Select Group · Dubai Design District (d3)
Artistry Two Residences Construction Updates
The Build Record of One 37-Storey Tower in d3, From Its First Reading
Artistry Two Residences recorded 0% on 14 January 2026, the zero point against which every later reading of this 37-storey d3 tower will be judged.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Artistry Two Residences at a Glance
Artistry Two Residences is Select Group's 235-residence address in Dubai Design District (d3), entered in the DLD register as project 4261 on plot 464, Zaabeel Second. Its record opens before the build does: the only reading, 0% on 14 January 2026, was logged a day before the 15 January 2026 registration and 26 days before the 09 February 2026 registered start, so the anchors below describe a project fixed on paper rather than a working site. Everything that follows has to lift one 37-storey building from that line to the 09 February 2029 registered completion.
4261
Active
09 February 2026 (registered)
235 residential units
31,454.73 sq m
09 February 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Artistry Two Residences Construction Update Timeline
The record for project 4261 holds one entry so far: 0% in the DLD register on 14 January 2026, logged the day before the 15 January 2026 registration and 26 days ahead of the 09 February 2026 registered start. That single dot sits at the far left of the track below, and the first reading taken after the registered start will add the second point this record needs before it can show a direction. The table row links the full January 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| January 2026 | 0% | 14 January 2026 | View the January 2026 update |
Pace Analysis
How Fast Artistry Two Residences Has Been Built
A single reading cannot produce a velocity, so this section keeps what the Artistry Two Residences record measures apart from what it only implies. Until a second reading is published, the figures below are arithmetic against the registered dates, not a recorded pace:
- 14 Jan 2026 to 09 Feb 2029: required average, 0% to 100% over 1,122 daysAbout 2.7 points per month needed
- Measured pace between inspections: one reading on record, 0% on 14 Jan 2026Not yet measurable
There is no curve to read yet, only an opening point and a registered finish 1,122 days apart. The reading to watch is the first one logged after the 09 February 2026 registered start: set against the 0% baseline of 14 January 2026, it gives Artistry Two Residences its first measured velocity, and putting that figure beside the 2.7-point requirement shows whether the tower is opening ahead of or behind an even schedule. For an end user planning a Q1 2029 move, the useful signal is whether readings keep arriving on a steady cadence; for an investor, whose 50% pre-handover payments are complete 18 months after reservation whatever the percentage says, it is whether the measured pace settles near that requirement once the structure starts to climb.
Get the Next Inspection Figure First
Tell me you are tracking Artistry Two Residences and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Artistry Two Residences at Dubai Design District
A 0% reading from 14 January 2026 only makes sense next to what the build is meant to deliver. The project guide covers the finished tower this record is tracking toward:

Artistry Two Residences, a 37-Storey Select Group Tower in d3
Artistry Two Residences is a single Select Group tower of 235 units in Dubai Design District, with amenities on three levels.
View the Artistry Two Residences Project GuideConsidering an Entry Before the Foundations?
Units at Artistry Two Residences are released from the developer's inventory, and the choice of layouts and stacks narrows as reservations build up through the construction period. If this record is what brought you here, ask me what is still open before the first post-start reading is published.
Ask About Remaining Availability on WhatsAppStage Record
Artistry Two Residences Build Stages, Mapped to the Inspections
Only the first of the five stages below has an inspection attached so far. The other four are placed inside the registered window between the 09 February 2026 start and the 09 February 2029 registered completion, and each gains its own dates and percentages as Artistry Two Residences readings are published.
Registration and Baseline Reading
The 14 January 2026 RERA visit to plot 464 found no works under way, the DLD register logged 0%, and project 4261 was registered on 15 January 2026, ahead of the 09 February 2026 registered start.
Site Mobilisation and Foundations
Site set-up and foundation works belong to this window, which opens at the registered start; no published reading falls inside it yet.
Superstructure to 37 Storeys
The core and floor plates rising to 155.4 meters, carrying residences on levels 2 to 33 and six duplex penthouses on levels 34 to 37.
Facade, Services, and Amenity Levels
Envelope and building services, then the fitted amenity decks: the horizon pool on level 1, and the lap pool, gym and thermal spa on level 22.
Finishing, Commissioning, and Handover
Apartment finishing and final approvals ahead of the 09 February 2029 registered completion and the expected Q1 2029 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Artistry Two Residences's own record.
Buyer Position
Tracking Your Position at Artistry Two Residences
This page is one of four project resources that together cover a Artistry Two Residences purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Artistry Two Residences Construction Updates
This page: the DLD record for Artistry Two Residences, from its January 2026 baseline to handover.

