
Imtiaz · Dubai Land Residence Complex
The Archive Construction Updates
The Dated Register Record for a Library-Led Residence in Dubailand
The Archive by Imtiaz read 2.96% on the DLD register on 29 June 2026, an enabling-works figure that opens the dated record for its two-wing Dubailand residence.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
The Archive at a Glance
The Archive by Imtiaz is a 310-residence apartment building in Dubai Land Residence Complex that the developer's floor plans lay out as two connected wings around a podium pool deck, with handover targeted by Imtiaz for Q3 2028. Its register record is still short: a construction start of 01 October 2025, project registration on 02 March 2026, and one dated reading, 2.96% on 29 June 2026, taken while the plot was in enabling works. The cards below are the DLD anchors every later reading on this page will be measured from.
3781
Active
01 October 2025
310 residential units
16,874.77 sq m
30 December 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
The Archive Construction Update Timeline
One dated figure makes up this record so far: 2.96%, entered on the DLD register on 29 June 2026, the same day RERA's progress report found enabling works progressing on the Archive plot. The register's inspection card also lists a previous value of 0% with no date, which the track below shows as an unlabelled baseline at its left edge rather than as a reading, and the single table row links the June 2026 update where both are read in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 2.96% | 29 June 2026 | View the June 2026 update |
Pace Analysis
How Fast The Archive Has Been Built
With a single dated reading and an undated 0% baseline, The Archive has no inspection-to-inspection pace yet. What the register dates do support is two averages, both arithmetic, not a forecast:
- 01 Oct 2025 to 29 Jun 2026: enabling works, registered start to 2.96% over 271 daysAbout 0.33 points per month
- 29 Jun 2026 to 30 Dec 2028: the remaining 97.04 points to the registered completion date over 915 daysAbout 3.18 points per month
There is no curve to read yet, and that is the finding. A figure of 2.96% at 29 June 2026, 271 days after the registered start, belongs to a plot still in enabling works, where register readings move only a little before main building works begin, so a low whole-build average is normal at this stage. The 3.18 figure is simply what the remaining 97.04 points would average to reach 100% by the 30 December 2028 registered completion date (arithmetic, not a forecast); Imtiaz targets handover in Q3 2028, earlier than that register date, which serves as the regulatory completion deadline. For an end user, the next dated readings show when work moves past enabling; for an investor, the span between two dated readings will give The Archive its first measured pace.
Get the Next Inspection Figure First
Tell me you are tracking The Archive and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About The Archive at Dubai Land Residence Complex
A 2.96% register figure dated 29 June 2026 only means something next to the building it measures. The project guide covers the residences, library and rooftop that this record is tracking toward:

The Archive by Imtiaz: A Reading-Led Building in Dubailand
The Archive by Imtiaz is a building of 310 apartments built around reading, from a two-storey library to a rooftop salon.
View the The Archive Project GuideConsidering an Early-Stage Entry?
Availability at The Archive shifts from one register cycle to the next while the plot is still in enabling works. If this record is what brought you here, ask me what is open today and how an entry now lines up with the developer's dated plan, starting with the 5% due on 15 November 2026.
Ask About Remaining Availability on WhatsAppStage Record
The Archive Build Stages, Mapped to the Inspections
Only the first two stages below carry register evidence for The Archive: the recorded start of 01 October 2025 and the enabling works reading of 2.96% on 29 June 2026. The three after them are the stages the coming readings will fill in, each left undated until a register entry records it.
Construction Start on the Register
The register gives 01 October 2025 as the construction start for project 3781, with DLD registration following on 02 March 2026, both as recorded.
Enabling Works Recorded
The RERA progress report of 29 June 2026 records enabling works progressing on the plot, and the register reads 2.96% the same day, the only dated figure so far.
Main Building Works
The two connected residential wings and the podium pool deck in the developer's floor plans are what the next register readings will begin to measure.
Facade, Fit-Out, and Amenity Levels
Envelope, apartment interiors, and the amenity spaces the developer describes, from the ground-level garden and library to the rooftop pools.
Finishing, Commissioning, and Handover
Closing readings toward 100%, measured against Imtiaz's Q3 2028 handover target and the registered completion date of 30 December 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Archive's own record.
Buyer Position
Tracking Your Position at The Archive
This page is one of four project resources that together cover a The Archive purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Archive Construction Updates
This page: the dated DLD register record for The Archive, from enabling works to handover.

The Archive by Imtiaz Golden Visa: A Reading-Led Apartment
No apartment at The Archive, Imtiaz's 310 residences in Dubai Land Residence Complex, reaches AED 2M; the 3 bedroom comes closest.
Read the The Archive Golden Visa Guide
The Archive by Imtiaz: The Dubai Land Residence Complex Escrow
Imtiaz's The Archive, DLD project 3781, escrows 310 units at Abu Dhabi Commercial Bank, certified 2.96% in June 2026.
Verify the The Archive Escrow AccountApproaching Handover
Between 2.96% and Handover: What The Archive Buyers Should Do Now
At 2.96% on 29 June 2026 the Archive plot was still in enabling works, and the developer's primary plan asks for money on dates rather than on construction stages: 20% at booking, then the next 5% on 15 November 2026 and 30% more across six dated instalments to 1 July 2028 before 50% on completion. That calendar, not the site, sets the timing here, so the three steps below belong before the 15 November 2026 instalment, not after it.
First, confirm that every instalment goes to the escrow account registered for project 3781 with Abu Dhabi Commercial Bank; The Archive by Imtiaz escrow account page sets out how to check it against the DLD record before you transfer.
Second, if UAE residency is part of the plan, settle it before you commit: every listed home type is priced below AED 2M ≈ USD 545K, and The Archive by Imtiaz Golden Visa threshold guide explains what that means for a single unit and which other routes exist.
Third, read The Archive by Imtiaz layouts and payment plan against your own dates; the developer publishes its instalment dates as indicative, so check that your SPA fixes each one and plan your budget around that schedule rather than the pace of the site.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Land Residence Complex Structure
A register reading is only half the picture; the other half is the district it is taken in. These three pages place The Archive's enabling-works record in its Dubailand community, market, and developer context:

Dubai Land Residence Complex: Nine Imtiaz Apartment Projects in Dubailand
Dubai Land Residence Complex, Dubai Holding's freehold community, lists nine Imtiaz apartment projects with 50/50, 60/40 and post-handover plans.
See Dubai Land Residence Complex Properties for Sale
Dubai Land Residence Complex: Dubailand's Established Apartment Community
Dubai Land Residence Complex has 49 occupied buildings, 140 open retail outlets and four community parks, with new towers rising.
Explore the Dubai Land Residence Complex Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
The Archive Construction Updates Frequently Asked Questions
The Archive by Imtiaz, DLD project 3781, is an active project at the enabling works stage, with a DLD register reading of 2.96% dated 29 June 2026. The RERA progress report of the same date lists its status as Enabling Works, Progressing, and the dated record is laid out in the inspection timeline above.
The latest dated reading for The Archive is 2.96% on 29 June 2026, a move of 2.96 points from a previous value of 0% that the register shows without a date, so no time span or monthly pace can be attached to that change. The register entry and the RERA report notes for that day are read in full in the The Archive by Imtiaz June 2026 construction update.
Imtiaz targets handover of The Archive in Q3 2028, while the DLD register carries a registered completion date of 30 December 2028 for project 3781. The register date sits after the developer's target and works as the regulatory completion deadline rather than a forecast; with the record at 2.96% on 29 June 2026, neither date has yet been measured against main building works, and this page's record is updated as each new reading is entered.
The Archive by Imtiaz holds 310 residences, studio to three bedroom apartments, which the developer's floor plans arrange in two connected residential wings around a podium pool deck. The 29 June 2026 register reading of 2.96% covers enabling works on that plot only; layouts, sizes and the amenity floors are set out in the The Archive by Imtiaz project guide.
The DLD register records construction at The Archive as starting on 01 October 2025, with project registration dated 02 March 2026, both exactly as recorded. From that start to the registered completion date of 30 December 2028 the window runs 1,186 days, roughly 39 months, and the first dated reading, 2.96% on 29 June 2026, arrived 271 days into it.
Counted from the 01 October 2025 start, the 2.96% recorded on 29 June 2026 averages about 0.33 points per month over 271 days, arithmetic rather than a forecast, and a low whole-build average is normal while a site is in enabling works. Reaching 100% by the 30 December 2028 registered completion date would take the remaining 97.04 points at about 3.18 points per month over 915 days, as set out in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Archive construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.