Sunset Bay by Imtiaz Construction Update - August 2026

August 2026 Inspection Places Sunset Bay by Imtiaz at 78.04% in the DLD Register

Internal works, external envelope, MEP and internal finishes were progressing at Sunset Bay when RERA inspected on 4 August 2026, with the DLD register reading 78.04 percent.

Direct advisor access. Every message answered personally, never by a call center.

78.04%DLD Register Progress
4 August 2026Inspection Date
Q4 2026Expected Completion
3460DLD Project Number

Verified DLD Register Data

Sunset Bay by Imtiaz Construction Snapshot

A 13.61 point rise over the previous register reading of 64.43%, a reading the register shows without a date, places Sunset Bay in the finishing band, where the 40% completion payment and the handover inspection become the decisions that matter.

Project Name

Sunset Bay by Imtiaz

Project Number

3460

Project Status

Active

Construction Progress

78.04%

Inspection Date

4 August 2026

Construction Start

25 December 2024

Total Units

66 residences

Total Built Area

7,853.92 sq m

Expected Completion

Q4 2026

Data source: RERA Independent Progress Monitoring Report for the inspection of 4 August 2026, read with the DLD project register reading posted for the same date; the report itself prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering of the planned rooftop amenity deck, not a site photograph. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Sunset Bay by Imtiaz Construction Progress Summary

On 4 August 2026 the RERA report recorded enabling, piling, foundation and structure works as completed on the G+2P+8+R building, while internal works, the external envelope, MEP and internal finishes were still progressing, with the report's progress status reading Main Contract, Progressing. The distance left to handover now sits in the envelope, services and finishes of the 66 residences rather than in the building's frame.

Completed
  • Enabling works on the Island A plot
  • Piling and foundation works
  • Structure works across the ground, both podium levels, all eight residential floors and the roof
In Progress at 78.04%
  • Internal works inside the building
  • External envelope works
  • MEP systems: mechanical, electrical and plumbing
  • Internal finishes across the 66 residences
Ahead of Handover
  • Further DLD register readings toward 100%
  • The developer's completion notice and the 40% completion payment
  • Handover expected in Q4 2026, against a registered completion date of 25 December 2026
Next inspectionPosted to the DLD project register after the next RERA site visit; no date for it appears in the August 2026 record, and a newer reading may already be live.
Completion targetQ4 2026 handover per the developer; the register lists 25 December 2026 as the registered completion date, 143 days after this inspection.
Remaining distance21.96 percentage points separate the 4 August 2026 reading from 100%.
Pace arithmeticArithmetic, not a forecast: 78.04 points over the 587 days since the 25 December 2024 start averages about 3.99 points per month (30-day month), while reaching 100% by the registered completion date implies about 4.61 points per month over the remaining 143 days.

Payments and Progress

What 78.04% Progress Means for Sunset Bay Buyers

Sunset Bay's 60/40 plan runs on calendar dates rather than construction milestones: by the 4 August 2026 reading every dated instalment, 60% of the price, had fallen due against 78.04% registered progress, leaving 40% payable on completion. At this stage of Sunset Bay, four actions matter most.

Before the Completion Payment

Verify the escrow account

The 40% due on completion should go only to the DLD regulated escrow account for project 3460 at First Abu Dhabi Bank, listed in the register as Sunset Bay One By Imtiaz. Sunset Bay by Imtiaz escrow account verification is the step before that transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Reread your SPA completion clauses

Check how your sale and purchase agreement defines completion, the handover notice period and the trigger for the 40% payment, then map those clauses against the Q4 2026 handover and the 25 December 2026 registered completion date. Not sure how your remaining payment maps to this reading? Send me your SPA schedule and I will map it against the register milestones.

Window Open Now

Book the snagging window

At 78.04%, and with Q4 2026 set for handover, Sunset Bay sits inside the usual booking window for a pre handover inspection, and fully furnished units add the custom furniture to the checklist. Sunset Bay by Imtiaz snagging inspection guide covers the timing before acceptance.

Every Cycle

Track the remaining readings

21.96 points remained after the August 2026 reading, so each new register figure shows how quickly the finishing works are closing. Sunset Bay by Imtiaz construction updates hub logs every reading as it posts.

General framework, not legal advice: completion definitions, notice periods, and payment obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 78.04%?

Entering Sunset Bay this late trades the instalment runway for visibility: the structure is recorded complete, the handover window is short, and because the plan is date-based the instalments already due are settled at signing, per the developer's current terms. Every payment goes to the DLD-registered escrow account for project 3460, released against verified construction progress.

Entering Now at 78.04%
  • Structure works recorded complete in the 4 August 2026 RERA report
  • Handover expected in Q4 2026, months rather than years away
  • Dated instalments settled at signing; 40% due on completion
Typical Launch Entry
  • Construction risk carried from the first excavation to handover
  • A multi-year wait is the usual off plan delivery horizon
  • Instalments spread across the build, priced at launch levels
AED 1.69M ≈ USD 460KStarting Price
60/40 Plan40% Due on Completion
Q4 2026Expected Handover
Ask What Is Available at Sunset Bay

Limited units available per the project page as of this update; availability shifts between cycles.

