Meraas · Dubai Design District
The Edit at d3 Construction Updates
Three Canal-Front Towers on Plot 448, Recorded From the Zero Baseline
The Edit at d3 read 0.24% in the DLD register on 19 August 2026: a first move off zero, marking enabling works at the three-tower canal plot.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
The Edit at d3 at a Glance
The Edit at d3 is Meraas's three-tower address of 557 residences on plot 448, on the Dubai Canal edge of Dubai Design District. Its record opens before the build itself: the first RERA inspection on file, dated 29 October 2025, predates both the 06 November 2025 DLD registration and the 10 January 2026 registered start, and the register only moved off 0% with the 0.24% recorded for 19 August 2026. The cards below are the register anchors every later reading on this page will be measured against.
4177
Active
10 January 2026 (DLD)
557 residential units
71,465.43 sq m
31 January 2030 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
The Edit at d3 Construction Update Timeline
Three RERA inspections are on file for The Edit at d3, and the DLD register reads 0% for the first two and 0.24% for the third: 29 October 2025, the most recent RERA inspection on record for December 2025 and carried by that month's update, then 01 June 2026 and 19 August 2026. All three dots sit within a quarter of a point of the left edge, so the track below is almost empty by design at this stage. The register does not date its own Previous Inspection figures, so these are the readings on file rather than a complete inspection log; each table row links that period's full update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 0.24% | 19 August 2026 | View the August 2026 update |
| June 2026 | 0% | 01 June 2026 | View the June 2026 update |
| December 2025 | 0% | 29 October 2025 | View the December 2025 update |
Pace Analysis
How Fast The Edit at d3 Has Been Built
Three readings on file give The Edit at d3 two measurable intervals so far, plus the average the rest of the build would need. Each figure below is derived arithmetic from the DLD register readings and their dates, not a forecast:
- Oct 2025 to Jun 2026 readings on file: pre-construction, 0% to 0%About 0.0 points per month
- Jun 2026 to Aug 2026 readings on file: enabling works, 0% to 0.24%About 0.1 points per month
- Aug 2026 to the 31 Jan 2030 registered completion date: 0.24% to 100%About 2.4 points per month needed
So far the curve is a flat line with a single upturn at its end. For roughly seven months between the 29 October 2025 and 01 June 2026 readings the register held at 0%, and the 10 January 2026 registered start fell inside that stretch without showing on site: the 01 June 2026 report still found no construction activities. The first movement, 0.24 points by 19 August 2026, arrived with the first report on file to note enabling works progressing, so that interval measures site preparation on plot 448 rather than building. What matters from here is the gap between the roughly 0.1 points a month recorded and the 2.4 a month implied by the 31 January 2030 registered completion date, or about 2.2 a month measured to the June 2030 anticipated handover. For an end user, the next readings show whether excavation for three basement levels under each tower starts to close that gap; for an investor, they show whether the calendar-dated instalments running to May 2028 are moving ahead of the site or alongside it.
Get the Next Inspection Figure First
Tell me you are tracking The Edit at d3 and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About The Edit at d3 at Dubai Design District
A 0.24% reading only means something against what is being delivered. The full project guide covers what The Edit at d3 buyers at this enabling works stage are committing to:

The Edit at d3: Three Meraas Towers on the Dubai Canal
The Edit at d3 holds 557 Meraas residences in three towers, from one bedroom apartments to five bedroom penthouses.
View the The Edit at d3 Project GuideConsidering an Early-Stage Entry?
The Edit at d3 is listed as a new launch, and availability across its five layouts shifts over time while the site is still in enabling works. If the record on this page is what brought you here, ask me for current availability before settling on a layout.
Ask About Remaining Availability on WhatsAppStage Record
The Edit at d3 Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it occupies in The Edit at d3's own record: the two stages already on file carry their inspection dates and register readings, and the three still ahead carry the tower data they will be measured against.
Registration and Baseline
The 29 October 2025 inspection found no construction activity and a progress status of N/A, with the register at 0%; project 4177 was registered on 06 November 2025.
Site Activation and Enabling Works
Registered start 10 January 2026. No construction activities were found on 01 June 2026 at 0%; enabling works were progressing on 19 August 2026, at 0.24%.
Excavation and Three-Level Basements
Excavation and basement structure for three levels beneath each of Towers A, B and C on the canal-front plot 448.
Tower Structure to 30, 37 and 33 Floors
Cores and floor plates rising above ground level for Tower A with 182 units, Tower B with 177 and Tower C with 198.
Facades, Sky Gardens, and Handover
Facades, the sky garden levels, finishing and commissioning, measured against the 31 January 2030 registered completion date and the June 2030 anticipated handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Edit at d3's own record.
Buyer Position
Tracking Your Position at The Edit at d3
This page is one of four project resources that together cover a The Edit at d3 purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Edit at d3 Construction Updates
This page: The Edit at d3 readings on file, up to 0.24% on 19 August 2026.

The Edit at d3 Golden Visa: Five Unit Types, All Qualifying
Meraas's The Edit at d3, a three-tower 557-unit project on the Dubai Canal edge, qualifies at all five unit types.
Read the The Edit at d3 Golden Visa Guide
The Edit at d3 Escrow: Meraas's Design District Account
The Edit at d3, Meraas's DLD project 4177, holds 557 units in Abu Dhabi Islamic Bank escrow, 0.24% certified August 2026.
Verify the The Edit at d3 Escrow AccountApproaching Handover
Between 0.24% and Handover: What The Edit at d3 Buyers Should Do Now
At 0.24% on 19 August 2026, what stands between The Edit at d3 and visible structure is excavation for three basement levels under each tower, yet the launch payment plan of record runs on calendar dates, not site stages. Its 5% second instalment is dated October 2026, within weeks of this page's September 2026 update, so the three steps below belong before that transfer, not after the next reading.
First, confirm that each payment goes only to the DLD-registered escrow account for project 4177 at Abu Dhabi Islamic Bank; The Edit at d3 escrow account check shows how to match it against the official record before you transfer.
Second, set the dates still ahead in your SPA, 5% in October 2026, 10% in March 2027, three further 10% instalments to May 2028 and 25% on handover, beside the readings in the inspection timeline, so you can see how far the site has moved each time money leaves your account.
Third, if residency is part of the plan, settle eligibility early through The Edit at d3 Golden Visa eligibility guide, since the entry tier sits at AED 2.00M ≈ USD 545K and the route for an off-plan unit differs from a completed one.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Design District Structure
A 0.24% build record is half the picture; the other half is the district it is rising into. These three pages set The Edit at d3's plot 448 build against the d3 market, the community, and Meraas:

Dubai Design District: d3 Apartments and Penthouses by Meraas and Select Group
Dubai Design District has 3 projects of apartments and penthouses for sale along Dubai Creek, minutes from Downtown Dubai and DIFC.
See Dubai Design District Properties for Sale
Dubai Design District Community Overview
Read the Dubai Design District (d3) guide: Meraas' design-led waterfront district with freehold residences and creative spaces.
Explore the Dubai Design District Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
The Edit at d3 Construction Updates Frequently Asked Questions
The Edit at d3, DLD project 4177, is an active project in its enabling works stage: the RERA inspection report dated 19 August 2026 lists its progress status as Enabling Works - Progressing, and the DLD project register reads 0.24% for that inspection. All three readings on file are set out in the inspection timeline above.
The DLD project register reads 0% for the inspection of 29 October 2025, 0% for 01 June 2026 and 0.24% for 19 August 2026, so the latest figure sits 0.24 points above the previous reading on file. The register does not date its own Previous Inspection figure, so these three are the readings on file rather than a complete log of every RERA visit.
The DLD project register carries 31 January 2030 as the registered completion date for project 4177, while the handover anticipated for buyers is June 2030, so the register's date is the earlier of the two. Neither date had passed when the register recorded 0.24% for the 19 August 2026 inspection, and this page reports both exactly as recorded, updating them if a later cycle revises either one.
The RERA inspection reports on file describe 557 residential units in three towers: Tower A at 3B+G+30 with 182 units, Tower B at 3B+G+37 with 177 units and Tower C at 3B+G+33 with 198 units, ranging from 1 bedroom apartments to 5 bedroom penthouses. The 557 total matches the DLD project register, which recorded 0.24% for the whole project on 19 August 2026.
Between the readings on file for 29 October 2025 and 01 June 2026 the DLD register showed no change at 0%, and from 01 June 2026 to 19 August 2026 it rose 0.24 points in about two and a half months, roughly 0.1 points a month. As derived arithmetic rather than a forecast, the remaining 99.76 points would need an average of about 2.4 points a month to reach the 31 January 2030 registered completion date, or about 2.2 to reach the June 2030 anticipated handover; the pace analysis above breaks down each interval.
No structure is on record yet at The Edit at d3: the RERA report dated 01 June 2026 found that no construction activities had started, and the report dated 19 August 2026 records enabling works progressing at the site, with the DLD register at 0.24% for that inspection. Excavation for three basement levels under each tower, and the towers themselves at 30, 37 and 33 floors above ground, are still ahead.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Edit at d3 construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.