Emaar Properties · Dubai Creek Harbour
ARLO at Dubai Creek Harbour Construction Updates
The Certified Build Record of a Canal-Edge Tower in Al Khairan First
ARLO at Dubai Creek Harbour reached 35.42% construction at its 03 June 2026 RERA inspection, a 9.43-point climb showing the canal-edge tower rising through overlapping work packages.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
ARLO at Dubai Creek Harbour at a Glance
ARLO at Dubai Creek Harbour is Emaar's 434-unit building on plot 182 in Al Khairan First, where a B+G+2P+48+Roof tower, as the RERA inspection report describes it, is paired with 3 bedroom townhouses on the canal edge. Nineteen months separate its 31 October 2024 construction start from the 35.42% certified on 03 June 2026, and the cards below are the registered anchors behind that record. One gap is worth knowing from the outset: the DLD register holds no completion date for project 3104, so every handover reference on this page uses the published Q4 2028 schedule.
3104
Active
31 October 2024
434 units
44,524.28 sq m
Q4 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
ARLO at Dubai Creek Harbour Construction Update Timeline
Two readings make up ARLO's record so far: a previous inspection at 25.99%, which the DLD app lists without a date, and the 35.42% certified on 03 June 2026, the first reading published in this series. The track below sets both against the October 2024 groundbreaking and the 100% handover mark, and the June 2026 row links the monthly update that carries the full inspection breakdown for project 3104.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 35.42% | 03 June 2026 | View the June 2026 update |
Pace Analysis
How Fast ARLO at Dubai Creek Harbour Has Been Built
ARLO's record holds a single dated reading, so its pace comes from arithmetic on fixed dates rather than from a pair of dated inspections. Three measures frame where the build stands:
- Oct 2024 to Jun 2026: groundbreaking to 35.42%, average since the 31 October 2024 startAbout 1.9 points per month
- Previous inspection to Jun 2026: superstructure, 25.99% to 35.42%9.43 points, interval undated
- Jun 2026 to end of Q4 2028: 35.42% to 100%, rate required on the published scheduleAbout 2.1 points per month
Neither monthly figure is a forecast. The 1.9 average spreads 35.42 points across the nineteen months since groundbreaking, a period that still includes the enabling, piling and substructure works the 03 June 2026 report lists as progressing; the 2.1 simply divides the remaining 64.58 points by the months left to 31 December 2028. The 9.43-point step from the previous reading cannot be turned into a monthly rate because the DLD app gives that inspection no date. The launch schedule offers a second yardstick: it pairs the 20% construction mark with April 2026 and the 40% mark with November 2026, and the June reading sits between the two, so record and calendar are in step. For an end user, the Q4 2028 handover still rests on readings yet to come; for an investor, the signal worth watching is the next certified figure and how it lands against that 40% mark.
Get the Next Inspection Figure First
Tell me you are tracking ARLO at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About ARLO at Dubai Creek Harbour
A 35.42% reading only matters against what is being delivered: 434 units split between apartments and canal-edge townhouses. The full project guide covers what buyers are tracking toward on this page:

ARLO at Dubai Creek Harbour: Canal-Front Homes with Rooftop Terraces
ARLO at Dubai Creek Harbour is a 434-unit Emaar building of apartments and townhouses with rooftop terraces over the canal.
View the ARLO at Dubai Creek Harbour Project GuideConsidering a Mid-Construction Entry?
Availability at ARLO is listed as limited as of this update, and it keeps shifting as the tower climbs toward its Q4 2028 handover. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
ARLO at Dubai Creek Harbour Build Stages, Mapped to the Inspections
ARLO's record has one feature that shapes this map: the 03 June 2026 RERA report lists every work package, from piling to internal finishes, as progressing at the same time, so the stages below overlap rather than follow in a clean line. Each is anchored to the dates and readings project 3104 actually holds, and the stages still ahead are pinned only to the construction marks on the launch schedule.
Registration and Site Mobilisation
DLD registered project 3104 on 28 May 2024, the month of the launch down payment, and construction formally started on 31 October 2024 on plot 182.
Enabling, Piling, and Substructure
Enabling, piling, foundation and substructure works began after the 31 October 2024 start and were still recorded as progressing on 03 June 2026.
Superstructure of the B+G+2P+48+Roof Tower
The frame is where the record sits now: up from the undated 25.99% reading to 35.42% on 03 June 2026, past the 20% construction mark paired with April 2026.
Envelope, MEP, and Fit-Out
Already under way in the June 2026 report, which lists external envelope, MEP and internal finishes as progressing; the launch schedule pairs 60%, 80% and 90% with June 2027, December 2027 and April 2028.
Completion and Handover
The final 10% instalment is tied to 100% construction completion in October 2028 and handover is scheduled for Q4 2028; the DLD register held no completion date as of 03 June 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on ARLO at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at ARLO at Dubai Creek Harbour
This page is one of four project resources that together cover a ARLO at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

ARLO at Dubai Creek Harbour Construction Updates
This page: the RERA record for ARLO, from 31 October 2024 groundbreaking to Q4 2028 handover.

ARLO at Dubai Creek Harbour Golden Visa on the Canal Edge
Three of four unit types at ARLO at Dubai Creek Harbour qualify, from 2 bedroom apartment; freehold title for every nationality.
Read the ARLO at Dubai Creek Harbour Golden Visa Guide
ARLO at Dubai Creek Harbour Escrow: Following the Creek Payments
ARLO at Dubai Creek Harbour pays Emirates Islamic escrow as DLD project 3104, its 434 units 35.42% certified June 2026.
Verify the ARLO at Dubai Creek Harbour Escrow AccountApproaching Handover
Between 35.42% and Handover: What ARLO at Dubai Creek Harbour Buyers Should Do Now
From the 35.42% certified on 03 June 2026, ARLO's remaining 64.58 points will be recorded reading by reading, and five of the six construction-linked instalments on its launch schedule, the 40% through 100% marks, still lie ahead. At this point the useful work for a buyer is on the payment side, not handover preparation. The nearest of those marks, 40% paired with a November 2026 date, sits 4.58 points above the June reading, so the three steps below are worth settling before that instalment falls due rather than after.
First, confirm that every remaining instalment is paid into the project 3104 escrow account held with Emirates Islamic Bank; the ARLO escrow account page explains how releases follow certified construction milestones.
Second, keep your sale and purchase agreement open beside the inspection timeline on this page, because the clause defining each construction-linked payment, not the percentage alone, decides when the 40% instalment is actually due.
Third, follow each new reading as it is added rather than site talk: the ARLO June 2026 inspection breakdown is the baseline the next certified figure will be measured against.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
ARLO's 35.42% is one reading in a district where several Emaar buildings are rising at once. These three pages put the tower's progress in its market, community, and developer context:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
ARLO at Dubai Creek Harbour Construction Updates Frequently Asked Questions
ARLO at Dubai Creek Harbour is an active DLD-registered project (number 3104) in its superstructure phase, certified at 35.42% at the RERA inspection of 03 June 2026 with a progress status of Main Contract - Progressing. The full record is in the inspection timeline above.
The 03 June 2026 inspection recorded 35.42% construction progress at ARLO, up 9.43 points from the previous reading of 25.99%, an earlier inspection the DLD app shows without a date. The work packages and figures behind that reading are set out in the ARLO June 2026 construction update.
Measured from the 31 October 2024 construction start, ARLO has averaged about 1.9 percentage points per month to reach 35.42% on 03 June 2026. Reaching 100% by the end of Q4 2028 works out to about 2.1 points per month from that reading. Both figures are arithmetic on the record rather than a forecast, and no monthly rate can be taken from the undated previous inspection. The working is in the pace analysis above.
Handover for ARLO at Dubai Creek Harbour is scheduled for Q4 2028, while the DLD register held no completion date for project 3104 at the 03 June 2026 reading of 35.42%. The launch payment schedule ties its final 10% instalment to 100% construction completion in October 2028, and this page's record is updated as each new inspection is recorded.
DLD registration records list 434 units for ARLO at Dubai Creek Harbour, project 3104, in a building the RERA inspection report of 03 June 2026 describes as B+G+2P+48+Roof. The mix runs from 1 bedroom apartments of 705 to 829 sq ft (66 to 77 sq m) to 3 bedroom townhouses of 3,263 to 3,276 sq ft (303 to 304 sq m).
Construction at ARLO officially started on 31 October 2024, five months after the project was registered with the DLD on 28 May 2024. The first dated reading tracked on this page is the 35.42% certified on 03 June 2026, nineteen months after the start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the ARLO at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.