About the Development

Sunset Bay by Imtiaz Project Details

Sunset Bay by Imtiaz in Island A at Dubai Islands residential building exterior with curved balconies, planted terraces, and a waterfront view beyond the surrounding buildings in Dubai - Presented by Tohid Fetrat
Island A · Imtiaz Developments

With structure works recorded complete in the August 2026 RERA report, Sunset Bay is a finishing stage development holding 66 fully furnished homes on Island A: 1 and 2 bedroom apartments plus 3 bedroom duplexes. Starting prices: AED 1.69M ≈ USD 460K.

For a buyer entering at this stage, the trade off is a short wait against paying most of the price up front, with the 40% balance due on completion and handover expected in Q4 2026.

Sunset Bay by Imtiaz Project Guide

Site Context This Cycle

Explore Sunset Bay Location on Dubai Map

Sunset Bay is a single compact building on Island A, about a 5 minute walk from the beach according to the developer's brochure, and its low G+2P+8+R profile shapes this cycle's works: with eight residential floors over two podium levels, the envelope, MEP and finishing packages recorded as progressing on 4 August 2026 are spread across a short building rather than stacked up a tall tower core.

Island A is still being built out around the project, so Sunset Bay is finishing into a growing waterfront district rather than a settled one; Infinity Bridge, about 5 minutes away by car per the developer's fact sheet, already ties the island to Deira and the airport side of the city. For buyers planning to occupy or let from Q4 2026, how much of the wider Dubai Islands master development is open at handover matters as much as the building itself. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Sunset Bay by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Sunset Bay During Its Finishing Stage

At 78.04%, residency eligibility, the escrow route for the final 40%, and the handover inspection are the questions that follow this reading. Each resource below is matched to where Sunset Bay stands in August 2026.

Sunset Bay by Imtiaz in Island A at Dubai Islands construction updates cover image featuring project renderings of the residential building with layered balconies, podium frontage, and palm landscaping in Dubai - Presented by Tohid Fetrat
You Are Here

Sunset Bay by Imtiaz Construction Updates

This page: the 4 August 2026 register reading and RERA report notes for Sunset Bay.

Sunset Bay by Imtiaz in Island A at Dubai Islands Golden Visa card graphic above a project rendering of the rooftop pool and landscaped amenity deck in Dubai - Presented by Tohid Fetrat

Sunset Bay by Imtiaz Golden Visa: 2 and 3 Bedroom Residences

Imtiaz's Sunset Bay, 66 furnished residences on Island A, qualifies with its 2 bedroom apartments and 3 bedroom duplexes only.

Read the Sunset Bay by Imtiaz Golden Visa Guide
Sunset Bay by Imtiaz in Island A at Dubai Islands escrow account protection graphic with shield and padlock icons above an aerial project rendering of the landscaped podium and terraces in Dubai - Presented by Tohid Fetrat

Sunset Bay by Imtiaz: The Island A Escrow Account

Sunset Bay by Imtiaz Developments is DLD project 3460, 66 units escrowed at First Abu Dhabi Bank, 78.04% certified August 2026.

Verify the Sunset Bay by Imtiaz Escrow Account
Sunset Bay by Imtiaz in Island A at Dubai Islands snagging inspection concept showing a bedroom interior with marble wall panels, full height glazing, a sea view, and a snagging graphic in Dubai - Presented by Tohid Fetrat

Sunset Bay Snagging for Furnished Homes on Island A

Sunset Bay by Imtiaz is a building on Island A at Dubai Islands, 66 residences from apartments to 3 bedroom duplexes.

Book a Sunset Bay by Imtiaz Snagging Inspection

Update Timeline

Other Sunset Bay by Imtiaz Construction Updates

August 2026 opens the monthly record for Sunset Bay on this site; each later register reading is added to the hub as it posts, so the run toward the Q4 2026 handover can be followed reading by reading.

All Sunset Bay by Imtiaz Construction Updates

FAQs

Sunset Bay by Imtiaz Construction Progress in August 2026: Frequently Asked Questions

As of the inspection dated 4 August 2026, the Dubai Land Department project register shows Sunset Bay by Imtiaz, project 3460, at 78.04% construction progress with a project status of Active. The RERA report for the same date prints no percentage of its own, so 78.04% is the register's reading rather than a figure from the report.

The register's inspection card dated 4 August 2026 lists 64.43% as the previous inspection and 78.04% as current progress. The register gives no date for the 64.43% reading, so the gap between the two shows direction only and cannot be converted into a monthly pace for Sunset Bay.

No change appears in the August 2026 record: the developer's expected handover remains Q4 2026, and the register still lists 25 December 2026 as the registered completion date, 143 days after the 4 August 2026 inspection. Registered dates can be revised between cycles and any revision would show in a later reading; how readings and completion dates relate is covered on the Sunset Bay by Imtiaz construction updates hub.

The Independent Progress Monitoring Report for 4 August 2026 describes a G+2P+8+R residential building with a concrete structure and blockwork, and records enabling, piling, foundation and structure works as completed. Internal works, the external envelope, MEP and internal finishes were progressing, and the report's progress status reads Main Contract, Progressing. The report also carries inspection photographs as part of the official record.

As of the August 2026 record, the register shows construction started on 25 December 2024 and the project registered on 17 January 2025, 23 days later. Both dates are reproduced here exactly as recorded, and the 78.04% reading of 4 August 2026 came 587 days after the recorded start.

No. The hero image is a developer rendering of the planned rooftop pool, landscaped amenity deck and leisure areas, used to illustrate this update; it does not show the building as it stood on 4 August 2026. The RERA report for that date carries its own inspection photographs, which stay with the official record.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Sunset Bay correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts