Art Bay West by Ellington in Al Jaddaf construction updates cover image featuring a project rendering of residential buildings with landscaped grounds in Dubai - Presented by Tohid Fetrat

Ellington · Al Jaddaf

Art Bay West Construction Updates

The Register Record of a G+10+R Al Jaddaf Build, from Its First Dated Reading

Art Bay West stood at 9.11% on the DLD register on 12 May 2026, opening this record with a G+10+R Al Jaddaf build at foundation level.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

9.11%Construction Progress
12 May 2026Latest RERA Inspection
173 unitsTotal Units
Project 2996DLD Registration

Construction Snapshot

Art Bay West at a Glance

Art Bay West is Ellington's 167-residence building in Al Jaddaf, registered with the Dubai Land Department as project 2996 and described in the RERA inspection report as G+10+R. The register dates the construction start to 12 March 2024 and the registration to 06 June 2024, and the only dated reading so far, 9.11% on 12 May 2026, sits 26 months after that start, so this record opens with a single point rather than a curve.

DLD Project Number

2996

Project Status

Active

Construction Start

12 March 2024

Total Units

173 units

Total Built-Up Area

21,750.95 sq m

Registered Completion Date

Q3 2026 (developer handover)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Art Bay West Construction Update Timeline

Two figures make up the Art Bay West record so far: a previous DLD register reading of 7.76%, which the register card shows without a date, and the current 9.11%, recorded on 12 May 2026 beside a RERA report of enabling works at an advanced stage and foundation works progressing. Only the dated reading earns a row in the table below; the earlier figure sits on the track as an unlabelled dot, and the May 2026 row opens the full update.

Inspection MonthConstruction ProgressInspection DateFull Update
May 20269.11%12 May 2026View the May 2026 update

Pace Analysis

How Fast Art Bay West Has Been Built

With one dated reading, the Art Bay West pace can only be read as a whole-build average from the registered start; the undated earlier figure gives a direction but no interval:

  • 12 Mar 2024 to 12 May 2026: construction start to 9.11%, over 791 daysAbout 0.35 points per month
  • Previous DLD register reading of 7.76%: inspection date not shown on the register cardInterval not measurable

Spread across the 791 days since the 12 March 2024 start, the 9.11% reading averages about 0.35 points per month when counted in 30-day months; that is arithmetic, not a forecast. The RERA report of 12 May 2026 shows where those months went, with enabling works at an advanced stage and foundation works progressing, so the average describes groundwork on a G+10+R plot and says little about the rate once the building rises above foundation level. A single dated point cannot show acceleration or taper; the next dated reading will turn it into a measurable interval. For an end user weighing a move-in date, and for an investor timing an entry, the practical step is the same now that the original Q3 2026 handover schedule has passed: confirm the current expected handover date with Ellington in writing and check the completion date in your SPA.

Get the Next Inspection Figure First

Tell me you are tracking Art Bay West and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Art Bay West at Al Jaddaf

A foundation-stage percentage says little without the building it leads to. The project guide sets out what the Art Bay West record is counting toward:

Art Bay West by Ellington in Al Jaddaf project rendering of mid rise residential buildings beside a waterfront promenade at dusk in Dubai - Presented by Tohid Fetrat

Art Bay West: Theatre Room and Youth Hub in Dubai Culture Village

Art Bay West holds 167 studio to 3 bedroom apartments under a rooftop Arts Club for workshops and performances.

View the Art Bay West Project Guide

Considering an Early-Stage Entry?

At 9.11% on the register, an Art Bay West purchase today leaves most of the build, and most of the plan, still ahead. Availability moves as the record does, so ask me what is open now before you compare apartment types and floors.

Ask About Remaining Availability on WhatsApp

Stage Record

Art Bay West Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Art Bay West record actually holds: the 12 March 2024 start, the 06 June 2024 registration and the 12 May 2026 report. Stages the record has not reached carry no dates, because none have been recorded for them.

Mar 2024 to May 2026

Site Activation and Enabling Works

From the 12 March 2024 construction start and the 06 June 2024 registration to the 12 May 2026 report, which lists enabling works at an advanced stage.

Current Phase12 May 2026, 9.11% on the register

Foundations

The RERA report of 12 May 2026 records foundation works progressing at the site, the furthest point of the G+10+R build documented in this record.

Not yet recorded

Building Above Foundation Level

No work above foundation level appears in the 12 May 2026 report; the next dated readings will show when this stage of the G+10+R building opens.

Not yet recorded

Envelope, Interiors and Building Services

Facade, interior and services works are absent from the record at 9.11%; their window will be mapped here from the inspection dates that cover them.

Original Schedule Q3 2026 (passed)

Completion and Handover

Art Bay West was originally scheduled for handover in Q3 2026, and that quarter has passed; the closing 30% payment of the plan falls due on completion, so confirm the current expected handover date with Ellington in writing and check it against your SPA.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Art Bay West's own record.

Buyer Position

Tracking Your Position at Art Bay West

This page is one of four project resources that together cover a Art Bay West purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Art Bay West by Ellington in Al Jaddaf construction updates cover image featuring a project rendering of residential buildings with landscaped grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Art Bay West Construction Updates

This page: the dated DLD register record for Art Bay West, from 9.11% in May 2026.

Art Bay West by Ellington in Al Jaddaf Golden Visa concept graphic with a gold card above a rendered landscaped residential entrance in Dubai - Presented by Tohid Fetrat

Art Bay West Golden Visa: Two of Four Apartment Types Qualify

At Ellington's Art Bay West, two of four apartment types, 2 and 3 bedroom tiers, start above the Golden Visa threshold.

Read the Art Bay West Golden Visa Guide
Art Bay West by Ellington in Al Jaddaf escrow account concept graphic with a shield and padlock above a rendered residential building exterior in Dubai - Presented by Tohid Fetrat

Art Bay West Escrow Account: Ring-Fenced for 173 Al Jaddaf Units

Art Bay West's 173 registered units pay into DLD project 2996's trust account at Commercial Bank of Dubai, certified at 9.11%.

Verify the Art Bay West Escrow Account

Approaching Handover

Between 9.11% and Handover: What Art Bay West Buyers Should Do Now

At the 12 May 2026 reading of 9.11%, none of the four construction-linked instalments in the Art Bay West 70/30 plan had been triggered, since the first falls due on completion of 30% construction. Calendar dates, not site progress, set the timing of the plan's first five instalments: together 50% of the price, they fall due within 240 days of the reservation date each buyer signs, so the three steps below belong before those transfers rather than after the next reading.

First, check that each transfer goes to the DLD-registered escrow account at Commercial Bank of Dubai; the Art Bay West escrow account page shows how to match it to project 2996.

Second, if residency is part of the plan, settle eligibility early through the Art Bay West Golden Visa eligibility guide, since only the 2 and 3 bedroom tiers are priced above the property threshold.

Third, follow each dated reading as it reaches the register, starting from the 12 May 2026 Art Bay West inspection record, and, because the original Q3 2026 handover schedule has passed, hold the current handover date Ellington confirms in writing against the completion date in your SPA.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Al Jaddaf Structure

A foundation-stage record reads differently beside the streets already finished around it. These three pages set the Art Bay West reading of 9.11% in its market, community and developer context:

View of Al Jaddaf properties for sale in Dubai showing waterfront residences, palm lined walkways and canal side living, Presented by Tohid Fetrat

Al Jaddaf: Binghatti Wraith and Amazonia Apartments on the Creek

Al Jaddaf, the creekside district on the Bur Dubai bank, lists apartments in Binghatti Wraith and Amazonia on 60/40 payment plans.

See Al Jaddaf Properties for Sale
View of Al Jaddaf community in Dubai showing modern waterfront residences, landscaped walkways and canal side surroundings, Presented by Tohid Fetrat

Al Jaddaf: A Creek-Side District With Two Green Line Metro Stations

Al Jaddaf sits on the Bur Dubai bank of the Creek, home to Jaddaf Waterfront and a growing branded-residence pipeline.

Explore the Al Jaddaf Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Art Bay West Construction Updates Frequently Asked Questions

Art Bay West, DLD project 2996, is an active project at an early stage of construction, recorded at 9.11% on the DLD register on 12 May 2026, 1.35 points above a previous register reading of 7.76% whose date the register card does not show. The RERA report of the same date describes enabling works at an advanced stage and foundation works progressing; the full record is in the Art Bay West inspection timeline above.

Art Bay West was originally scheduled for handover in Q3 2026, and that quarter has passed. This page sets no revised date: the way to confirm the current expected handover date is in writing from Ellington, read against the completion date in your own sale and purchase agreement. The most recent dated figure on this page is the 9.11% DLD register reading of 12 May 2026, taken while foundation works were progressing, and this page's record is updated as each new inspection is recorded.

The RERA inspection report of 12 May 2026 describes Art Bay West as a G+10+R building, and the project holds 167 residences, studio to 3 bedroom apartments. Sizes and starting prices for each apartment type are set out in the Art Bay West project guide.

The DLD register records the Art Bay West construction start as 12 March 2024 and the project registration as 06 June 2024. The first dated reading in this record, 9.11% on 12 May 2026, is documented in the Art Bay West May 2026 construction update.

Art Bay West has averaged about 0.35 percentage points per month, measured from the 12 March 2024 start to the 9.11% DLD register reading of 12 May 2026, a span of 791 days counted in 30-day months; that figure is arithmetic, not a forecast. The register's earlier 7.76% reading carries no date, so no pace between the two readings can be measured; the working is set out in the Art Bay West pace analysis above.

Art Bay West progress is tracked through two official records for project 2996: the DLD register, which publishes percentage readings such as 9.11% on 12 May 2026, and the RERA inspection report, which records the stage of works in words rather than as a figure. Each dated reading joins the table on this page with its date, and the method applied to every project on the site is explained on the Dubai Construction Updates hub.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Art Bay West construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status