towers.

DLD Project Number

3868

Project Status

Active

Construction Start

15 October 2025

Total Units

98 residential units

Total Built-Up Area

11,738.67 sq m

Registered Completion Date

15 February 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Sunset Bay Grand Construction Update Timeline

The Sunset Bay Grand record holds one dated reading so far: 16.29% on 17 August 2026, 306 days after the 15 October 2025 start. The register also carries a previous figure of 10.32% with no date beside it, so it sits on the track below as an unlabelled dot rather than a table row, and the 5.97-point step between the two cannot be spread across any number of months. The single row links the August 2026 monthly update, where that reading is examined in full.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202616.29%17 August 2026View the August 2026 update

Pace Analysis

How Fast Sunset Bay Grand Has Been Built

With a single dated reading, Sunset Bay Grand has no inspection-to-inspection velocity yet. What can be worked out is the average since the registered start and the rate implied by the distance still to cover, both arithmetic, not a forecast:

  • Oct 2025 to Aug 2026: start to first dated reading, 16.29 points over 306 days to 17 August 2026About 1.6 points per month
  • Aug 2026 to Feb 2028: the remaining 83.71 points spread across the 547 days to the 15 February 2028 registered completion dateAbout 4.6 points per month
  • Previous reading to Aug 2026: 10.32%, undated, to 16.29% on 17 August 2026, a 5.97-point stepNo dated span, no pace

Read together, these figures describe the opening of a record rather than a curve. The first 306 days carried Sunset Bay Grand through site activation, enabling works, piling and foundations, all listed as completed in the 17 August 2026 RERA report, while the structure itself was only recorded as progressing. The 4.6-point figure is simply the distance left divided by the days left to the registered completion date; it is not a projection and not a verdict on the Q4 2027 handover. Buyers should also know that the launch payment schedule put 30% of the price due by 17 August 2026, rising to 40% on 15 September 2026, while the register read 16.29%; that is arithmetic rather than a delay signal. For end users and investors alike, the next dated reading is the figure that matters: it will give this project its first measured pace, and until it lands the completion and delay clauses in each SPA remain the reference.

Get the Next Inspection Figure First

Tell me you are tracking Sunset Bay Grand and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Sunset Bay Grand at Island A

A register percentage only means something next to the building it measures. The full project guide covers the finished Sunset Bay Grand this record is tracking toward:

Night exterior view at Sunset Bay Grand by Imtiaz at Dubai Islands Presented by Tohid Fetrat

Sunset Bay Grand: Furnished Island A Apartments by Imtiaz

Sunset Bay Grand by Imtiaz holds 98 fully furnished apartments of one to three bedrooms over 10 floors on Dubai Islands.

View the Sunset Bay Grand Project Guide

Considering an Early-Stage Entry?

Availability at Sunset Bay Grand keeps shifting while the structure rises, and the choice of floors and views narrows as it does. If the record on this page is what brought you here, ask me for current availability before the next register reading lands.

Ask About Remaining Availability on WhatsApp

Stage Record

Sunset Bay Grand Build Stages, Mapped to the Inspections

Each stage below is pinned to the window it occupies in the Sunset Bay Grand record, from the 30 September 2025 registration to the one dated reading of 17 August 2026, so the early stages read as done and the later ones as still ahead of this single building.

Sep 2025 to Oct 2025

Registration and Site Mobilization

Registered as DLD project 3868 on 30 September 2025, with construction starting 15 days later on 15 October 2025; the August 2026 report still notes mobilization as ongoing.

Oct 2025 to Aug 2026

Enabling, Piling and Foundations

Enabling works, piling and foundations for the single building, all three recorded as completed in the RERA report dated 17 August 2026.

Current PhaseAug 2026, 16.29% at last reading

Podium and Residential Structure

Structure works were recorded as progressing at 16.29% on 17 August 2026, toward two podium levels, 10 residential floors and a roof level; the report names no level reached.

Not yet recorded

Envelope, Services and Amenity Levels

Facade, building services, the first-floor amenity deck and the rooftop sky pool follow the frame; none of this work appears in the 17 August 2026 report.

Toward Q4 2027

Furnishing, Completion and Handover

All 98 residences are to be handed over fully furnished, with handover expected in Q4 2027 and the 40% completion payment set for December 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sunset Bay Grand's own record.

Buyer Position

Tracking Your Position at Sunset Bay Grand

This page is one of four project resources that together cover a Sunset Bay Grand purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sunset Bay Grand by Imtiaz in Dubai Islands construction updates cover image featuring a project rendering of the residential building with layered balconies landscaped podium and surrounding streets in Dubai - Presented by Tohid Fetrat
You Are Here

Sunset Bay Grand Construction Updates

This page: the dated register history of Sunset Bay Grand, from registration to Q4 2027 handover.

Sunset Bay Grand by Imtiaz in Dubai Islands Golden Visa concept with a Golden Visa card beside a project rendering of the residential building and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Sunset Bay Grand Golden Visa: 98 Furnished Apartments

Every apartment type at Sunset Bay Grand, Imtiaz's single building on Island A, qualifies alone, so no second property is needed.

Read the Sunset Bay Grand Golden Visa Guide
Sunset Bay Grand by Imtiaz in Dubai Islands escrow account protection concept with shield and padlock icons above a project rendering of the residential building pool deck and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Sunset Bay Grand Escrow: Imtiaz's Island A Account

First Abu Dhabi Bank holds Sunset Bay Grand escrow for Imtiaz Developments, DLD project 3868, 98 units, 16.29% certified August 2026.

Verify the Sunset Bay Grand Escrow Account

Approaching Handover

Between 16.29% and Handover: What Sunset Bay Grand Buyers Should Do Now

At 16.29% on 17 August 2026, what a Sunset Bay Grand buyer can act on is the payment record, not the building. The instalments in the launch schedule carry fixed dates, and the next one is 10% on 15 December 2026, so the three checks below belong before that transfer, not after it.

First, confirm that every instalment goes only to the First Abu Dhabi Bank trust account registered for project 3868; the Sunset Bay Grand escrow account page shows how to check it against the DLD record.

Second, if residency is part of the plan, settle the application path early through the Sunset Bay Grand Golden Visa guide, since every layout is priced from AED 2.19M ≈ USD 596K and eligibility shapes how the purchase is structured.

Third, follow the dated record rather than the renderings: the Sunset Bay Grand August 2026 inspection page holds the only dated reading so far, and each new register figure joins the timeline above as it lands.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Island A Structure

A register reading describes one building; the three pages below place the Sunset Bay Grand foundations and rising frame within the Island A market, the island community around the plot and the Imtiaz portfolio:

Aerial masterplan view of Island A properties for sale with waterfront residences, marinas, green spaces, and connected roadways in Dubai. Presented by Tohid Fetrat

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses

Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.

See Island A Properties for Sale
Aerial masterplan view highlighting Island A at Dubai Islands in Dubai, Presented by Tohid Fetrat

Island A Community Overview

Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.

Explore the Island A Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Sunset Bay Grand Construction Updates Frequently Asked Questions

Sunset Bay Grand is an active DLD-registered project (number 3868) whose register reading stood at 16.29% on 17 August 2026, with the RERA report of that date showing enabling, piling and foundations finished and the structure under way. Every dated figure is laid out in the inspection timeline above.

The reading dated 17 August 2026 put Sunset Bay Grand at 16.29%, 5.97 points above the earlier register figure of 10.32%, which carries no date. That reading has its own page, the Sunset Bay Grand August 2026 construction update.

Handover for Sunset Bay Grand is expected in Q4 2027. For project 3868, the DLD project register separately lists 15 February 2028 as the registered completion date, printed here exactly as recorded. At the 17 August 2026 reading of 16.29%, 83.71 points remained to 100%, and this page adds each new register reading as it is recorded.

Sunset Bay Grand holds 98 residential units, the figure shown for project 3868 in the DLD register, all in one building and every home delivered fully furnished in one, two and three bedroom layouts. Floor plans and sizes are in the Sunset Bay Grand by Imtiaz overview.

With only one dated reading, Sunset Bay Grand has no measured pace between inspections yet. As arithmetic, not a forecast, 16.29 points in the 306 days between the 15 October 2025 start and 17 August 2026 comes to roughly 1.6 points for each 30-day month, while covering the remaining 83.71 points by the registered completion date of 15 February 2028, 547 days later, would take roughly 4.6 points a month. The workings are in the pace analysis above.

Construction at Sunset Bay Grand started on 15 October 2025, 15 days after the project was registered with the Dubai Land Department on 30 September 2025. The first dated register reading, 16.29%, followed 306 days after the start, on 17 August 2026.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sunset Bay Grand construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status