Artistry Two Residences Golden Visa Through Any Apartment or Penthouse
Select Group's Artistry Two Residences, a 37-storey tower of 235 residences in d3, qualifies at all four unit types.
Read the Artistry Two Residences Golden Visa Guide
Artistry Two Residences: The Second Artistry Escrow at Emirates NBD
Artistry Two Residences, Select Group's DLD project 4261, escrows 235 units at Emirates NBD, 0% certified January 2026.
Verify the Artistry Two Residences Escrow AccountApproaching Handover
Between 0% and Handover: What Artistry Two Residences Buyers Should Do Now
At the 0% reading of 14 January 2026 nothing on site yet shows how the build will go, but your instalment clock starts the day you reserve: Artistry Two Residences dates every payment from reservation, so the first 20% and the 4% DLD registration fee are due within 14 days of reserving and half the price is settled by month 18, whatever the record says by then. That is why the three checks below belong before the first transfer, not after the first floors appear.
First, make sure your 20% instalment is payable only to the account registered to project 4261; the escrow protection details for Artistry Two Residences show how to check the trust account held with Emirates NBD before you transfer anything.
Second, if residency is part of the plan, read the Golden Visa rules for an Artistry Two Residences purchase now; every unit tier starts at AED 2.21M ≈ USD 602K or above, and the guide sets out how an off-plan unit at that level is assessed before handover.
Third, follow the record rather than the calendar: the first reading after the 09 February 2026 registered start is the one that turns this page's arithmetic into a measured pace, and it is added to the inspection timeline above once it is issued.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Design District Structure
A build record is only half the picture; the other half is the district filling in around plot 464. These three pages set the Artistry Two Residences record against its market, its community, and its developer:

Dubai Design District: d3 Apartments and Penthouses by Meraas and Select Group
Dubai Design District has 3 projects of apartments and penthouses for sale along Dubai Creek, minutes from Downtown Dubai and DIFC.
See Dubai Design District Properties for Sale
Dubai Design District Community Overview
Read the Dubai Design District (d3) guide: Meraas' design-led waterfront district with freehold residences and creative spaces.
Explore the Dubai Design District Community
Select Group: Premium Waterfront Residences From Marina Gate to Peninsula
Select Group delivers waterfront developments in Palm Jumeirah, Business Bay and Dubai Marina: founded in 2002, with over 7,000 units delivered.
View the Select Group Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Artistry Two Residences Construction Updates Frequently Asked Questions
Artistry Two Residences is an active DLD-registered project (number 4261) at its baseline stage, recorded at 0% on 14 January 2026, the single reading in its record so far. Its registered construction start of 09 February 2026 came after that reading, and no post-start figure has been published yet; the inspection timeline above carries the full record.
One. The DLD register logged 0% for Artistry Two Residences on 14 January 2026, and with no earlier reading there is no point change to report. The RERA findings from that visit are set out in the January 2026 Artistry Two Residences construction update.
The DLD register gives 09 February 2026 as the registered construction start for Artistry Two Residences. The first tracked reading, 0% on 14 January 2026, came 26 days before that start and one day before the 15 January 2026 registration, so it captures plot 464 ahead of any scheduled works.
As of the 14 January 2026 inspection, nothing: the RERA report for plot 464 records no construction activity under way, and the DLD register reading for that date is 0%. No later reading has been published, so the record does not yet show which works followed the 09 February 2026 registered start.
The DLD register lists 09 February 2029 as the registered completion date for project 4261, per the register entry current at the 14 January 2026 reading, while the expected handover for Artistry Two Residences sits in Q1 2029, the same quarter. The registered date has not passed, and this page's record is updated if a later reading or register change moves it.
Artistry Two Residences is registered with 235 residential units in a single 37-storey tower rising to 155.4 meters, combining 1, 2 and 3 bedroom apartments with 4 bedroom duplex penthouses on the top floors. Layouts for each type are in the Artistry Two Residences project overview.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Artistry Two Residences construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.