Emaar · Dubai Hills Estate · Construction Update

Vida Residences Hillside Construction Update - May 2026

May 2026 Inspection Confirms Vida Residences Hillside Reaches 10% Construction Progress in Dubai Hills Estate

Enabling, piling, foundation, and early structure works dominate site activity at Vida Residences Hillside, verified at 10 percent in the May 2026 RERA inspection cycle.

Direct advisor access. Every message answered personally, never by a call center.

10%Construction Progress
04 May 2026Inspection Date
Q2 2029Expected Completion
3534DLD Project Number

Verified DLD Inspection Data

Vida Residences Hillside Construction Snapshot

A 4.99 point rise from the previously recorded 5.01% puts Vida Residences Hillside firmly in the enabling and foundations band, the stage where escrow discipline and payment plan structure decide more than site photographs do.

Project Name

Vida Residences Hillside by Emaar

Project Number

3534

Project Status

Active

Construction Progress

10%

Inspection Date

04 May 2026

Construction Start

30 June 2025

Total Units

500 residential units

Total Built Area

49,683.63 sq m

Expected Completion

Q2 2029

Data source: RERA inspection conducted on 04 May 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Vida Residences Hillside Construction Progress Summary

Between the previously recorded 5.01% and the inspection carried out on 04 May 2026, Vida Residences Hillside moved to 10%, a gain earned below ground level rather than in visible height. RERA records the main contract as progressing, with enabling, piling, foundation, and structure packages all active on plot 5413 at the time of the site visit.

Completed
  • Project registration recorded on 11 February 2025
  • Construction start recorded on 30 June 2025
  • Trust account opened with Emirates Islamic Bank for project 3534
In Progress at 10%
  • Enabling works across plot 5413 in Dubai Hills Estate
  • Piling beneath the two tower footprints
  • Foundation works and the shared basement level
  • First structure works on the podium (1B+G+1P+1F+R)
Ahead of Handover
  • Vertical structure for Tower A (G+20F+R) and Tower B (G+19F+R)
  • Facade, MEP, and interior fit out across 500 homes
  • Remaining RERA inspection cycles toward 100%
  • Handover from the Q2 2029 window
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion targetQ2 2029 as the current handover window, roughly three years beyond this inspection date.
Remaining distance90 percentage points separate the May 2026 reading from handover readiness.

Payment Linked Progress

What 10% Progress Means for Vida Residences Hillside Buyers

Dubai off plan payment plans tie instalments to calendar dates, to certified construction milestones, or to both, so a verified reading of 10% is not just a status line: it tells you which obligations are still ahead of you. At this stage of Vida Residences Hillside, four actions matter most.

Before Every Instalment

Verify the escrow account

Every payment ahead of handover should go only to the DLD regulated escrow account registered for project 3534, recorded with Emirates Islamic Bank. Vida Residences Hillside escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Milestone Payment

Reread your SPA milestone schedule

Four instalments on the published plan are tied to 60%, 80%, 90%, and 100% construction completion, and at 10% none of them has been triggered yet. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Early in the Payment Plan

Confirm your Oqood registration

Off plan purchases in Dubai are recorded on the interim property register before title is issued at completion. Confirm that the registration exists in your name against the DLD record for project 3534, and keep the receipt filed with your sale and purchase agreement.

Every Cycle

Track the remaining cycles

Around 90 points of certified progress separate this reading from completion, across several more inspection cycles. Vida Residences Hillside construction updates hub keeps a build this long free of surprises.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 10%?

Entering at the foundations stage trades certainty for runway: the construction risk is still ahead, but so is the entire payment schedule, and the choice of layouts is at its widest. Every payment goes to the DLD-registered escrow account for project 3534, released against certified construction progress.

Entering Now at 10%
  • Full runway: 80% spread across instalments running to 2029
  • Launch pricing on record from AED 1.82M ≈ USD 495K
  • Widest choice of layouts across two towers and the townhouse row
Entering Near Completion
  • Structure certified, but most of the balance falls due within months
  • Shorter wait, at whatever the market has done in the interim
  • Choice limited to whichever units remain unsold
AED 1.82M ≈ USD 495KStarting Price
80/20 Plan20% Due on Completion
From Q2 2029Expected Handover

9 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Vida Residences Hillside Project Details

Vida Residences Hillside by Emaar in Dubai Hills Estate residential building exterior with tiered balconies and landscaped grounds in Dubai - Presented by Tohid Fetrat
Dubai Hills Estate · Emaar

With piling and foundation works still the headline activity, Vida Residences Hillside is an early stage development of 500 homes: 1 to 3 bedroom apartments across two towers, plus a row of 3 bedroom townhouses. Starting prices: AED 1.82M ≈ USD 495K.

For buyers entering at this stage, the trade off is a long wait against the full length of the payment plan, with handover expected from Q2 2029.

Site Context This Cycle

Explore Vida Residences Hillside Location on Dubai Map

Vida Residences Hillside occupies plot 5413 in Hadaeq Sheikh Mohammed Bin Rashid, on the Dubai Hills Estate parcel that fronts Hillside Park, with the two towers set back behind a shared podium and a townhouse row along the northern edge. A single plot carrying three built forms is why this cycle reads as enabling, piling, foundation, and structure at once: the packages overlap across the site rather than following one another.

Because Dubai Hills Estate is an already delivered master community, with the mall, the park, the golf course, King's College Hospital, and school campuses in use, buyers here wait out construction beside working infrastructure rather than a future promise, which matters when the handover window sits three years out. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview

Buyer Resources for This Project

Investing in Vida Residences Hillside During Early Construction Progress

The foundations band is where payment protection and residency planning do the real work, long before there is anything to photograph. Each resource below is matched to where Vida Residences Hillside stands right now.

Vida Residences Hillside by Emaar in Dubai Hills Estate construction updates cover image featuring a project rendering of the residential tower overlooking a landscaped community park in Dubai - Presented by Tohid Fetrat
You Are Here

Vida Residences Hillside Construction Updates

This page: the verified May 2026 inspection record for Vida Residences Hillside, from enabling works onward.

Vida Residences Hillside by Emaar in Dubai Hills Estate Golden Visa eligibility concept with a Golden Visa card above a private balcony and landscaped community view in Dubai - Presented by Tohid Fetrat

Vida Residences Hillside at Dubai Hills Estate Golden Visa Around Hillside Park

Vida Residences Hillside at Dubai Hills Estate is two towers and a townhouse row; 2 bedroom apartments and above qualify individually.

Read Vida Residences Hillside Golden Visa Guide
Vida Residences Hillside by Emaar in Dubai Hills Estate escrow account protection concept with shield and padlock icons above the outdoor pool and landscaped surroundings in Dubai - Presented by Tohid Fetrat

Vida Residences Hillside at Dubai Hills Estate: Emirates Islamic Escrow

Vida Residences Hillside at Dubai Hills Estate, DLD project 3534, puts 500 units in Emirates Islamic escrow, 10% certified May 2026.

Verify Vida Residences Hillside Escrow Account

Update Timeline

Other Vida Residences Hillside Construction Updates

This is the first published reading in the series. Follow the timeline to see how Vida Residences Hillside moves from foundations toward handover, cycle by cycle.

All UpdatesVida Residences Hillside Construction Updates Hub
Next Update · One Message Per CycleGet notified the day it publishes
All Vida Residences Hillside Construction Updates

FAQs

Vida Residences Hillside Construction Progress in May 2026: Frequently Asked Questions

As of the RERA inspection conducted on 04 May 2026, Vida Residences Hillside stands at 10% construction progress in the DLD project register, with the main contract recorded as progressing.

The register moved from a previously recorded 5.01% to 10% at the 04 May 2026 inspection, a gain of 4.99 points. That gain sits almost entirely below ground: enabling, piling, and foundation packages carry long site durations for a modest share of certified contract value.

The 04 May 2026 progress report records enabling, piling, foundation, and structure works all progressing on plot 5413. The built form ahead is a shared podium of 1B+G+1P+1F+R, Tower A at G+20F+R, and Tower B at G+19F+R.

The current handover window is Q2 2029, roughly three years beyond the May 2026 reading. Expected completion dates in the DLD project register can be revised between inspection cycles, so the window shown here reflects the record as of May 2026; any revision would appear in a later update on this cluster.

The published plan ties four instalments to certified construction completion: 60%, 80%, 90%, and a final 20% instalment at 100%. At the 10% reading recorded on 04 May 2026 none of those four milestones has been reached, so the instalments still falling due are the date-linked ones. Your own sale and purchase agreement governs the exact wording.

The 04 May 2026 progress report records Emirates Islamic Bank P.J.S.C. as the trust account bank for project 3534, registered to developer Dubai Hills Estate L.L.C. under developer number 984. The account is confirmed against the DLD project record before any transfer is released.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Vida Residences Hillside at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts